1 The Balance work quantities and amounts are to be calculated as on 01.07.2017 excluding pending bills including sub works if any.
2 The taxable input materials are to be identified eg. Bitumen, Cement, Steel
3 Tax payable for the materials is to be calculated which is ITC.
4 Net effect of GST is to be arrived.
The Calculations can be done as shown below: (MODEL FOR GUIDANCE) Rs in Lacs.
Taxable Inputs ( amount of Bitumen, Cement, Steel etc) Input Tax Credit
Balance
amount of
work as on
Sl. 01- 07- 2017 Cost of on
Name of Work Hire on Metal on Sand on Steel at on Cement
No. (excluding Metal labour Bitumen
Sand Steel Cement Bitumen charges of compone at (col.4x at(col.5x (col.6x at (col.7x
pending bills at (col.8x
machinery 5% 5%) 18%) 28%)
and including nt 18%
sub works)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
G.O.130
Widening and
strengthening of
existing Single lane to
1 Double lane road of 1961.66 1149.63 13.89 23.09 109.47 186.83 417.99 51.19 57.48 0.69 4.16 30.65 33.63
Deverkadra-Kothapally
road from Km.10/0 to
32/4 in Mahabubnagar
District
G.O.129
G.O.99
Widening of Makthal-
6 Anugonda road from
Km.0/0 to 22/0 in
Mahabubnagar District
Widening of Branch
7 road to Krishna from
Km 0/0 to 9/2 in
Mahabubnagar District
Improvements to
Krishna to Thangadi
road from Km 0/0 to
8 3/0 in (working reach
from Km 0/0 to 2/4)
road in Mahabubnagar
District under Krishna
Pushkaralu
Improvements to
Dandu - Mustipally
9 road from Km. 0/0 to
15/0 in Mahabubnagar
District
Emergency repairs of
(R&B) inspection
10 Bunglow at makthal in
Mahabubnagar District
( Under Krishna
Pushkaralu)
Emergency Repairs of
(R&B) Inspection
11 Bnglow at Krishna in
Mahabubnagar District
(Under Krishna
Pushkaralu)
MLA building
Construction of
Residence cum Office
for Hon'ble MLA at
12 Makthal, Makthal
Constituency
Headquarters in
Mahabubnagar District
HLB's
Construction of HLB at
13 Km 2/0-2 of Makthal-
Anugonda road in
Mahabubnagar District
Construction of HLB at
14 11/2-4 of Dandu -
Mustipally road in
Mahabubnagar District
Construction of High
Level Bridge at Km
15 14/2-4 of Amarchintha
- Jaklair road in
mahabubnagar District
Construction of HLB at
Km 7/8-10 of
16 Nellikondi - Allipur
road in Mahabubnagar
District
Work Contracts
b works if any.
16 17 18 19 20
Sand
Avg Rate of
Agreement Work done
Description Coef metal per Amount
Qty Qty cum
1 VCC(1:4:8) 0.45 700 0 576.61 181632.15
2 VCC M15 0.45 783.45 0 576.61 203285.297
3 VRCC M20 0.45 2003.88 0 576.61 519955.7611
4 VRCC M30 0.45 100.8 0 576.61 26155.0296
5 VRCC M35 0.45 1765.74 0 576.61 458164.5036
1389192.741
Steel
Cement
Bitumen
41798532.39
recorded
Agt qty qty
27050.27
38495.52
4455.4
700
783.45
2003.88
100.8
1765.74
177.88
203.21
991.8
991.8
700
783.45
2003.88
100.8
1765.74
1.4
6
21.27
38.75
700
783.45
2003.88
100.8
1765.74
4455.4
148513.4
148513.4
4455.4
991.8
991.8
Amount of
labour
45227 34.79
714660.5556 197906
55953.4392 34539.16
453458.8332 139956.43
135.4166667 50
364691.7401 27050.27
691995.4675 38495.52
153216.7739 4455.4
245947.3333 700
370467.39 783.45
39033.806 665.16
633125.312 1338.72
4436.46 75.6
164717.8782 2683.43
0 177.88
62630.2224 76378.32
27564.08704 148513.4
27564.08704 148513.4
4159.4 1.4
14622 6
56505.40046 5217.89
40607.456 208.03
110700 922.5
373861.6896 1644.36
409588.04 1072.22
54297.712 203.21
5119167.5
Metal
Avg Rate of
Agreement
Description Coef metal per Amount
Qty cum
1 GSB 1.28 27050.27 973.7003906 33713738.84
2 WMM 1.32 38495.52 1011.308754 51388730.41
3 BC 1.471 4455.4 3564.600228 23361926.76
4 VCC(1:4:8) 0.9 700 1061.608889 668813.6
5 VCC M15 0.9 783.45 1226.608889 864888.0606
6 VRCC M20 0.9 2003.88 1287.608889 2322192.33
7 VRCC M30 0.9 100.8 1409.608796 127879.71
8 VRCC M35 0.9 1765.74 1409.608796 2240102.372
9 Rough stone revetment 1.2 177.88 419.1083333 89461.1884
Filter media 1.2 203.21 754 183864.408
6 25mm thick mawc 0.027429 991.8 24.35142857 662.4479138
25mm thick mawc 0.010286 991.8 74.74285714 762.4796473
114963022.6
Sand
Avg Rate of
Agreement
Description Coef metal per Amount
Qty cum
1 VCC(1:4:8) 0.45 700 576.61 181632.15
2 VCC M15 0.45 783.45 576.61 203285.297
3 VRCC M20 0.45 2003.88 576.61 519955.7611
4 VRCC M30 0.45 100.8 576.61 26155.0296
5 VRCC M35 0.45 1765.74 576.61 458164.5036
1389192.741
Steel
Cement
Bitumen
12 VRCC M20 Curtain walls & 1338.72 519.1333333 694974.18 472.93 633125.312
Body wall
13 VRCC M30 75.6 471.9416667 35678.79 58.68 4436.46
14 VRCC M35 2683.43 471.9416667 1266422.43 61.38 164717.878
15 Rough stone revetment 177.88 0.00 0
16 Scarifying 76378.32 5.8133 444010.09 0.82 62630.2224
17 PC 148513.4 1.372285714 203802.82 0.1856 27564.087
18 TC 148513.4 1.558571429 231468.74 0.1856 27564.087
19 HYSD TIE RODS 1.4 2971 4159.4
20 MS 6 2437 14622
EWE PIPE CULVERT &
21 5217.89 13 67832.57 10.8291666667 56505.4005
Bridges
22 Dismantling 208.03 284.52 59188.70 195.2 40607.456
23 hume pipes 922.5 120 110700
24 granular filling 1644.36 15.12 24862.72 227.36 373861.69
25 RSR & apron 1072.22 382 409588.04
26 filter media 203.21 3.8 772.20 267.2 54297.712
40847645.16 5073940.5
%age on recorded
9.95 agt qty pending GSt
Ecv qty