Professional Documents
Culture Documents
INTRODUCTION
The economics of generation of electrical energy and the huge demands for power
in the modern times requires creation of bigger power substation.
The power stations may be far from the load center/consumers and so long high
voltage transmission lines are necessary for tranfer of bulk power transfer.
Switching station and transformers are installed in between generation and
distribution.
SUBSTATION :
Classifications of Substations
The substations may be classified in numerous ways, such as on the basis
of nature of duties, service rendered, operating voltage, importance, and
design.
Nature of Duties
Step-up or Primary Substations The generating voltage of
such type of substations is usually 3.3, 6.6, 11 or 33 KV. This
generating voltage is usually stepped up to primary transmission
voltage so that the large bulk of power can be transmitted. Such
types of substations are usually associated with generating
substations.
2
Basis of Importance
Grid Substations In such types of substations, bulk power is
transmitted from one point to another point in the grid. These are
important because any distribution in these substations may
cause the failure of the grid.
Town Substations These substations step down the voltage
at 33/11 kV for more distribution in the towns. If there is any fault
occurs in this substation, then the supply of the whole town is
blocked.
On the Basis of Design
Indoor Type Substations In such type of substations, the
apparatus is installed within the substation building. Such type of
substations is usually for the voltage up to 11 KV but can be
raised for the 33 KV or 66 KV when the surrounding air is
polluted by dust, fumes or gasses, etc.
Outdoor Substations These substations are further
subdivided into two categories
Pole Mounted Substations Such Substations are erected for
distributions of power in the localities. Single stout pole or H-
pole and 4-pole structures with relevant platforms are operating
for transformers of capacity up to 25 KVA, 125 KVA, and above
125KVA.
Foundation Mounted Substations Such types of substations are
used for mounting the transformers having capacity 33,000 volts or
above.
3
400KV :
1. MISA - 2 nos.of circuits
2. BONGAIGAON-(1,2,3,4)
3. BISHWANATH CHARIALI-(1,2,3,4)
4. KAMENG hydro project-(1,2)(under construction)
220KV
1. SONABIL - single circuit
2. ASEB
132KV
1. INCOMER-1 NEEPCO
2. INCOMER-2 ASEB
3. KHUPI NEEPCO
4. GOHPUR ASEB
5. DIPOTA ASEB
Equipments
4
BUS BAR:
This is the simplest arrangement consisting of a single set of a bus bar for the full length of
the switchyard and to this set of bus bars are connected to all the generators, transformer
and feeders as illustrated in the figure.
Advantages:
Lower cost
Small land area requirement
Easily expandable
Simple in concept and operation
Disadvantages:
Lowest reliability.
Failure of circuit breaker cause loss of feeder.
Bus bar fault causes blackout of entire sub-station.
The bus-bar may be sectionalized by a circuit breaker and isolating switches so that
a fault on one part does not cause a complete shutdown.
In a sectionalized bus bar arrangement only one additional circuit breaker is required
which does not cost much in comparison to the total cost of the bus bar system.
Advantages:
Disadvantages:
Higher cost than simple single bus system.
Loss of circuit/feeder for circuit breaker failure.
Advantages :
Circuit breaker outage/maintenance does not disturb the service of feeder.
Reasonable cost.
Fairly small land area required.
Easily expandable.
Disadvantages :
In case of bus bar fault entire substation get blackout.
Additional circuit breaker is required.
any feeder can be taken from any of the bus. Actually every feeder is connected to both of
the buses in parallel through individual isolator as Double main bus bar scheme :
In double main bus bar system two identical bus bars are used in such a way that
shown in the figure.
By closing any of the isolators one can put the feeder to associated bus.
Both of the buses are energized and total feeders are divided into two groups,
one group is fed from one bus and other from other bus. But any feeder at any
time can be transferred from one bus to other. There is one bus coupler breaker
which should be kept close during bus transfer operation.
For transfer operation, one should first close the bus coupler circuit breaker then
close the isolator associated with the bus to where the feeder would be
transferred and then open the isolator associated with the bus from where feeder
is transferred.
.
8
Advantages :
The double main cum transfer bus bar scheme provides the facilities of a double bus
arrangement and a main a transfer bus arranement.
The bus to which transfer bus isolator is connected can be used as a transfer bus
also.
During the time a circuit is bypass ,the bus coupler will act as the breaker for the
bypass circuit.
Advantages :
Disadvantages :
This system is a combination of Main and Transfer Bus and Double Bus
Arrangement.
This has got flexibility of transferring any circuit to any of the main buses.
For maintenance or any fault occurrence on a bus, particular bus only becomes
dead, while the other bus continues to be in service.
Any circuit breaker can be taken out for maintenance by transferring that circuit to
transfer bus, and transferring its protection to transfer bus coupler circuit breaker.
Advantages :
Disadvantages :
Additional isolator and circuit breaker required for transfer bus tie
Interruption of power during isolator operation.
Interruption of power is likely to cause major disturbance if the feeder are important
and heavily loaded.
Advantages:
Disadvantages:
In double breaker bus bar system two identical bus bars are used in such a way that
any outgoing or incoming feeder can be taken from any of the bus similar to double
bus bar system.
Only difference is that here every feeder is connected to both of the buses in parallel
through individual breaker instead only isolator as shown in the figure. By closing any
of the breakers and its associated isolators one can put the feeder to respective bus.
Both of the buses are energized and total feeders are divided into two groups, one
group is fed from one bus and other from other bus similar to previous case. But any
feeder at any time can be transferred from one bus to other.
There is no need of bus coupler as because the operation is done by breakers
instead of isolator.
For transfer operation, one should first close the isolators and then the breaker
associated with the bus to where the feeder would be transferred and then he or she
opens the breaker and then isolators associated with the bus from where feeder is
transferred.
12
Advantages :
Disadvantages:
Lightning Arrester:
Lightning arresters built for power substation use are immense devices,
consisting of a porcelain tube several feet long and several inches in diameter,
typically filled with discs of zinc oxide. A safety port on the side of the device
vents the occasional internal explosion without shattering the porcelain
cylinder.
Lightning arresters are rated by the peak current they can withstand, the
amount of energy they can absorb, and the breakover voltage that they
require to begin conduction. They are applied as part of a lightning protection
system.
13
Capacitive voltage transformers exist and are used by utilities for high-voltage
(greater than 66 kV) metering. They have a capacitive voltage divider but also
have a dual-winding transformer to couple the divided voltage to the metering
circuit. They tend to have lower allowable burdens than a wound transformer
but can be made economically at higher voltage ratings. Another difference is
that even though they decrease voltage, they do not increase current as found
in wound electromagnetic transformers.
Wave Trap:
A wave trap (high-frequency stopper) is a maintenance-free parallel resonant
circuit, mounted inline on high-voltage (HV) AC transmission power lines to
prevent the transmission of high frequency (40 kHz to 1000 kHz) carrier
signals of power line communication to unwanted destinations. Wave traps
are cylinder-like structures connected in series with HV transmission lines. A
wave trap is also called a line trap.[1]
The wave trap acts as a barrier or filter to prevent signal losses. The inductive
reactance of the line trap presents a high reactance to high-frequency signals
but a low reactance to mains frequency. This prevents carrier signals from
being dissipated in the substation or in a tap line or branch of the main
transmission path and grounds in the case of anything happening outside of
the carrier transmission path. The line trap is also used to attenuate the
shunting effects of high-voltage lines.
The trap consists of three major components: the main coil, the tuning device,
and the protective device (also known as a surge arrester). The protective and
tuning devices are mounted inside the main coil.
Current Transformer-
It is used for measuring high value currents. It is Designed to provide a current in its
secondary coil proportional to current flowing in its primary coil. The Primary winding
consists of very few turns and the Secondary winding consists of large no. of
turns.Current to be measured is passes through primary winding.
16
In live tank current transformer, the main core of the transformer is placed in the top tank.
The top tank also houses the secondary winding which is termed as live part of the
transformer body. Before placing them inside the tank, which is typically made of mild steel,
the core and secondary winding is insulated with various types of insulating material to
protect it from high voltage current.
The primary winding in a live tank CT is constructed of short length. This is done intentionally
as a shorter shape provides higher levels of durability and strength when the primary
winding is exposed to short time current.
In terms of functionality, in a live tank current transformer the heat generated during a short
term current test is minimal due to faster dissipation of heat by the primary coil into the
transformer oil which is filled in the tank.
Dead tank current transformer are a category of current transformers in which the core of the
transformer and its secondary winding are placed in the bottom part of the transformer tank.
This tank is earthed which gives it the term dead tank.
The primary winding in a dead tank CT is insulated similarly to other current transformers
and is then brought down to the bottom tank where it is earthed. Further, the primary is
made to pass through an insulated porcelain. In Dead tank CTs, the length of the primary
conductor decides the mechanical force exerted on the transformer when it is exposed to
short time dynamic current. It is therefore important to increase the length of the primary
conductor to ensure that there is no damage to the transformer when it is exposed to high
currents.
18
The size and shape of dead tank current transformers are large. They use up more steel in
construction of transformer tank. Since the size of the transformer tank is larger, it also uses
more transformer oil which makes it expensive to produce compared to live tank CTs. They
are heavier and as such transportation costs involved in transporting them from
manufacturing location to installation locations is more. As such, the demand for dead CTs is
lower compared to live tank CTs.
Turret is the housing of the CTs to be placed in the bottom of the bushing. The CTs are ring
type and used for protection of the Transformer. Bushing lead is the primary and the ring coil
is the secondary of the CT. Following test are done before erection of the turret on the
transformer tank.
2. Ratio test-
The test is done by injecting current in a primary lead passing through the ring and
measure the current in the secondary terminals. The value should be as
per the name plate data with 1%
3. Polarity check- the test is done with a 12v DC battery by switch on and switch
off principle.
CIRCUIT BREAKER:-
Circuit breaker is a switching device which can be operated manually and automatically for
controlling and protection of electrical power system.
The Circuit breakers are used to break the circuit in any normal or abnormal
condition. The normal condition is when we take shutdown and abnormal condition is any
fault in the feeder. There are two insulators one before and one after the circuit breaker in a
bay. The Circuit Breaker breaks automatically for short circuit fault or any other types of
electrical fault which may cause the power network to suffers a high stress of fault current in
them and damage the equipment and networks permanently.
1.support structure
4.pre-insertion resistor
19
According to their arc quenching media the circuit breaker can be devided as:
The purpose of the di-electric media in CB is for providing insulation between the live
parts of CB and extinguishing the arc generated during the making and breaking of CB
contact.
According to the operating mechanism of circuit breaker they can be devided as:
There are mainly two types of circuit breakers used for any substation:
2.MOCB Breakers
The use of SF6 Circuit breaker is mainly in the EHV substations which have high
input KV. In such breakers,Sulphurhexaflouride gas (SF6) is used as quenching medium
because sulphurhexaflouride gas (SF6) is an electronegative gas and has a strong tendency
to absorb free electrons.
Advantages of SF6:
Due to the superior arc quenching properties of sulphurhexaflouride gas (SF6) , the SF6
Circuit Breakers have many advantages over oil or air circuit breakers. Some are listed
below:
A MOCB places the interrupting unit in insulating oil is available only in interrupting
chamber.The features of designing MOCB is to reduce the requirement of oil and hence this
breaker is called minimum oil circuit breaker.It is used generally in 33kv and 132kv.
Closing time ,opening time and close open time of thrCB are measured with CB operational
analyzer kit and results to be as per manufacturer recommendation.
The closing time of all the poles should be same.if some poles are delayed in closing ,the
other pole should trip.
The SCR test indicates proper making of the contact on closing of the CB.the DCRM test
indicates the contact resistance during the closing andopening operation.this test along
contact travel test indicate the perfection of contact making and its quality.
At the instant of low pressure of SF6 inside the CB in the prescribed limit,the breaker should
not be operatedfor safety.this is done by providing interlocking in closing and tripping
circuit.checking of this interlock is very important.
8. ISOLATOR:
Isolator is a manually operated mechanical switch which separates a part of the electrical
power.Isolators are used to open a circuit under no load.Its main purpose is to isolate one
portion of the circuit from the other and not intended to be opened while current is flowing in
the line.
Types of isolators:
1.single break
2.double break
3.tandem isolator
21
Depending upon the position in the power system ,the isolators are divided as:
1.bus side isolator: the isolator is directly connected with main bus
2.line side isolator: the isolator is situated at line side of any feeder
3.transfer bus side isolator: the isolator is directly connected with transfer bus
1.main structure
3.support insulator
4.rotary insulator
4.moving blade
Earthing switches:
Earthing switches are mounted on the base of mainly line side isolator. Earthing switches
are normally vertically break switches. Contact arm of earthing switchs are normally aligned
horizontally at off condition during switching on operation. These earthing arms rotate and
move to vertical position and make contact with earth female contacts fitted at the top of the
post insulator stack of isolator at its outgoing side.The earthing arms are so interlocked with
main isolator moving contacts that it can be closed only when the main contacts of isolator
are in open position.The main isolator contacts can be closed only when the earthing arms
are in open position.
TRANSFORMER
A transformer is a static machine used for transforming power from one circuit to another
without any direct electrical connection and with help of mutual induction between two
windings. It transforms power from one circuit to another without changing its frequency
but may be in different voltage level.
TYPES OF TRANSFORMER
(a) 1 Transformer
(b) 3 Transformer
(Auto-Transformer)
Three-winding features
rating between 25 kVA to 315 kVA for pole mounting 350KVA to 2.5 MVA for ground
mounting type
industrial purpose
PRINCIPLE OF TRANSFORMER
23
11 kV/415 V
CONSTRUCTION
(01). Core
(02). Windings
(04). Tanks
(05). Bushings
(10). Breather
(11). Radiators
1.transformer core
2.tertiary winding
24
in some high rating transformer,one winding in addition to its primary and secondary winding
is used.the additional winding ,apart from primary and secondary windings,is known as
tertiary winding of transformer.because of this third winding ,the transformer called three
winding transformer.
it reduces the unbalancing in yhe primary due to unbalancing in the three phase load.
it redistributes the flow of fault current.
as the tertiary winding is connected in delta formation in 3 winding transformer ,it
assists in limitation of fault current in the event of short circuit from line to neutral.
Its purpose is to provide a circulating path for the harmonics produced in the
transformers along with power frequency. It reduces unbalancing in primary winding.
3.tap changer
Voltage control in electric power supply network is required for adjustment of voltage
at consumers premises as short period (1 2 %), daily (3 5 %) and seasonal (5
10 %) voltage variations in accordance with variations of load.
Tappings are invariably provided on the HV winding.
fine voltage variation
current interruption level
position of HV and LV windings w.r.t. core
managing the situation under low-load conditions
4.tanks
basically it is a container used to keep windings(both) and cooling oils.
The Tank and cover is fabricated from mild steel plate, blended and welded to
construct them as required size and shape. The fabricated tank (before
coating/painting) is subjected to pressure test to ensure no oil leakage
The inner dimensions of the transformer are fixed by the active dimensions of
the
transformers and clearances between windings and grounded parts of
transformer.
5.bushings
bushing is an insulated device that is used to prevent unwanted leakage of
electricity.
Up to 33 kV Porcelain Bushings
Above 33 kV Condenser Bushings
25
6.auxillary equipements
a) Temperature Indicators
The thermocouple is placed in the pocket (filled with transformer oil) provided with
the top of the main tank near the hot oil. Thermocouple is connected to oil temperature
indicator placed in Marshalling Kiosk. Thermometer is set for alarm and tripping at a desired
temperature.
the pressure relief valve plays a significant role in the protection of a power transformer.a
major fault in the transformer causes vaporisation of the oil,leading to rapid build up of
gaseous pressure.if this pressure is not released within few seconds,the tank buldges and
bursts(ruptured),resulting into spiling of oil over wide area and sometimes causing fire.
pressure relief valve is mounted on the tank cover or on one side of the tank,and provide
instantaneous release of oil/vapour pressure.
Mediums of Cooling :
Air symbol is A
Gas symbol is G
Water symbol is W
Circulation :
Natural symbol is N
Forced symbol is F
Different cooling systems employed for oil immersed power and distribution
transformers are :
3. OFAN (Oil Forced, Air Natural) : forced oil circulation by oil pump and coolers
4. OFAF (Oil Forced, Air Forced) : forced oil circulation and forced air cooling
5. OFWF (Oil Forced, Water Forced) : forced oil and forced air cooling
8.insulating oil
One of the most important factors which determines the life and satisfactory
operation of a Transformer is the oil in which it is immersed. The insulating oil for
Transformers (and Switchgear) is a pure hydrocarbon mineral oil with or without
additives. It performs two prime functions :
9. conservator tank
this is a cylindrical tank mounted on supporting structure on the roof of the transformer main
tank.the main function of conservator tank is to provide adequate space for expansion of oils
inside the transformer.
When air is breathed-in, there is a possibility of moisture and dust from atmosphere
to be sucked in. These contaminants deteriorate the insulation properties of oil.
Silica Gel Breather is provided which arrests moisture and dust from the drawn in air,
and admits only dry air.
Normal (dry) colour of Silica Gel is bright blue, which becomes pink when moisture is
absorbed. It can be dried by heating during the periodic maintenance, to obtain blue
colour.
11.Radiators :
The purpose of radiators is to limit the temperature of oil and winding in a transformer by
dissipating heat and therefore cooling of transformer oil.
Radiators are manufactured from cold rolled steel sheets, cold drawn and seam
welded to form its desired dimensions and then galvanized after fabrication.
In power and ehv for cooling radiators, fans and pumps fitted seperately.
It is a very sensitive gas and oil operated instrument which safely detects the
formation of gas or sudden pressure inside the transformer.
Buchholz Protection : This is used for two types of faults inside the transformer.
6. Uneven load sharing between two transformers in parallel causing overheating due
to circulating current.
These generate gasses collected in the upper chamber while flowing towards the
conservator, the oil level drops, and the top float triggers the alarm switch.
3. Puncture on bushing
These types of faults are of serious nature and operate both the floats provided in the
Buchholz Relay and trip out the transformer
Vector Grouping :
HV winding connection.
LV winding connection.
Phase Displacement :
Phase rotation is always anti-clockwise. (international adopted convention)
Use the hour indicator as the indicating phase displacement angle. Because there
are 12 hours on a clock, and a circle consists out of 360, each hour represents 30.
Thus 1 = 30, 2 = 60, 3 = 90, 6 = 180 and 12 = 0 or 360.
The minute hand is set on 12 o'clock and replaces the line to neutral voltage
(sometimes imaginary) of the HV winding. This position is always the reference point.
Because rotation is anti-clockwise, 1 = 30 lagging (LV lags HV with 30)and 11 =
330 lagging or 30 leading (LV leads HV with 30).
Reactor:
For transmission lines, the space between overhead line and ground forms a
capacitor parallel to transmission line, which causes an increase in voltage as
the distance increases. When a network becomes larger, sometimes the
short-circuit current on transmission line exceeds the short-circuit rating of the
equipment. To offset the capacitive effect of the transmission line and to
regulate the voltage and reactive power of the power system, reactors are
30
Bus Reactors:
A bus reactor is a type of air core inductor, or in some cases, oil filled,
connected between two buses or two sections of the same bus in order to limit
the voltage transients on either bus. It is installed in a bus to maintain system
voltage when the load of the bus changes. It adds inductance to the system to
offset the capacitance of the line which varies due to load, humidity, weather,
generator excitation and temperature.
Shunt Reactors:
Shunt reactors are used in power systems to counteract the effect of the line
parasitic capacitance, thereby stabilizing the system voltage within acceptable
limits. For short lines, we can basically ignore the impact of capacitive current
from a voltage regulation point of view, but medium and long lines can have
voltages at their receiving end much higher than the sending end, thus
creating issues such as over-fluxing of power transformers and over stressing
of line insulators. Under light-load conditions, the line produces more VARs,
resulting in receiving end voltage being higher than sending end voltage. In
order to consume the excess VARs when system is lightly loaded, an inductor
is added to the system. Since inductors absorbs VARs, a reactor is connected
in parallel with shunt capacitance of the line known as Shunt Reactor.
31
PROTECTION
1. Equipment Protection
2. Transmission Line Protection
1. Differential Relay
2. Restricted Earth Fault (REF)
3. Backup Impedance
4. Buchholz Relay
5. Pressure Release Valve/Device (PRV)
6. Oil Temperature Indicator/Winding Temperature Indicator (OTI/WTI)
1. Differential Relay
NORMAL CONDITION
P
32
The P arrow above the equipment (transformer) shows the flow of power.
In external fault condition the differential relay is not able to detect the fault. It is
because of the no directional chance of currents of current transformers (CTs) thus at OP
both currents I1 and I2 subtract each other and results in zero difference, so it does not
send trip signal to relay. Hence there is no interruption of power flow (P).
In internal fault condition the differential relay is able to detect the fault. It is because of
the directional chance of current of one of the current transformers (CTs), thus at OP
both currents I1 and I2 adds up and results in non-zero difference current, so it does
sends trip signal to relay. Hence there will be a interruption of power flow (P).
Earth fault is the fault between the live conductor and the earth. It occurs because of the
insulation breakdown. When the fault occurs the short-circuit currents flow through the
system, and this current is returned through the earth or through any electrical
equipment. This fault current damaged the equipment of the power system and also
interrupted the continuity of the supply.
The earth fault can be dispersed by using the restricted earth fault protection scheme.
The earth fault protection scheme consist the earth fault relay, which gives the tripping
command to the circuit breaker and hence restricted the fault current.
3. BACKUP IMPEDANCE
This protection scheme is used for the protection of reactors by an inverse neutral over-
current protection to detect high magnitude winding-to-ground faults. Its generally
monitor the impedance of the reactor.
4. BUCHHOLZ RELAY
34
It is connected between the main tank and the conservator tank of the transformer
which is inclined to 30 degrees. How it works? If there is occurrence of fault in the
transformer the oil of the tank gets over heated and gases are formed. The generation
of gases may be slow or fast depending upon the type of fault whether it is minor or
incipient one or heavy short circuit. Buchholz consist two hinged floats one at the top of
the metallic chamber and other one is at bottom of the chamber.
During minor fault, gas bubbles are generate which goes to upper side of the chamber
and compress the oil, this disturbs the float and float tilts ad the alarm circuit is closed
through mercury switch and the indication is given.
During heavy fault, large volume of gases is formed which cause violent displacement of
the oil and disturbs the lower float. The lower float tilts and the contacts are closed
which trip the transformer.
It is used in the emulsifying system. It works when there is a pressure difference between the
water source and quartz, during catching of fire or over heating of the equipment the quartz
breakdown and thus makes changes in pressure and valve gets open.
6. OTI/WTI
The WTI means winding temperature Indicator and OTI means Oil temperature Indicator
which indicates the winding temperature & oil temperature of the transformer and
operates the alarm, trip, and cooler control contacts. This instrument operates on the
principle of thermal imaging and it is not an actual measurement.
35
DISTANCE PROTECTION
The above figure consists of two line sections AB and CD; it is desired to provide distance
protection scheme.
The protection scheme is divided in three zones, i.e. Z1, Z2, and Z3. Z1 corresponds to
approximately 80% length of the line AB and is a high speed zone. The ordinates shown
corresponding to Z1 gives the operating time in case the fault takes place in this zone.
36
Second zone Z2 for relay at A covers remaining 20% length of the line AB and 20% of the
adjoining line. In case of a fault in this section relay at A will operate when the time
elapsed corresponds to the ordinate Z2. The main idea of the second zone is to provide
protection for the remaining 20% section of the line AB. In case of arcing fault in section
AB which adds to the impedance of the line as seen by the rely at A, the adjustment is
such that the relay at A will see that impedance in second zone and will operate. This is
why the second zone is extended into the adjoining line. The operating time of the
second zone is normally about 0.2 to 0.5 second.
The third zone unit at A provides back up protection for faults in the line CD, i.e., if there
is a fault in the line CD and if for some reason the relay at C fails to operate then relay at
A will provide backup protection. The delay time for the third zone is usually 0.4 to 1.00
sec.
In case of the feeder is being fed from both the ends and say the fault takes place in the
second zone of the line AB (20% of the line AB), the relay at B will operate
instantaneously (because it lies in the first zone BA) whereas the fault lies in the second
zone of the relay at A. This is undesirable from stability point of view and it is desirable
to avoid this delay. This is made possible when the relay at B gives an inter trip signal to
the relay at A in order to trip the breaker quickly rather than waiting for zone-2 tripping.
STEP POTENTIAL
Step potential is the step voltage between the feet of a person standing near an
energized grounded object.
37
When a fault occurs at a tower or substation, the current will enter the earth. Based on
the distribution of varying resistivity in the soil a corresponding voltage distribution will
occur. The voltage drop in the soil surrounding the grounding system can present
hazards for personnel standing in the vicinity of the grounding system. Personnel
stepping in the direction of the voltage gradient could be subjected to hazardous
voltages.
In the case of Step Potentials or step voltage, electricity will flow if a difference in
potential exists between the two legs of a person. Calculations must be performed that
determine how great the tolerable step potentials are and then compare those results
to the step voltages expected to occur at the site.
High soil resistivity tends to increase Step Potentials. A high resistivity top layer and low
resistivity bottom layer tends to result in the highest step voltages close to the ground
electrode: the low resistivity bottom layer draws more current out of the electrode
through the high resistivity layer, resulting in large voltage drops near the electrode.
Further from the ground electrode, the worst case scenario occurs when the soil has
conductive top layers and resistive bottom layers: in this case, the fault current remains
in the conductive top layer for much greater distances away from the electrode.
TOUCH POTENTIAL
38
When a fault occurs at a tower or substation, the current will pass through any metallic
object and enter the earth. Those personnel touching an object in the vicinity of the
GPR (Ground Potential Rise) will be subjected to these touch voltages which may be
hazardous.
For example if a person happens to be touching a high-voltage tower leg when a fault
occurs, the electricity would travel down the tower leg into the persons hand and
through vital organs of the body. It would then continue on its path and exit out through
the feet and into the earth. If a person having long arms and touching the tower leg and
yet standing away, he would have a huge difference in potential between his feet and
the tower, so larger the difference in potential there will be a larger hazardous.
The gases in oil are extracted and the quantity is analysed. By observing percentage of
different gases present in oil, one can predict the internal condition of a new transformer.
Generally no hydrocarbon should be present as it causes thermal stresses and
decomposition of insulation. However O2 and N2 may be present. The total gas content
should be less than 1%.
FRA is conducted to assess the mechanical integrity of the transformer which may get
disturbed due to transportation shocks. FRA signatures will be taken after assembly and oil
filling and compared with factory testing to ensure the healthiness of core/coil assembly
during transportation.
The performance of a transformer largely upon perfection of specific turns or voltage ratio of
transformer. The voltage should be applied only in the high voltage winding to get current of
low magnitude. It is done at various tap position by applying 3 phases ,415V supply on HV
and LV side of Power transformer.. At Various taps applied voltage and Resultant between
various Phases and phases and neutral measured with precision voltmeter and noted. Test
can detect Shorted turns or open circuits in the windings,incorrect winding connections,
and other internal faults or defects in tap changer.
With 415 V applied on high voltage side, voltage between all phases on the low
voltage(LV) and intermediate voltage(IV) side is measured for every tap position.Reapeating
the same procedure on IV side,the voltage is measured in LV.The ratios are calculated in
each case which should be as per the name plate data.
Polarity test:
Polarity means the direction of the induced voltages in the primary and the secondary
winding of the transformer. It is essential to know the relative polarities at any instant of the
primary and the secondary terminals for making the correct connections if the transformers
are to be connected in parallel or they are used in a three phase circuit because while doing
parallel operation, if we connect terminals of opposite polarity, it will result in a dead short -
circuit. So, to connect the same polarity windings together both in primary and
39
Each of the terminals of the primary as well as the secondary winding of a transformer is
alternatively positive and negative with respect to each other as shown in the figure below.
Let A1 and A2 be the positive and negative terminal respectively of the transformer primary
and a1, a2 are the positive and negative terminal of the secondary side of the transformer.If
A1 is connected to a1 and A2 is connected to a2 that means similar terminals of the
transformer are connected, then the polarity is said to be additive. If A1 is connected to
a2 and A2 to a1, that means the opposite terminals are connected to each other, and thus the
voltmeter will read the subtractive polarity.
In the primary side, the terminals are marked as A1 and A2 and from the secondary side the
terminals are named as a1 and a2. The terminal A1 is connected to one end of the secondary
winding, and a voltmeter is connected between A2 and the other end of the secondary
winding.When the voltmeter reads the difference that is (V1 V2), the transformer is said to
be connected with opposite polarity know as Subtractive polarity and when the voltmeter
reads (V1 + V2), the transformer is said to have additive polarity.
The vector group of transformer is an essential property of transformer for successful parallel
operation of transformer.It is done at factory site for ensuring the customer specified vector
group of transformer.The phase sequence or the order in which the phase reach their
manximum positive voltage must be identical for two paralleled
transformers.otherwise,during the cycle,each pair of phases will be short circuited.
40
The HV side of the transformer is kept open. Now with the help of variac, applied voltage
gets slowly increased until the voltmeter gives reading equal to the rated voltage of the LV
side. After reaching at rated LV side voltage, all three instruments reading (Voltmeter,
Ammeter and Wattmeter readings) are recorded.
. .
Therefore it is seen that the open circuit test on transformer is used to determine core
losses in transforme.
Short Circuit Test on Transformer
A voltmeter, wattmeter, and an ammeter are connected in HV side of the transformer as
shown. The voltage at rated frequency is applied to that HV side with the help of a variac of
variable ratio auto transformer.
The LV side of the transformer is short circuited. Now with the help of variac applied voltage
is slowly increased until the ammeter gives reading equal to the rated current of the HV side.
After reaching at rated current of HV side, all three instruments reading (Voltmeter, Ammeter
and Watt-meter readings) are recorded. The ammeter reading gives the primary equivalent
of full load current IL. As the voltage applied for full load current in short circuit test on
transformer is quite small compared to the rated primary voltage of the transfomer, the
core losses in transformer can be
A pure insulator when is connected across line and earth behaves as a capacitor or a
dielectric and the electric current passing through the insulator, only have capacitive
component. There is no resistive component of the current, flowing from line to earth through
insulator. But due to ageing of insulator the impurities like, dirt and moisture enter into it.
which provide conductive path to the current. Consequently, leakage electric current flowing
from line earth through insulator has also resistive component. The healthiness of an
electrical insulator can be determined by ratio of resistive component to capacitive
component. For good insulator this ratio would be quite low. This ratio is commonly known
as tan or tan delta or as dissipation factor. The cable, winding, current
transformer, potential transformer, transformer bushing, on which tan delta
test or dissipation factor test to be conducted, is first isolated from the system.
In the vector diagram, the system voltage is drawn along x-axis. Conductive electric
current i.e. resistive component of leakage current, IR will also be along x-axis.As the
capacitive component of leakage electric current IC leads system voltage by 90, it will be
drawn along y-axis.Now, total leakage electric current IL(Ic + IR) makes an angle (say) with
y-axis.
From the diagram above, it is cleared, the ratio, IR to IC is nothing but tan or tan delta.
Insulation resitance
In insulation resistance test,the voltage is applied across the insulator. Due to this applied
high DC voltage there will be a current through the electrical insulator. Dividing the applied
voltage by this current we get the actual resistive value of the insulator.
Say the applied high voltage is V and corresponding current through the insulator,is I.Hence
as per Ohms law the value of insulation resistance is
43
This test is generally done by means of megger.Megger gives required direct (DC) voltage
across the insulator, and it also shows the resistive value of insulation directly in Mohm
range.
It is done as:
Since the IR value of transformer insulating oil may vary with temperature.
IR values to be recorded at intervals of 15 seconds, 1 minute and 10 minutes.
With the duration of application of voltage, IR value increases. The increase in IR is an
indication of dryness of insulation.
Polarization index = 10 minutes value / 1 minute value. high polarization index of an insulator
implies healthiness of insulator.Minimum recommended value should be less than 4.
DIGITAL ELECTRONICS
.
Two transformers are said to be connected in parallel if the primary windings are connected
to supply busbars and secondary windings are connected to load busbars.. While connecting
two or more than two transformers in parallel, it is essential that their terminals of similar
polarities are joined to the same busbars .The wrong connections may result in a dead short-
circuit and primary transformers may be damaged. There are three principal reasons for
connecting transformers in parallel. Firstly, if one transformer fails, the continuity of supply
can be maintained through other transformers. Secondly, when the load on the substation
becomes more than the capacity of the existing transformers, another transformer can be
added in parallel. Thirdly, any transformer can be taken out of the circuit for repair/routine
maintenance without interrupting supply to the consumers.
(ii) The voltage ratings and voltage ratios of the transformers should be the same.
44
(iii) The per unit or percentage impedances of the transformers should be equal.
The vector group of transformer is an essential property for successful parallel operation
of transformers The phase sequence or the order in which the phases reach their maximum
positive voltages, must be identical for two paralleled transformers. Otherwise, during the
cycle, each pair of phases will be short circuited.
The several secondary connections are available in respect of various primary three phase
connection in a the three phase transformer. So for same primary applied three
phase voltage there may be different three phase secondary voltages with various
magnitudes and phases for different internal connection of the transformer.
Let's have a discussion in detail by example for better understanding.
We know that, the primary and secondary coils on any one limb have induced emfs that are
in time-phase. Let's consider two transformers of same number primary turns and the
primary windings are connected in star. The secondary number of turns per phase in both
transformers are also same. But the first transformer has star connected secondary and
other transformer has delta connected secondary. If same voltages are applied in primary of
both transformers, the secondary induced emf in each phase will be in same time-phase with
that of respective primary phase, as because the the primary and secondary coils of same
phase are wound on the same limb in the core of transformer. In first transformer, as the
secondary is star connected, the secondary line voltage is 3 times of induced voltage per
secondary phase coil. But in case of second transformer, where secondary is delta
connected, the line voltage is equal to induced voltage per secondary phase coil. If we go
through the vector diagram of secondary line voltages of both transformer, we will easily find
that there will be a clear 30o angular difference between the line voltages of these
transformers. Now, if we try to run these transformers in parallel then there will be a
circulating current flows between the transformers as because there is a phase angle
difference between their secondary line voltages. This phase difference can not be
compensated. Thus two sets of connections giving secondary voltages with a phase
displacement can not be intended for parallel operation of transformers.
The following table gives the connections for which from the view point of phase sequence
and angular divergences, transformer can be operated parallel. According to their vector
relation, all three phase transformers are divided into different vector group of transformer.
All electrical power transformers of a particular vector group can easily be operated in
parallel if they fulfill other condition for parallel operation of transformers.
reason the oil comes in contact with air. The air can also be entered in the oil due to
unattended leakages in the body of the equipment.
Contact of atmospheric air with the oil causes unwanted oxidation reaction in the oil. These
oxidation reactions are further accelerated due to temperature and presence of catalysts like
solid copper, iron and other dissolved metallic materials in the oil. Temperature of oil rises
due to loading of the equipment and any flash or arc formed in oil filled space of the
equipment. As a result of these oxidation reactions the color of the oil becomes darker and
resistivity of the insulating oil decreases. At the same time acidity of the oil increases. Also
the tan delta or dielectric dissipation factor of the oil increases. That means over all
insulating properties of the oil deteriorated. Deteriorated oil also affects the other insulating
parts (mainly paper insulation) of the equipment. Deteriorated oil decreases the normal life
span of the oil immersed equipment and may increase the no load (fixed) losses of the
equipment.