INSTRUMENT LOOP CHECK

ITR No I10B
Item/Tag No. @T System No. @S
Item/Tag Description @D Sub System No. @SS
Sub System Description @SSD
Location @L Print Date @PD

INFORMATION
Controller Tag
Signal Range Manufacturer
Number
Service Data Sheet Model Number

Loop Number Line of Equip No Serial Number

 Flam  Gas  Break glass  Other (To


Type of Detector e specify):________
PRE COMMISSIONINGCHECK OK_________
N/A P/L
Fire Alarm Panel.
1 Verify completeness of factory acceptance report of Fire Alarm Panel.
Verify the cable has been terminated and tested as per check sheet I-10A and
2
completed.
3 Verify no dust inside Enclosure /Cabinet / Panel and insulation surfaces are clean.

4 Verify Instruments & its Accessories /Electrical equipment/Panel externally clean.

5 Check Power Supply and On Fire Alarm Panel

6 Verify all tools/equipment/test kits for the loop test are available

7 Verify MCP and Fire alarm bell connected to Fire Alarm Panel

8 Verify the Address of the components connected to the panel.


Verify all the indication/display in FAP are correctly activated upon testing of the
9
loop

1
INSTRUMENT LOOP CHECK

10 Confirm and check Function test of Fire Alarm Panel

11 Check Functional Test of MCP, Fire Alarm Bell & Detectors with FAP

12 Check all the interfaces and control functions as per requirement.


Functional Test of F&G System (Connected to FGS)
Verify completeness of factory acceptance report of Fire & Gas systems
1
components.
2 Verify the cable has been terminated both field & panel side and tested.

3 Verify the correct electric power supply is connected to the Fire and Gas panel

4 Verify no dust inside Enclosure /Cabinet / Panel and insulation surfaces are clean.

5 Verify Instruments & its Accessories /Electrical equipment/Panel externally clean.

Confirm all system cable from marshaling cabinet are connected properly as per
6
vendor drawing.
Verify device / loop details are correct according to I/O schedule, project data
7
sheet and vendor data sheet.

8 Verify the field indication of detector.


Confirm device loop rack / slot / channel location are correct for all devices in
9
loop.
LOOP TEST (COLD)
ANALOG TRANSMITTER(Note2)
MODEL NO: SERIAL NO:

DIGITAL SWITCH(Note2)
MODEL NO: SERIAL NO:

Digital Output
MODEL NO: SERIAL NO:

Cable integrity test

2
INSTRUMENT LOOP CHECK

Instrument Tag Number JB Number & Marshalling Cabinet


Terminal No. Number & Terminal No. OK N/A P/L

REFERENCE DRAWINGS
1 Vendor Drawing
2 Cable Termination details
3 Panel Drawings
4 Loop Drawings
5 Instrument Datasheet
OBSERVATION / REMARKS

COMPLETED BY VERIFIED BY PMT/OWNER


CONTRACTOR
Designation
Company
Name
Signature
Date

You might also like