MATERIAL REQUISITION REVIEW CHECKLIST

BRIEF DESCRIPTION : LIGHTING POLES & FIXTURES


CONTRACTOR MR NO. : ADDAR-MR-011
SA-DUMMY PO NO.
ELEMENT YES NO NA REMARKS
ITEM DESCRIPTION STANDARDIZED TO SAMSS
9COM: 6000001008, 6000000983,
CATALOGUED, CCC, INSPECTABLE ITEMS
IDENTIFIED 6000000897
SPECIFICATION ARE CORRECT, STNDS.,
DRAWINGS ARE REFERENCED IN ITEM
DESCRIPTION.
SAMSS/SAES ARE REFERENCED AND
APPLICABLE INTERNATIONAL STANDARDS.
REQUIRED DATA SHEET ATTACHED (IF
APPLICABLE)

REVISION DATE OF SAMSS/SAES ARE


SPECIFIED

PROJECT DRAWING SHEETS INITIALED

CORRECT INSPECTION CODE (SA-175)


IDENTIFIED AND ATTACHED.
INSPECTION AND TEST REQUIREMENTS ON SA-
175 SPECIAL DESCRIBED (IF APPLICABLE)
APPLICABLE NMR ATTACHED (SA FORM 7900-
7930), SUFFICIENT QTY 601, 602 & 603'S
REQUESTED.
SPARE PARTS DATA PACKAGE
REQUIREMENTS; SAEP-3101; ESP.

HAZARDOUS, HEAVY LIFT, SPECIAL MATERIAL


REQUIREMENTS.

CAPITAL SPARES/START-UP/COM SPARE


PARTS/PROCESS & OP. MATERIALS, SPECIAL
TOOL MAINTENANCE EQUIPMENT.
VENDOR REPRESENTATIVE FOR SAFE START-
UP

ENGLISH LANGUAGE NOTE

VENDOR MR DEVIATION STATEMENT.

SPECIAL REQUIREMENTS(LIST)

"SCHEDULE Q" LEVEL OF INSPECTION.


NOTE: Level of Inspection shall be as per SAEP- LEVEL-0
1151, unless approved by VID