Name of Date of Date of Date of Total time Total cost Total cost impact Change order
S.No. Package/Contract Extra Item Description Justification / Reason Recommend taken for Remarks
Contractor/ Agency submission ation approval approval impact (R0) (R1) prepared (Y/N)
Due to change in the drawing 3. For R-0 & R-1, Cost Deviation is
(offset at grid 20), change of lift with Client for process.
4 Rebaring opening, addition of grid at 9-Mar-11 19-Apr-11 7-Sep-11 461,410.00 966,055.00 No
L-M/00-10 etc. due to Design
change.
Civil Structural Work M/s. B. L. Kashyap & Additional for providing and laying M7.5
6 Sons Ltd. (1:4:8) concrete from outsource batching
plant.
Additional for providing and laying M25
Not Approved by FISPL as they are Reply given to
not payable as per our terms & 27-Feb-12 BLK on 22 N. A. No Reply given to BLK on 22 March 2012
7 and above grade concrete from outsource
conditions March 2012
batching plant.
Providing extra additional for slab
8 thickness more than 200mm th. And upto
300mm.
12 Providing & laying of 12mm th internal 26-Apr-12 7-Nov-12 pending - 93,090.00 No Submitted to client
plaster
Qty. not taken in BOQ
13 Providing & laying of 15mm th internal 26-Apr-12 7-Nov-12 pending - 135,121.00 No
plaster
This Item was not in BOQ . There
is an item of 50X6 mm Cu strip for
equipment body earthing as well.
We felt that body earthing can be
done with 50x6 GI strip where we
can save substantial amount. We
raised the point and got the
approval from MEP consultant to
go ahead with GI Earthing. Cost of
50x6 mm Cu strip as per BOQ Rate
is Rs2123 X 1700 m = Rs3609100,
Low Side Electrical cost of GI strip is Rs246 X 1700 m
14 B E Contracts (P) Ltd. Eathing Installation Earth G.I. strip = Rs418200. Hence net saving is Rs 27-Oct-12 30-Oct-12 9-Nov-12 10 -3,190,900.00 Yes Approved by Logix
Work
3190900/- by using GI strip.
Note 1 : Client has taken the time for the approval of the Qty. and Rate of Extra Items.