Project No. 19 Project Name Project detail/ Location
Check list for Reinforcement
Location : Drawing Ref : Sheet No .
S. No. Points to be verified Yes No N/A Remarks
1 Is the material approval received 2 Is the material as per the approval 3 Has the approval for Bar bending schedule taken 4 Are the rebars free from rust corrosion 5 Are all the bars of the correct sizes as per drawing & specs. 6 Is the spacing as per drawing & specs. 7 Is the inspection of reinforcement after placing in position done 8 Has the additional steel around cutouts / ducts / sleeves / lap lengths been checked 9 Whether chairs are provided to keep the top bar horizontal for footings/slabs etc., stirrups, hooks etc. if any 10 Whether binding wire properly tightened 11 Whether proper spacers are installed & are sufficient 12 Are all the starter bars and splices of correct sizes & number Other special requirements/Remarks:
NAME SIGNATURE DATE
Site Engineer MEP Engineer NA Project Engineer Project Manager HSEQ QA/QC Incharge