Project Bekaert steel tire cord manufacture project

Location VSIP Quang Ngai, Vietnam


The current tracking revision 4 VARIATION ORDER TRACKING FILE
The current tracking date 11/3/2020

Variation number Content VO 1st submission date VO latest Latest submission Latest revision Design team's approval Project team's approval Commercial approval Status Approved value Remark
submisison date value (current) Date By Date By Date By
Adding of 04 steel staircases and 08 ladders inside of Approved with
VO #1 19/Nov/19 19/Nov/19 597,134,766 0 12/13/2019 Pieter Johanes Tony - Shall be stored
the final production building note
Changing of the wall design from 02 walls of 100mm
VO #2 19/Nov/19 19/Nov/19 (468,938,808) 0 12/13/2019 Pieter Johanes Tony Approved (468,938,808) The work has been done on site
thickness to 01 wall of 200mm thickness.

Changing of the RR Lab. & Office's window to acoustic Design Bekaert will review the design proposal but
VO #3 R3 7/13/2020 8/18/2020 121,808,002 9/22/2020 Pieter On hold On hold Not approved -
type, relocating of the doors. execution will be in 2022.

Adding the roof life-line, extending the roof safety rail


VO #4 R2 Adding the safety rail on the concrete roof of the RR 26/Mar/19 11/3/2020 3,658,867,516 1 Progress Progress Progress On progress - - Apprved by Bekaert Risk management
office

The new ground slab design - Final production building


VO #5 (B01.1, B01.2, B02, B03 : Changing in B04) 30/Mar/19 Replaced - To be replaced by VO #5.1, VO #5.2, VO #5.3 & VO #5.4

Bekaert require to execute the sparepart area.


Changing ground slab design at Technical Facility & Approved for Pieter to confirm catch pit execution or not; Not todo
VO #5.1 R2 Office Production Building (B03 + B04) 7/13/2020 8/18/2020 918,133,091 9/22/2020 Pieter On hold On hold sparepart area - Mario:postpone and keep the corner free (no action).
Ask Mr Phuc why the floor load is VO?
VO #5.2 R2 Dyke wall 8/18/2020 128,059,428 On hold On hold On hold Not approved - Waiting for approval from client.
Design Bekaert will review the design proposal but
VO #5.3 Transformer oil retention tank On hold On hold On hold Not approved - execution will be in 2022.

Dinco to explain the situation to have the approval from


VO #5.4 Changing in ground slab design of B1.1 & B1.2 On hold On hold On hold Not approved - Bekaert design team.
VO #6 Additional CSA work for the sample making room 7/13/2020 On hold On hold On hold Not approved - The sample making project on hold
VO #7 Additional underground trench & piping work for the 7/13/2020 7/22/2020 653,693,910 9/22/2020 Pieter 9/22/2020 Johanes On hold On hold - The trench already done; Bekaert ask to hold.
Lab
Reduction of VO for fire-rated 120' wall 100mm and
VO #8 8/17/2020 (938,328,693) 9/22/2020 Pieter 9/22/2020 Johanes Progress Approved (938,328,693) - Bekaert site will approach Tony for approval.
200mm thickness
Adding of the steel staircase for the maintenance work
VO #9 On hold On hold On hold Not approved - Check if this is a part of tender; Ask Mr Phuc why this is VO?
at the cooling tower areas
Adding of the separation wall inside of the electrical
Design Bekaert will review the design proposal but
VO #10 room in technical facility (B03), new utility room for RR On hold On hold On hold Not approved -
execution will be in 2022.
lab (B04) as following Ree's design

VO #11 Adjustment price of Backfill K=0.95 to Backfill K=0.90 (25,523,562) - Submitted to BVN. Waiting for approval.

Combined 02 times of change:


- First change: changing of insulation types, changing of SUS
VO #12 Changing wire mesh which is underneath of roof 2,245,027,789 Pieter Johanes Tony Approved 2,245,027,789 201 mesh to galvanized steel mesh
insullation
- Second change: changing of galvanized steel mesh to SUS
304

VO #13 New Penstock gate 11/2/2020 11/2/2020 593,880,000 Not approved - Submitted to BVN with 4 options. Waiting for approval.

Covering Opening by temporary plywood or aluminum


VO #14 sheet. 11/3/2020 11/3/2020 795,514,375 Not approved -

Accumulation value 8,279,327,814 837,760,288