HVAC STATIC PRESSURE TEST

ITR No H11B
Item/Tag No. @T System No. @S
Item/Tag Description @D Sub System No. @SS
Sub System Description @SSD
Location @L Print Date @PD

INFORMATION
Lay Out Drawing

No. Items to be Checked OK N/A Punch List no.

Ensure that the Ductwork installation is in accordance


1
with the current GA Drawing(s) and CCN's are closed out.
Confirm Mechanical Completion Records are all complete
2
and no subsequent damage has occurred.
3 Ensure all blanks have been removed.
Ensure all dampers are in the open position i.e. control,
4
shut off, manual and fire dampers.
5 Check that all access hatches are closed.
Test holes (with sealing covers) in ducting for air flow
6
measurements provided.
7 Preservation removed.

COMMENT(S) / ADDITIONAL INFORMATION:

COMPLETED BY CONTRACTOR VERIFIED BY PMT/OWNER


Designation
Company
Name
Signature
Date