ACTIVITIES PREDECESSORS DAYS COST OF LABOR
LABORERS

I. MOBILIZATION

A. PURCHASING OF MATERIALS SECURING BUILDING PERMIT 1-3 2

B. BUILDING OF TEMPORARY SHELTER PURCHASING OF MATERIALS 2 3

C. BUILDING OF TEMP. UTILITIES PURCHASING OF MATERIALS 2 3

D. STORAGE OF MATERIALS PURCHASING OF MATERIALS 2 3


II. SITE PREPARATION

A. CLEARING OF SITE SITE CLEARING 2 4

B. PLOT BEARING SITE CLEARING 1 2

C. PERIMETER FENCING PLOT BEARING 1 2

D. STAKING OF BATTER BOARDS PLOT BEARING 2 2

E. EXCAVATING SITE CLEARING 3-4 4


III. CONCRETE WORKS

A. MIXING OF CONCRETE EXCAVATING 2 3

B. POURING OF CONCRETE MIXING OF CONCRETE 4 2

C. CONCRETING OF FOOTING EXCAVATING 4 3

D. CONCRETING OF COLUMN FORMWORK OF COLUMN 3 3

E. CONCRETING OF BEAMS FORMWORK OF BEAM 3 3


F. CONCRETING OF FIRST FLOOR FORMWORK 3 3
IV. REINFORCEMENT BARS

A. CUTTING AND BENDING


PURCHASING OF MATERIALS 3 2

B. INSTALL OF REBAR FOOTING CUTTING AND BENDING,


EXCAVATING
2 2

CUTTING AND BENDING,


C. INSTALL OF COLUMN REBAR EXCAVATING
3 3

D. INSTALL BEAM AND GIRDER REBAR CUTTING AND BENDING 3 3


V. CARPENTRY WORKS

PURCHASING OF MATERIALS,
A. FORMWORKS EXCAVATION
4 2

PURCHASING OF MATERIALS,
B. LAYOUT OF SCAFFOLDING FORMWORKS
3 2

C. FORMWORK OF COLUMNS INSTALL OF COLUMN REBAR 4 3


D. INSTALL SECOND FLOOR WOOD CONCRETING OF BEAMS 2 2
GIRDERS
E. INSTALL SECOND FLOOR WOOD JOISTS LAYOUT OF SCAFFOLDING 2 2

F. INSTALL SECOND FLOOR WOOD POSTS LAYOUT OF SCAFFOLDING 3 2


VI. UTILITIES

A. ROUGHING-IN-ELECTRICAL CONCRETE WORKS 4 3

B. ROUGHING-IN-PLUMBING CONCRETE WORKS 4 3


CONCRETE
WORKS,ROUGHING-IN- 4 2
C. INSTALL WIRINGS OF ELECTRICAL
ELECTRICAL

D. INSTALL ALL ELECTRICAL FIXTURES CONCRETE WORKS 4 2

E. INSTALL ALL PLUMBING FIXTURES CONCRETE WORKS 2 2


VII. ROOFING

A. INSTALL PERIMETER SECOND FLOOR CONCRETE WORKS,


2 2
WOOD STUDDING REINFORCEMENT BARS

B. INSTALL PURLINS, FACIA BOARDS AND LAYOUT OF SCAFFOLDING 2 2


RIVET
C. INSTALL GUTTERS, FLASHINGS RIDGE ROOFING INSTALLATION 2 2
ROLLS AND VALLEYS
D. ROOFING INSULATION LAYOUT OF SCAFFOLDING 3 2

E. STOCK ROOF SHINGLES ROOFING INSULATION 4 3

F. INSTALL ROOF SHINGLES STOCK ROOF SHINGLES 3 3


VIII. FINISHES

CONCRETE WORKS,
A. TINSMITHRY REINFORCEMENT BARS
2 3

CONCRETE WORKS,
B. WAINSCOTING REINFORCEMENT BARS
2 2

INSTALL WIRINGS OF
C. INSTALL LIGHTING 2 2
ELECTRICAL

D. INSTALL DOORS AND WINDOWS CONCRETE WORKS, 3 4


CONCRETE WORKS, INSTALL
E. PAINTING LIGHTING
3 4

XI. FINISH AND CLEAN-OUT

A. REMOVE FORMWORKS PAINTING 2 3


B. REMOVE ALL SCAFFOLDINGS AND REMOVE FORMWORKS 2 3
DEBRIS
REMOVE ALL
C. CLEAN-UP PREMISES SCAFFOLDINGS AND DEBRIS
2 3

X. PROJECT TURNOVER

A. CERTIFICATE OF OCCUPANCY FINISH AND CLEAN-OUT 1 1

Mobilization
Earthwork
Concrete work
Masonry work
Reinforcement bars
Mob
Carpentry
Earthwork
Reinforcement
concrete