Contractor Submittals
(Shop drawings, material submissions / samples, programmes, supplier approvals, etc.)
SUBMISSION
Contractor issues submittal
Mace DC Procedure: as hard copy with
submission cover sheet,
Step 1: Tag: IC ref number transmittal and soft copy via
email for upload to the Box.
Step 2: Stamps date received and initial
Mace Project /
Package Manager
Review
NO
NO REQUIRE
CLIENT (Generally Same Day as Received)
APPROVAL?
YES
‘FOR APPROVAL’
Reviewer writes ‘For
Approval’ on Cover Sheet
Submission Form.
Mace DC scans submittal
sheet and emails to Client
before issuing hard copy.
Mace to Review,
(If Reviewed by Mace generally 3 – 5 Days Response Time)
Respond and
(If approved by Client then processed Same Day)
Update Alert Status
Mace DC issue to
STATUS B STATUS C
STATUS A Contractor as
Proceed, in line with Do not proceed
Proceed.
comments.
rejected and Client
and resubmit.
for information
Mace DC Procedure:
RETURN TO CONTRACTOR
Step 1: Update Status Register. Mace issue approved
submission to Contractor to
Step 2: Update Out-Going Document Register. proceed as per comment and
send to Client for information.
Step 3: Issue to Contractor and Client with a
Document Transmittal Cover Sheet.
Notes:
UPLOAD FILING RECORD
- Mace DC must record all correspondence on
Step 4: Save Scanned Final Revision to Box for Record. Mace DC to upload scanned copy incoming and outgoing register
of proceeded submission onto Box
for record.
Intercontinental Ha Long Bay (ICHL) Project Mace Document Control Flow Chart
Request for Information
SUBMISSION
Contractor issues RFI in hard copy with SUBMISSION
submission cover sheet and soft copy Consultant sends RFI via email
via email, linked to
INBOX
Mace DC receives stamps RFI (Same Day)
and issues for review by
FORWARD
(3 – 5 Days) MACE CAN Mace DC to issue RFI to (Same Day)
ANSWER? relevant Consultants for
YES NO
response
RESPONSE
Consultants responds (3 – 5 Days)
to Mace DC
ISSUANCE ISSUANCE
Mace DC issue response to (Same Day) Mace DC issue response to (Same Day)
Contractor / Consultant to Contractor / Consultant to
proceed proceed
Mace DC Procedure:
Mace Project /
Package Manager (2 Working Days)
Review
MACE
APPROVAL
NO Mace DC returns to
Contractor for revision
within 48
(Same Day) and resubmission
hours
ISSUANCE TO
CONTRACTOR
Mace issues approved (Same Day)
Mace DC Procedure: submission to contractor
to proceed and to Client
Step 1: Update status register for information
Mace Project /
Package Manager (2 Working Days)
Review and Action
Mace DC assigns a
reference number and
(Same Day)
obtains signature from
sender
RETURN TO ‘RECEIVER’
Mace DC Procedure: Mace DC sends response to
(Same Day)
receiver specified by sender
Step 1: Update status register as hardcopy
Notes:
- Mace DC must record all correspondence on
incoming and outgoing register
Intercontinental Ha Long Bay (ICHL) Project Mace Document Control Flow Chart
Alternative Proposal by others
ALTERNATIVE PROPOSAL
Alternative Design, Sample or
Method is put forward by
i.e. Consultant, Contractor with
description and drawings and
RAISE EWN (as needed) issued to Mace for review
Mace Project Manager raises
(Same Day) Early Warning Notice to
Client
ISSUE CR
Mace assigns reference number and
upload onto the Box and the BIM Cloud
System
(Same Day)
DESIGN COMMENT
Design consultants comment on impact of
change and state design fees and prepare
detailed design of change for pricing and
upload comments in BIM Cloud System
(3-5 Days)
CONFIRMATION OF IMPLICATIONS
Mace confirm cost and
programme implications
for each package affected and upload
comments in BIM Cloud System
(3-5 Days)
ISSUE ENGINEER’S
INSTRUCTION
Mace to raise and issue
Mace DC Procedure: EI to contractor and/or
instruct consultants to
Step 1: Update status register commence with change
Mace DC Procedure:
ISSUANCE OF IPA (Day 1)
Step 1: Tag: IC ref number Contractor issues Interim Payment Application (with
draft invoice) for Mace and WTP (QS) parallel review on
Step 2: Stamps date received and initial the 5th Day of the Month as per Client request.
INBOX
Mace upload initial / draft onto the Box and the BIM Cloud System
(Day 2-12) Mace & WTP (QS) assesses the Interim Payment
Application and value the works completed to the end of (10 Days)
the assessment period. Interim Payment Application will
be processed the following period if submitted late.
(Day 14-42) Mace issues the IPA with comments to BIM for
review and further comment through BIM Cloud System. If
no further comments then Mace PM produces draft (7-28 Days)
Interim Payment Certificate based upon the agreed
valuation. PM returns to the Contractor to update.
INBOX
Mace upload the issued IPC onto the Box and the BIM Cloud
System
Internal
Client
Process
Contractor workers
Contractor FAIL Repair / Modify based
(Any time that suits the QA/QC on all comments and
Contractors Programme) Inspection issues found by
Contractor QA/QC
PASS (In Contractor’s own planned time)
Contractor
QA/QC
APPROVAL