ID Task Name Duration Start Finish Predecessors 20, '10 Sep 27, '10 Oct 4, '10 Oct 11,

cessors 20, '10 Sep 27, '10 Oct 4, '10 Oct 11, '10
T W T F S S M T W T F S S M T W T F S S M T W T
1 Odprašivanje zida 1 day Wed 9/22/10 Wed 9/22/10
2 Pivkan 1 day Thu 9/23/10 Thu 9/23/10 1
3 Skidanje paučine 1 day Fri 9/24/10 Fri 9/24/10 2
4 Pivkan 1 day Mon 9/27/10 Mon 9/27/10 3
5 Gletovanje 1 day Tue 9/28/10 Tue 9/28/10 4
6 Pivkan 1 day Wed 9/29/10 Wed 9/29/10 5
7 Šalovanje 1 day Thu 9/30/10 Thu 9/30/10 6
8 Pivkan 1 day Fri 10/1/10 Fri 10/1/10 7
9 Otpakiravanje naljepnice 1 day Mon 10/4/10 Mon 10/4/10 8
10 Pivkan 1 day Tue 10/5/10 Tue 10/5/10 9
11 Zaljepljivanje naljepnice 1 day Wed 10/6/10 Wed 10/6/10 10
12 Pivkan 1 day Thu 10/7/10 Thu 10/7/10 11
13 Skidanje gornjeg pokrova naljepnice 1 day Fri 10/8/10 Fri 10/8/10 12
14 Pivkan 1 day Mon 10/11/10 Mon 10/11/10 13
15 Odstranjivanje zračnih mjehurića 1 day Tue 10/12/10 Tue 10/12/10 14
16 Pivkan i divljenje novouređenom zidu 1 day Wed 10/13/10 Wed 10/13/10 15

Task Milestone External Tasks


Project: Project1
Split Summary External Milestone
Date: Wed 9/22/10
Progress Project Summary Deadline