0 PROCEDURE AND FLOWCHART


START
5.1

SITE NOMINATION

CLIENT NOMINATE SITE LEMCON SITE NOMINATION


via Bus. Development Group

Lemcon Receives Order from Client via Email on site nomination


` Bus Dev. Group forwards LOI (Letter of Intent) for Site Nomination ready for
Survey via email or Pipe drive monitoring

Operations forwards Site Nomination to Design Group to Perform Site Survey


(Note: Floor Plan may or may not be available)

Design Group conducts Site Survey & Produced HLD/LLD TSSR & BOQ

Design Group submits the Design and BOQ to Operations

Operations Reviews the Submitted Design & BOQ

Operations
No Design Group revised
Approval

Yes

Operations submit the Design and BOQ to Client for comments and approval via Email

Clients Approval Lemcon Revise as per


No
Client request

Yes
A

A
Lemcon receives approved Design and BOQ from Client signed documents or via
email (NTP signed document or email approved by client)

Client released Purchase Order

Site Implementation (Site Inspection/Audit)

Site Acceptance (Punchlist Clearing)

Handover to Client Operations (PAC /


FAC)