You are on page 1of 11

4.00.

OBRAS DE CONCRETO SIMPLE

4.01. CIMIENTOS CORRIDOS


DIMENSIONES SUB TOTAL
DESCRIPCIÓN UNIDAD Nº DE VECES TOTAL (m3)
ANCHO (m) ALTO (m) LARGO (m) (m3)
EJE A-A, B-B, C-C m3 3 0.40 1.00 8.95 10.74
EJE 1-1, 2-2, 3-3, 4-4, 5-5;
ENTRE LOS TRAMOS A-B m3 5 0.40 1.00 3.20 6.4

EJE 1-1, 2'-2', 4-4, 5-5; ENTRE m3 4 0.40 1.00 3.80 6.08
LOS TRAMOS B-C
EJE B'-B' ENTRE LOS m3 1 0.40 1.00 1.25 0.5
TRAMOS 2'-2''
EJE 2''-2'' ENTRE LOS m3 1 0.40 1.00 2.60 1.04 24.76
TRAMOS B'-C

4.02 SOBRECIMIENTOS
4.02.01 CONCRETO DE SOBRECIMIENTOS

DIMENSIONES SUB TOTAL


DESCRIPCIÓN UNIDAD Nº DE VECES TOTAL (m3)
ANCHO (m) ALTO (m) LARGO (m) (m3)

EJE A-A, C-C ENTRE LOS m3 4 0.15 0.30 6.90 1.242


TRAMOS 1-4
EJE 1-1, 2-2, 3-3, 4-4, 5-5;
ENTRE LOS TRAMOS A-B m3 5 0.15 0.30 3.60 0.81

EJE 2'-2'; ENTRE LOS TRAMOS m3 1 0.15 0.30 3.00 0.135


B'-C
EJE B'-B' ENTRE LOS m3 1 0.15 0.30 1.30 0.0585
TRAMOS 2'-2''
EJE 2''-2'' ENTRE LOS m3 1 0.15 0.30 2.30 0.1035
TRAMOS B'-C
EJE 1-1 ENTRE LOS m3 1 0.15 0.30 3.90 0.1755
TRAMOS B-C
EJE 5-5; ENTRE LOS m3 1 0.15 0.30 4.10 0.1845
TRAMOS B-C
EJE B-B, ENTRE LOS m3 1 0.15 0.30 3.20 0.144 2.853
TRAMOS 1-4
EJE B-B, ENTRE LOS m3 1 0.15 0.30 3.20 0.144 2.853
TRAMOS 1-4

4.02.02 ENCOFRADOS Y DESENCOFRADOS

DIMENSIONES SUB TOTAL TOTAL (m2)


DESCRIPCIÓN UNIDAD Nº DE VECES
ANCHO (m) ALTO (m) LARGO (m) (m2)
EJE A-A, C-C ENTRE LOS
TRAMOS 1-4 m2 4X2 ------- 0.30 6.90 16.56

EJE 1-1, 2-2, 3-3, 4-4, 5-5;


ENTRE LOS TRAMOS A-B m2 2x5 ------- 0.30 3.60 10.8

EJE 2'-2'; ENTRE LOS TRAMOS m2 2x1 ------- 0.30 3.00 1.8
B'-C
EJE B'-B' ENTRE LOS m2 2x1 ------- 0.30 1.30 0.78
TRAMOS 2'-2''
EJE 2''-2'' ENTRE LOS m2 2x1 ------- 0.30 2.30 1.38
TRAMOS B'-C
EJE 1-1 ENTRE LOS m2 2x1 ------- 0.30 3.90 2.34
TRAMOS B-C
EJE 5-5; ENTRE LOS m2 2x1 ------- 0.30 4.10 2.46
TRAMOS B-C
EJE B-B, ENTRE LOS m2 2x1 ------- 0.30 3.20 1.92 38.04
TRAMOS 1-4
5.00 PISOS Y PAVIMENTOS

5.01 PISOS:
5.01.01 .- CONCRETO EN FALSO PISO

CALCULO DEL ÁREAS


Unidad de medida (m2)
A.- PUERTAS

Area
EJE DESCRIPCIÓN Largo. (m) Ancho (m) (m2)
5-5 Tramo B-C 1 0.15 0.15
B-B Tramo 3-4 0.9 0.15 0.135
B-B Tramo 2-3 0.9 0.15 0.135
2-2 Tramo A-B 0.9 0.15 0.135
2'-2' Tramo B'-B' 0.9 0.15 0.135
2''-2'' Tramo B''-C 0.7 0.15 0.105
TOTAL = 0.80

B.- SALA

DESCRIPCIÓN Largo. (m) Ancho (m) Area (m2)

A1 4.9 4.1 20.09


A2 1.25 1 1.25
TOTAL = 21.34

C.- COMEDOR

Area
Largo. (m) Ancho (m)
(m2)
3.6 2.5 9

D.- BIBLIOTECA

Area
Largo. (m) Ancho (m)
(m2)
3.6 2 7.2

E.- BAÑO

Area
Largo. (m) Ancho (m) (m2)
3 1.1 3.3

E.- COCINA

Area
Largo. (m) Ancho (m) (m2)
3.6 2.2 7.92

E.- PATIO

Area
Largo. (m) Ancho (m) (m2)
3.6 1.5 5.4

F.- DORMITORIO

Area
Largo. (m) Ancho (m)
(m2)
4.1 2.4 9.84

G.- ÁREA DE ESCALERA A DESCONTAR


Area
Largo. (m) Ancho (m)
(m2)
0.25 0.9 0.225

EL VOLUMEN TOTAL DONDE SE UTILZARA CONCRETO SIMPLE f'c=140 kg/cm2


SERA IGUAL A

ÁREA A 64.57 m2
RELLENAR

ESPESOR DE 0.05 m
PISO

VOLUMEN DE
CONCRETO 3.2285 m3

5.01.02 .- PISO ACABADO CON CERAMICO

Area
DESCRIPCIÓN Nª VECES Ancho (m) Long. (m) (m2)
4.00 0.15 0.90 0.54
Puertas 1.00 0.15 0.70 0.11
1.00 0.15 1.00 0.15
1.00 1.00 1.25 1.25
Sala
1.00 4.10 4.90 20.09
Comedor 1.00 2.50 3.60 9.00
Biblioteca 1.00 2.00 3.60 7.20
Baño 1.00 1.10 3.00 3.30
Cocina 1.00 2.20 3.60 7.92
Patio 1.00 1.50 3.60 5.40
Dormitorio 1.00 2.40 4.10 9.84

1.00 0.25 0.90 0.23


Área a descontar
Total = 64.57
5.01.02 .- CONTRAPISO (e =0.04m)

Area
DESCRIPCIÓN Nª VECES Ancho (m) Long. (m) (m2)
4.00 0.15 0.90 0.54
Puertas 1.00 0.15 0.70 0.11
1.00 0.15 1.00 0.15
1.00 1.00 1.25 1.25
Sala
1.00 4.10 4.90 20.09
Comedor 1.00 2.50 3.60 9.00
Biblioteca 1.00 2.00 3.60 7.20
Baño 1.00 1.10 3.00 3.30
Cocina 1.00 2.20 3.60 7.92
Patio 1.00 1.50 3.60 5.40
Dormitorio 1.00 2.40 4.10 9.84
1.00 0.25 0.90 0.23
Área a descontar
Total = 64.57

EL VOLUMEN TOTAL DONDE SE UTILZARA MORTERO PROPORCIÓN 1:5 SERA IGUAL A:


ÁREA A 64.57 m2
RELLENAR

ESPESOR DE 0.04 m
CONTRAPISO
VOLUMEN DE
CONCRETO 2.5828 m3

7.02. VIGAS

7.02.01.- CONCRETO f'c 210 kg/cm2


DIMENSIONES SUB TOTAL TOTAL (m3)
DESCRIPCIÓN UNIDAD Nº DE VECES
ANCHO (m) ALTO (m) LARGO (m) (m3)
EJE A-A, C-C ENTRE LOS m3 2 0.15 0.30 9.00 0.81
TRAMOS 1-4
EJE 1-1, 2-2, 3-3, 4-4, 5-5;
ENTRE LOS TRAMOS A-B m3 5 0.40 0.20 3.60 1.44

EJE 1-1, 2-2, 3-3, 4-4, 5-5;


ENTRE LOS TRAMOS B-C m3 5 0.40 0.20 4.10 1.64

EJE B'-B' ENTRE LOS m3 1 0.15 0.20 2.00 0.06


TRAMOS 2-2''
EJE 2'-2', 2''-2'' ENTRE LOS m3 2 0.15 0.20 2.90 0.174
TRAMOS B'-C
EJE B-B, ENTRE LOS m3 1 0.15 0.40 9.00 0.54
TRAMOS 1-4
ENTRE LOS EJE 4-4 Y 2''-2'' m3 1 0.15 0.20 2.20 0.066
ENTRE LOS TRAMOS B'-C
ENTRE LOS EJE 2-2 Y 2'-2' m3 1 0.15 0.20 0.40 0.012 4.742
ENTRE LOS TRAMOS B'-C

VOLUMEN DE CONCRETO EN VIGAS

PRIMER NIVEL 4.7420 m3


SEGUNDO NIVEL 4.7420 m3
TOTAL 9.4840 m3

7.02.02.- ENCOFRADO DE VIGAS

DIMENSIONES SUB TOTAL TOTAL (m2)


DESCRIPCIÓN UNIDAD Nº DE VECES
ANCHO (m) ALTO (m) LARGO (m) (m2)
EJE A-A Y C-C ENTRE LOS EJES m2 2 ------- 0.30 9.00 5.4
1-1 Y 5-5
EJE 1-1 Y 5-5 ENTRE LOS EJES
A-A Y C-C m2 2 ------- 0.20 7.50 3

m2 1 ------- 0.20 4.90 0.98

EJE 1-1 Y 5-5 ENTRE LOS EJES


A-A Y C-C m2 1 ------- 0.20 0.90 0.18

m2 1 ------- 0.20 0.60 0.12

m2 1 ------- 0.40 1.50 0.6

m2 1 ------- 0.20 0.40 0.08

EJE A-A Y C-C ENTRE LOS EJES


1-1 Y 5-5 m2 1 ------- 0.20 1.80 0.36

m2 1 ------- 0.20 1.10 0.22

EJE A-A Y B-B ENTRE LOS EJES


1-1 Y 2-2 m2 1 ------- 0.20 3.40 0.68

EJE B-B ENTRE LOS EJES 1-1 Y


2-2 m2 1 ------- 0.40 1.50 0.6 12.22
ÁREA DE ENCOFADO EN VIGAS

PRIMER NIVEL 12.22 m2


SEGUNDO NIVEL 12.22 m2
TOTAL 24.44 m2

7.03. LOSAS ALIGERADAS


7.03.01 CONCRETO f'c 210 kg/cm2

NUMERO DE VIGETAS POR m2

h 20 cm

0.30 0.10 0.30

N DE VIGETAS 2.5 vigetas x m

VOLUMEN DE CONCRETO EN (e=5 cm) por metro lineal

V DE CONCRETO 0.05 m3

VOLUMEN DE CONCRETO EN LAS VIGUETAS (e = 0.15 m)

V DE CONCRETO 0.0375 m3
POR LO TANTO EL VOLUMEN DE CONCRETO POR m2 SERÁ: 0.05+0.0378 = 0.0875 m3 por m2 de losa aligerada

AREA TOTAL A TECHAR

DIMENSIONES SUB TOTAL


DESCRIPCIÓN UNIDAD TOTAL (m2)
ANCHO (m) LARGO (m) (m2)
EJE A-A Y B-B ENTRE LOS EJES m2 3.60 9.00 32.4
2-2 Y 5-5
EJE 4-4 Y 5-5 ENTRE LOS EJES
B-B Y C-C m2 2.20 4.10 9.02

EJE 1-1 Y 2-2 ENTRE LOS EJES


B-B Y C-C m2 1.20 4.00 4.8

EJE 2-2 Y 2''-2'' ENTRE LOS


EJES B-B Y C-C m2 2.00 4.00 8

EJE 2''-2'' Y 4-4 ENTRE LOS


EJES B-B Y C-C m2 1.50 3.15 4.725

m2 0.20 0.90 0.18 59.125

VOLUMEN DE CONCTRETO
∀=59.125 𝑚^2∗(0.0875𝑚^3)/
〖 1𝑚 〗 ^2 = 5.17 m3

VOLUMEN DE CONCRETO EN VIGAS


PRIMER NIVEL 5.17 m3
SEGUNDO NIVEL 5.17 m3
TOTAL 10.35 m3

ÁREA DE ENCOFADO EN LOSAS ALIGERADAS

PRIMER NIVEL 59.13 m2


SEGUNDO NIVEL 59.13 m2
TOTAL 118.25 m2

PARTIDA UNIDAD METRADO


Concreto f'c 210 kg/cm2 m3 10.35
Encofrado y desencofado m2 118.25