Date : 09 – 19 -18

PROJECT STATUS

Attn : Maam Ely


CC : Sir Mahlon
Project : SOTO GRANDE
Location : MA-A , DAVAO

Re : ITEMS INSTALL

I. Concern's / Scope of Work :

For the last 3 weeks we stay her on davao , we already started installing the headboard , bedbunk and the
crown part of the closet .
The following floor are already been started for installation :

3th floor : with headboard and bedbunk 4th floor with headboard and bedbunk
# 301 # 410 # 412
II. Deliveries : # 302 # 409 ( crown was also install ) # 403
# 303 # 408
# 305 # 407
# 316 # 413
# 317 # 404
7 floor with headboard and bedbunk
th

#703
# 704
but on September 18 , 2018 , all the headboard of 7th floor and 4th floor are already install. Right now they are still working
on 3th floor , to install all the remaining headboard that need to be install.,

The status of 5th floor and 6th floor , are still working such as the paintor and also the tiles contractor ..so sir romy told the paint and tiles
contractor to prioritized the 5th floor - 6th floor so that we can start installing on that floor.

Page 1
Sheet1

Merigen B. Bongcars
Prepared by:

Page 2
Sheet1

dbunk and the

now they are still working

ir romy told the paint and tiles

Page 3
Sheet1

Project In – charged
Received by: