You are on page 1of 1

TABEL RAB PEKERJAAN DINDING

HARGA SATUAN JUMLAH HARGA TOTAL HARGA


NO URUTAN PEKERJAAN VOL SAT
UPAH BAHAN UPAH BAHAN (UPAH+BAHAN)
1 2 3 4 5 6 7 = (3x5) 8 = (3x6) 9 = (7+8)
E PEKERJAAN DINDING
E.1 Pemasangan Dinding Bata Merah (5x11x22) Tebal 1 Bata Campuran 1PC : 4PS 1767.508 m² Rp 85,550.00 Rp 160,923.92 Rp 151,210,266.63 Rp 284,434,242.60 Rp 435,644,509.22
E.2 Pemasangan Plesteran Campuran 1PC : 4PS tebal 15 mm 3535.015 m² Rp 48,840.00 Rp 11,854.13 Rp 172,650,132.60 Rp 41,904,520.29 Rp 214,554,652.89
E.3 Pemasangan Dinding Bata Merah (5x11x22) Tebal 1 Bata Campuran 1PC : 2PS 215.88 m² Rp 85,550.00 Rp 182,546.14 Rp 18,468,534.00 Rp 39,408,060.70 Rp 57,876,594.70
E.4 Pemasangan Plesteran Campuran 1PC : 2PS tebal 15 mm 431.76 m² Rp 48,840.00 Rp 16,808.55 Rp 21,087,158.40 Rp 7,257,257.65 Rp 28,344,416.05
E.5 Pemasangan Acian 3800.664 m² Rp 32,560.00 Rp 4,483.05 Rp 123,749,603.56 Rp 17,038,564.50 Rp 140,788,168.06
TOTAL HARGA RAB PEKERJAAN DINDING Rp 487,165,695.19 Rp 390,042,645.75 Rp 877,208,340.93

TABEL BIAYA UPAH PEKERJAAN DINDING


No Tenaga Kerja Satuan Jumlah Kebutuhan Harga Satuan (Rp) Biaya Upah
1 2 3 4 5 6 = (4 x 5)
1 Pekerja oh 3140.1977 Rp 95,600.00 Rp 300,202,900.12
2 Tukang Batu oh 1371.7601 Rp 109,300.00 Rp 149,933,378.93
3 Kepala Tukang oh 137.17601 Rp 120,000.00 Rp 16,461,121.20
4 Mandor oh 157.009885 Rp 131,000.00 Rp 20,568,294.94
TOTAL BIAYA UPAH PEKERJAAN DINDING Rp 487,165,695.19

TABEL BIAYA BAHAN PEKERJAAN DINDING


No Bahan Satuan Jumlah Kebutuhan Harga Satuan (Rp) Biaya Upah
1 2 3 4 5 6 = (4 x 5)
1 Bata merah bakar kelas I bh 277674.25 Rp 798.00 Rp 221,584,051.50
2 Semen Tiga Roda kg 95143.06834 Rp 1,379.40 Rp 131,240,348.47
3 Pasir pasang m³ 275.1241575 Rp 135,278.00 Rp 37,218,245.78
TOTAL BIAYA BAHAN PEKERJAAN DINDING Rp 390,042,645.75