Recavery Plan Of R.W.

I
Last revised due to the
Last approved depend on mitigation plan with Mr.
the letter No. 28 Ko
Actual Estimated time to
No. Activity Start Finish Progress Start Finish Remark
Progress Finish the Activity
Precast All FDN of
1 Concrete Sleeper 10-Apr-18 9-Feb-19 50% 20-Aug-18 1-Feb-18 35% 15-Mar-19 Sleepers in the shope(Inc.
Rebar for Pedestal)

2 Local Pipe Support Foundations 18-Aug-18 14-Mar-19 11% 23-Dec-18 29-Jul-19 0% 1-Mar-19

Interface with Sludge


3 FDN for 60-K-001-A/B Air Compressor 24-Jun-18 22-Jul-18 100% 26-Jul-18 30-Aug-18 80% 25-Dec-18 Basin (Backfiling) & Piping
GRV

Interface with Sludge


4 FDN for Compressor Shelter 4-Jul-18 3-Aug-18 100% 7-May-18 9-Jul-18 70% 1-Jan-19 Basin
5 Sludge Basin (60-BA-002) 12-Feb-18 24-May-18 100% 23-Mar-18 29-Oct-18 82% 22-Oct-18
6 Recycled Water Basin (60-BA-003) 23-Feb-18 3-Jun-18 100% 15-Mar-18 25-Aug-18 82% 22-Oct-18
7 Thickening Basin (60-BA-004 A/B) 22-Apr-18 1-Nov-18 73% 10-Jun-18 28-Dec-18 65% On time

Ali Hadi