STF Palong Timur Rev.00 Run All Bs 21.04.2018 STF Palong Timur Rev.00 Run All Bs 21.04.2018
STF Palong Timur Rev.00 Run All Bs 21.04.2018 STF Palong Timur Rev.00 Run All Bs 21.04.2018
STF PALONG TIMUR REV.00 RUN ALL BS 21.04.2018 323.0d 155.0d -118.0d 02-Oct-17 08:00 AM 18-Oct-18 08:00 AM 91.44% 44.15%
A
Milestone 323.0d 0.0d -118.0d 02-Oct-17 08:00 AM A 18-Oct-18 08:00 AM 0% 0%
ML-001-100 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A 02-Oct-17 08:00 AM A 100% 100%
ML-001-110 Milestone Finish STF 0.0d 0.0d -118.0d 18-Oct-18 08:00 AM 18-Oct-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A 07-Nov-17 05:00 PM A 100% 100%
Preliminary Works 22.0d 0.0d 11-Dec-17 08:00 AM A 25-Jan-18 05:00 PM A 100% 100%
Setting Up of Site 12.0d 0.0d 11-Dec-17 08:00 AM A 23-Dec-17 05:00 PM A 100% 100%
A1120 Site measurement & site survey 12.0d 0.0d 11-Dec-17 08:00 AM A 23-Dec-17 05:00 PM A 100% 100%
Earthwork 12.0d 0.0d 23-Dec-17 08:00 AM A 25-Jan-18 05:00 PM A 100% 100%
A1130 Site clearance & excavation works 12.0d 0.0d 23-Dec-17 08:00 AM A 25-Jan-18 05:00 PM A 100% 100%
Water Retaining Structure 154.0d 42.0d -22.0d 06-Dec-17 08:00 AM A 07-Jun-18 05:00 PM 100% 57.45%
Wash Water Collection & Sludge Balancing Tank 154.0d 42.0d -22.0d 06-Dec-17 08:00 AM A 07-Jun-18 05:00 PM 100% 57.45%
Substructure 34.0d 0.0d 06-Dec-17 08:00 AM A 12-Mar-18 05:00 PM A 100% 100%
A1140 Install reinforcement 26.0d 0.0d 06-Dec-17 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
A1150 Install formwork 26.0d 0.0d 10-Dec-17 08:00 AM A 06-Mar-18 05:00 PM A 100% 100%
A1160 Concreting work 5.0d 0.0d 11-Jan-18 08:00 AM A 12-Mar-18 05:00 PM A 100% 100%
Wall & Top Slab 114.0d 36.0d -22.0d 17-Jan-18 08:00 AM A 01-Jun-18 04:00 PM 100% 40%
A1170 Frame 24.0d 0.0d 17-Jan-18 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1180 External finishes 18.0d 18.0d -22.0d 21-Apr-18 08:00 AM 12-May-18 05:00 PM 100% 0%
A1190 Internal finishes 18.0d 18.0d -22.0d 13-May-18 08:00 AM 01-Jun-18 04:00 PM 100% 0%
Backfilling & Compaction 18.0d 18.0d -22.0d 13-May-18 08:00 AM 01-Jun-18 04:00 PM 100% 0%
A1210 Backfill, level & compact 18.0d 18.0d -22.0d 13-May-18 08:00 AM 01-Jun-18 04:00 PM 100% 0%
Testing 6.0d 6.0d -22.0d 02-Jun-18 08:00 AM 07-Jun-18 05:00 PM 100% 0%
A1200 Cleaning & Water Tighness Testing 6.0d 6.0d -22.0d 02-Jun-18 08:00 AM 07-Jun-18 05:00 PM 100% 0%
Platform Structure 203.0d 91.0d -101.0d 06-Dec-17 08:00 AM A 04-Aug-18 05:00 PM 100% 13.33%
Dewatering Container (Geotube) 203.0d 91.0d -101.0d 06-Dec-17 08:00 AM A 04-Aug-18 05:00 PM 100% 13.33%
Substructure (Drain & Slab) 143.0d 31.0d -101.0d 06-Dec-17 08:00 AM A 27-May-18 05:00 PM 100% 27.37%
A1220 Install reinforcement 26.0d 26.0d -101.0d 06-Dec-17 08:00 AM A 21-May-18 05:00 PM 100% 30%
A1230 Install formwork 26.0d 26.0d -101.0d 10-Dec-17 08:00 AM A 21-May-18 05:00 PM 100% 30%
A1240 Concreting work 5.0d 5.0d -101.0d 22-May-18 08:00 AM 27-May-18 05:00 PM 100% 0%
Ramp 24.0d 24.0d -101.0d 28-May-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
A1250 Formwork, reinforcement, concrete & cover 24.0d 24.0d -101.0d 28-May-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
Geotube 36.0d 36.0d -101.0d 24-Jun-18 08:00 AM 04-Aug-18 05:00 PM 100% 0%
A1260 Preparation & installation 36.0d 36.0d -101.0d 24-Jun-18 08:00 AM 04-Aug-18 05:00 PM 100% 0%
Building 203.0d 91.0d -71.0d 06-Dec-17 08:00 AM A 04-Aug-18 05:00 PM 100% 7.54%
Polymer Plant 203.0d 91.0d -71.0d 06-Dec-17 08:00 AM A 04-Aug-18 05:00 PM 100% 7.54%
Substructure (Footing, Stump, Ground Beam & Slab) 143.0d 31.0d -71.0d 06-Dec-17 08:00 AM A 27-May-18 05:00 PM 100% 27.37%
A1270 Install reinforcement 26.0d 26.0d -71.0d 06-Dec-17 08:00 AM A 21-May-18 05:00 PM 100% 30%
A1280 Install formwork 26.0d 26.0d -71.0d 10-Dec-17 08:00 AM A 21-May-18 05:00 PM 100% 30%
A1290 Concreting work 5.0d 5.0d -71.0d 22-May-18 08:00 AM 27-May-18 05:00 PM 100% 0%
Frame (Upper Beam & Column) 24.0d 24.0d -71.0d 28-May-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
A1300 Scaffold, stagging, formwork, reinforcement, t-prox, soffit & concrete
24.0d 24.0d -71.0d 28-May-18 08:00 AM 23-Jun-18 05:00 PM 100% 0%
Ramp & Drain 18.0d 18.0d -71.0d 24-Jun-18 08:00 AM 14-Jul-18 05:00 PM 100% 0%
A1310 Excavation, levelling, formwork, reinforcement & concrete 18.0d 18.0d -71.0d 24-Jun-18 08:00 AM 14-Jul-18 05:00 PM 100% 0%
Roof 18.0d 18.0d -71.0d 24-Jun-18 08:00 AM 14-Jul-18 05:00 PM 100% 0%
A1320 Install roof truss & covering 18.0d 18.0d -71.0d 24-Jun-18 08:00 AM 14-Jul-18 05:00 PM 100% 0%
Wall 18.0d 18.0d -71.0d 24-Jun-18 08:00 AM 14-Jul-18 05:00 PM 100% 0%
A1330 Scaffold, stagging, formwork, reinforcement & concrete 18.0d 18.0d -71.0d 24-Jun-18 08:00 AM 14-Jul-18 05:00 PM 100% 0%
Drawing & Material Approval 24.0d 0.0d 22-Nov-17 08:00 AM A 19-Dec-17 05:00 PM A 100% 100%
A1440 Submission of Drawing / Material for approval 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A1450 Review & approval for Drawing / Material 12.0d 0.0d 06-Dec-17 08:00 AM A 19-Dec-17 05:00 PM A 100% 100%
Wash Water Collection & Sludge Balancing Tank 154.0d 42.0d -16.0d 06-Dec-17 08:00 AM A 07-Jun-18 05:00 PM 94.05% 61.9%
Procurement 102.0d 30.0d -22.0d 06-Dec-17 08:00 AM A 26-May-18 05:00 PM 100% 92.86%
A1460 Horizontal Screw Pump, Subermisble Supernatant Pump 72.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1470 FAT Wash Water Recovery Pumpset 6.0d 0.0d 05-Mar-18 08:00 AM A 27-Mar-18 05:00 PM A 100% 100%
A1480 Pipes, Fittings & Valves 30.0d 0.0d 05-Mar-18 08:00 AM A 31-Mar-18 05:00 PM A 100% 100%
A1490 Submersible Mixer 30.0d 0.0d 05-Mar-18 08:00 AM A 31-Mar-18 05:00 PM A 100% 100%
A1500 Crane / Lifting Equipment, High Pressure Rubber Hose 30.0d 30.0d -22.0d 05-Mar-18 08:00 AM A 26-May-18 05:00 PM 100% 60%
Installation 42.0d 42.0d -16.0d 21-Apr-18 08:00 AM 07-Jun-18 05:00 PM 76.19% 0%
A1510 Construction of Horizontal Screw Pump Pit 24.0d 24.0d -16.0d 21-Apr-18 08:00 AM 19-May-18 05:00 PM 100% 0%
A1520 Horizontal Screw Pump, Subermisble Supernatant Pump 18.0d 18.0d -16.0d 20-May-18 08:00 AM 07-Jun-18 05:00 PM 55.56% 0%
A1530 Pipes, Fittings & Valves 18.0d 18.0d -16.0d 20-May-18 08:00 AM 07-Jun-18 05:00 PM 55.56% 0%
A1540 Submersible Mixer 12.0d 12.0d -16.0d 20-May-18 08:00 AM 01-Jun-18 04:00 PM 83.33% 0%
A1550 Crane / Lifting Equipment, High Pressure Rubber Hose 12.0d 12.0d -22.0d 27-May-18 08:00 AM 07-Jun-18 05:00 PM 83.33% 0%
Existing Sedimentation Tank 160.0d 48.0d -28.0d 06-Dec-17 08:00 AM A 14-Jun-18 05:00 PM 100% 65.22%
Procurement 60.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1560 Submersible Sludge Pump 60.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
A1570 Pipes, Fittings & Valves 30.0d 0.0d 06-Dec-17 08:00 AM A 10-Apr-18 05:00 PM A 100% 100%
Installation 48.0d 48.0d -28.0d 21-Apr-18 08:00 AM 14-Jun-18 05:00 PM 100% 0%
A1580 Submersible Sludge Pump 24.0d 24.0d -28.0d 21-Apr-18 08:00 AM 19-May-18 05:00 PM 100% 0%
A1590 Pipes, Fittings & Valves 24.0d 24.0d -28.0d 20-May-18 08:00 AM 14-Jun-18 05:00 PM 100% 0%
Polymer Plant 244.0d 132.0d -112.0d 06-Dec-17 08:00 AM A 20-Sep-18 05:00 PM 85.61% 25.86%
Engineering Design 18.0d 0.0d 06-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
A1600 Engineering design for Polymer Plant & Dosing System 18.0d 0.0d 06-Dec-17 08:00 AM A 27-Dec-17 05:00 PM A 100% 100%
Procurement & Delivery 60.0d 60.0d -52.0d 06-Dec-17 08:00 AM A 28-Jun-18 05:00 PM 100% 60%
A1610 Metering Pumps (Diaphragm type) 60.0d 60.0d -112.0d 06-Dec-17 08:00 AM A 28-Jun-18 05:00 PM 100% 60%
A1620 Crane / Lifting Equipment 30.0d 30.0d -22.0d 06-Dec-17 08:00 AM A 26-May-18 05:00 PM 100% 60%
A1630 Static Mixer & Sludge Blender 30.0d 30.0d -22.0d 06-Dec-17 08:00 AM A 26-May-18 05:00 PM 100% 60%
Fabrication 36.0d 36.0d -88.0d 30-Jun-18 08:00 AM 09-Aug-18 05:00 PM 100% 0%
A1640 Mixing & Service Tank 36.0d 36.0d -112.0d 30-Jun-18 08:00 AM 09-Aug-18 05:00 PM 100% 0%
A1650 Hopper, Feeder & Pump Skid 36.0d 36.0d -112.0d 30-Jun-18 08:00 AM 09-Aug-18 05:00 PM 100% 0%
A1660 Local Control Panel 30.0d 30.0d -82.0d 30-Jun-18 08:00 AM 02-Aug-18 05:00 PM 100% 0%
Installation 36.0d 36.0d -112.0d 11-Aug-18 08:00 AM 20-Sep-18 05:00 PM 44.44% 0%
A1670 Mixing & Service Tank 24.0d 24.0d -112.0d 11-Aug-18 08:00 AM 06-Sep-18 05:00 PM 66.67% 0%
A1680 Hopper, Feeder & Pump Skid 24.0d 24.0d -112.0d 11-Aug-18 08:00 AM 06-Sep-18 05:00 PM 66.67% 0%
A1690 Dosing Pipeworks 24.0d 24.0d -112.0d 11-Aug-18 08:00 AM 06-Sep-18 05:00 PM 66.67% 0%
A1700 Local Control Panel 12.0d 12.0d -112.0d 08-Sep-18 08:00 AM 20-Sep-18 05:00 PM 0% 0%
A1710 Crane / Lifting Equipment 12.0d 12.0d -112.0d 08-Sep-18 08:00 AM 20-Sep-18 05:00 PM 0% 0%
A1720 Static Mixer & Sludge Blender 12.0d 12.0d -112.0d 08-Sep-18 08:00 AM 20-Sep-18 05:00 PM 0% 0%
Pipeworks 154.0d 30.0d -17.0d 20-Dec-17 08:00 AM A 21-Jun-18 05:00 PM 100% 30.77%
Procurement 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
A1730 To procure & deliver 200mm Pipes to site 24.0d 0.0d 20-Dec-17 08:00 AM A 29-Mar-18 05:00 PM A 100% 100%
Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A1870 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM A 21-Nov-17 05:00 PM A 100% 100%
A1880 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
Switchboard / MCC Panel 223.0d 99.0d -79.0d 22-Nov-17 08:00 AM A 13-Aug-18 05:00 PM 88.57% 44.35%
A1890 Procurement & fabrication of Panel 84.0d 84.0d -118.0d 22-Nov-17 08:00 AM A 26-Jul-18 05:00 PM 100% 60%
A1900 FAT Electrical Control & Swicthboards 1.0d 1.0d -79.0d 27-Mar-18 08:00 AM A 30-Jun-18 05:00 PM 100% 60%
A1910 Installation works 30.0d 30.0d -79.0d 10-Jul-18 08:00 AM 13-Aug-18 05:00 PM 40% 0%
Submain Cabling Works for MCC-SDP-Palong 178.0d 54.0d -118.0d 05-Mar-18 08:00 AM A 27-Sep-18 05:00 PM 78.79% 26.67%
A1920 Procurement & delivery of Cable 24.0d 24.0d -118.0d 05-Mar-18 08:00 AM A 23-Aug-18 05:00 PM 100% 60%
A1930 Installation & cabling works 30.0d 30.0d -118.0d 25-Aug-18 08:00 AM 27-Sep-18 05:00 PM 53.33% 0%
Distribution & Earthing System 178.0d 54.0d -118.0d 05-Mar-18 08:00 AM A 27-Sep-18 05:00 PM 78.79% 26.67%
A1940 Procurement & delivery 24.0d 24.0d -118.0d 05-Mar-18 08:00 AM A 23-Aug-18 05:00 PM 100% 60%
A1950 Installation & cabling works 30.0d 30.0d -118.0d 25-Aug-18 08:00 AM 27-Sep-18 05:00 PM 53.33% 0%
Compound Lighting System 178.0d 54.0d -118.0d 05-Mar-18 08:00 AM A 27-Sep-18 05:00 PM 78.79% 26.67%
A1960 Procurement & delivery 24.0d 24.0d -118.0d 05-Mar-18 08:00 AM A 23-Aug-18 05:00 PM 100% 60%
A1970 Installation & cabling works 30.0d 30.0d -118.0d 25-Aug-18 08:00 AM 27-Sep-18 05:00 PM 53.33% 0%
Relocation of Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM A 31-Dec-17 05:00 PM A 53.33% 100%
A1980 To relocate existing Cable 30.0d 0.0d 11-Dec-17 08:00 AM A 31-Dec-17 05:00 PM A 53.33% 100%
Miscellaneous Works 30.0d 30.0d -118.0d 25-Aug-18 08:00 AM 27-Sep-18 05:00 PM 53.33% 0%
A1990 Any other neccessary works 30.0d 30.0d -118.0d 25-Aug-18 08:00 AM 27-Sep-18 05:00 PM 53.33% 0%
Instrumentation Works 250.0d 114.0d -96.0d 08-Nov-17 08:00 AM A 30-Aug-18 05:00 PM 90.7% 54.24%
Drawing & Material Approval 24.0d 0.0d 08-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
A2000 Submission of Drawing / Material for approval 12.0d 0.0d 08-Nov-17 08:00 AM A 21-Nov-17 05:00 PM A 100% 100%
A2010 Review & approval for Drawing / Material 12.0d 0.0d 22-Nov-17 08:00 AM A 05-Dec-17 05:00 PM A 100% 100%
Procurement & Fabrication 84.0d 84.0d -96.0d 22-Nov-17 08:00 AM A 26-Jul-18 05:00 PM 100% 60.47%
A2020 To procure & fabricate Instrument Panel 84.0d 84.0d -96.0d 22-Nov-17 08:00 AM A 26-Jul-18 05:00 PM 100% 60%
A2030 FAT 1.0d 0.0d 07-Feb-18 08:00 AM A 01-Mar-18 05:00 PM A 100% 100%
Installation 30.0d 30.0d -96.0d 28-Jul-18 08:00 AM 30-Aug-18 05:00 PM 40% 0%
A2040 Installation & signal cabling works 30.0d 30.0d -96.0d 28-Jul-18 08:00 AM 30-Aug-18 05:00 PM 40% 0%
Infrastructure Works 24.0d 24.0d -101.0d 12-Aug-18 08:00 AM 08-Sep-18 05:00 PM 57.89% 0%
Training, Testing, Commissioning & Maintenance 17.0d 17.0d -118.0d 29-Sep-18 08:00 AM 17-Oct-18 05:00 PM 0% 0%
A2070 Preparation of testing & report 12.0d 12.0d -118.0d 29-Sep-18 08:00 AM 11-Oct-18 05:00 PM 0% 0%
A2080 Pre-commissioning 6.0d 6.0d -118.0d 29-Sep-18 08:00 AM 04-Oct-18 05:00 PM 0% 0%
A2090 Setting to work 3.0d 3.0d -118.0d 06-Oct-18 08:00 AM 08-Oct-18 05:00 PM 0% 0%
A2100 Commissioning & training 7.0d 7.0d -118.0d 09-Oct-18 08:00 AM 16-Oct-18 05:00 PM 0% 0%
A2110 Handing over to Client 1.0d 1.0d -118.0d 17-Oct-18 08:00 AM 17-Oct-18 05:00 PM 0% 0%