You are on page 1of 3

Rebar inspection

Establish a checklist of procedures and determine


minimum requirements for inspection acceptance
ontractors should understand requirements for inspection accep- Material inspection
C the process of rebar inspection,
whether the inspection is done by
tance should be established. In-place inspection of rebar starts
with the mill test report and may be
their own forces or by an inspector Checklist supplemented by a report from an
representing the owner or building The list should cover (but not be independent testing laboratory. Re-
official. The goal of inspection or limited to) the following: ports should state grade of steel, ten-
quality-control programs is to ensure A construction schedule from sile properties, chemical composition
that contract documents and building the general contractor is important so (and carbon equivalent if rebar is to
codes are followed. The programs al- the inspector can follow the placing be welded), and spacing and height
so ensure structural safety and archi- crew and inspect in-place rebar be- of deformations. Compare these val-
tectural aesthetic compliance. fore the scheduled placing and fin- ues with those in the applicable
Inspection and testing do not add ishing of the concrete. ASTM standard. Examination of the
quality to the product, but only con- Certified mill test or bar coating bar mill markings will identify the
firm whether it meets the established reports may accompany material producing mill, the type and grade
criteria. Quality during construction is shipped to the jobsite. If the reports are of steel, and the bar size.
achieved mostly by the contractor’s sent to the contractor, they should still
quality-assurance program, involving be made available to the inspector. Reinforcing bar inspection
workers and field supervisors. The Independent testing laboratory Visually check bar diameter and
contractor’s inspectors are separate reports on samples taken at the fab- shape (if bent); measure bar lengths,
from the inspectors mandated by the ricator’s shop or the jobsite offer ver- spacing, embedment, and bearing on
owner or local building department. ification of the producer’s mill test a wall or beam. In a slab, count the
The contractor’s quality-control in- report. total number of pieces and measure
spection helps assure that the finished Approved placing drawings the slab bar spacing. Check these fig-
construction meets the owner’s re- should be available for review and ures against the approved placing
quirements. Inspections by the mater- study by field-placing personnel and drawings in conjunction with the
ial producer and supplier assure that the inspector at least 1 day before the structural drawings. Similarly, check
products meet material specifications. actual placing of the rebar. beam longitudinals, column verti-
Inspectors should be familiar with A material shipment schedule cals, and stirrup and tie spacings.
the project contract documents (espe- should be provided and updated as
cially structural and rebar placing necessary so in-place inspections can Bar supports
drawings) and building code re- be scheduled. Measure chair heights to verify
quirements, and have access to mate- Potential problems should be that the specified cover and clear-
rial standards and references, codes, discussed to identify difficult-to-place ances will be satisfied. It is extremely
and industry manuals or reports. details, lack of specifics on the con- important to check the chairs or
The inspection program should be tract documents, possible engineer- standees supporting slab and mat
established at a pre-construction con- ing drawing discrepancies, detailing top bars for height. The entire mat
ference. The size or complexity of the or placing errors, and approval of im- and cages also should be checked for
project determines the scope of the plemented field changes. stability, since they can easily be dis-
inspection program. This meeting Tolerances should be discussed to placed during concrete placement.
should be attended by representatives identify those which are critical, the Normally side supports are not pro-
of outside inspection agencies, the method of measurement, and the ba- vided unless called for in the contract
general contractor’s superintendent, sis for rejection or acceptance. documents. Where specifications re-
concrete subcontractor’s superinten- Periodic meetings should be quire corrosion-protection measures,
dent, the supplier’s representative, the held to discuss previous inspection verify the class of protection of the
ironworker foreman, and others, such reports, problems and solutions, and bar supports furnished.
as the architect, engineer, or engineer’s the schedule of upcoming work.
site representative. At the meeting, a
checklist of procedures and minimum
Rebar tying requirements Tolerances Inspection of bar placement in walls
Reinforcing bars are tied together to Tolerances establish permissible and slabs is usually straightforward.
form a rigid mat for footings, walls, variations in dimensions and loca- Ironworkers often shift rebar to avoid
and slabs. A rigid cage is formed tions, and should neither be overly obstructions, such as small openings,
when beam or column longitudinals restrictive or lenient. The engineer or pipe sleeves, electrical outlets, and sim-
are tied to the stirrups and ties. Iron- architect usually specifies the stan- ilar items. This usually is acceptable if
workers usually tie a minimum num- dard tolerances to be followed, nor- the total number of bars is not reduced.
ber of rebar intersections. If the speci- mally by reference to ACI 117. The Consult Appendix C in CRSI’s Manual
fications are not precise about the inspector will establish a range of ac- of Standard Practice to determine first
number of tied intersections, the work ceptability. Incompatible tolerances bar spacing, if that information is not
should be accepted unless it is appar- should be referred to the design pro- shown in the contract documents.
ent the mats or cages of reinforcing fessional for resolution.
steel will be displaced from their in- Fabricating tolerances for rebar are In-place bending and rebending
spected position during concreting. tabulated by ACI 117, the ACI Detail- One of the more controversial con-
The placer is responsible for tying ing Manual, and the Concrete Rein- struction procedures is the practice of
bars so they will remain in position. forcing Steel Institute (CRSI) Manual bending and rebending installed re-
Tack welding of rebar to rebar should of Standard Practice. Fabricating bar. CRSI’s EDR No. 12 can be used
not be allowed, and only coated tie shops do not have problems meeting as a guide.
wire should be used to tie coated bars. the recommended tolerances. Typi- When the contractor requests using
cally, the tolerance for length of planned prebent dowels or straight
Splices straight bars and out-to-out dimen- dowels, the engineer should accept
Length and location of lap splices sion of bars with hooks or bends at the procedure and notify the inspec-
should be specified in the contract one or both ends is 1 inch. tor. The inspector should discuss the
documents and on the approved plac- Placing tolerances recognize the im- bending procedure for straight dow-
ing drawings. If mechanical connec- precise nature of the placing opera- els with the placing foreman to assure
tions are required in lieu of lap splices, tion and allow deviation criteria. ACI that the bends conform to ACI 315.
the placing foreman or the mechanical 117 indicates bar placing tolerances Where large diameter bars are in-
connection supplier should provide including clear distance to forms and volved, some preheating may be rec-
the inspector with evidence that the resulting concrete surfaces (varies ommended by the designer to avoid
architect or engineer has approved use with member size, 1⁄2 inch for mem- brittle failure.
of the connection, and provide litera- bers 12 to 24 inches), uniform spacing
ture describing the recommended in- or positioning of bars in slabs or walls Conclusions
stallation procedures. ( 3 inches), stirrup and tie spacing in Mistakes can and will happen, but
Special attention may be needed in beams and columns (one-twelfth an inspector is expected to find them
the inspection of mechanical connec- beam depth or column width), loca- and have them corrected. A quality-
tions or welded splices, as well as crit- tion of bar bends and bar ends ( 2 control program by the contractor
ical components and activities that are inches, except 1 inch at discontinu- helps reduce errors and makes final
not routine for either the placer, con- ous ends of members), length of lap inspection easier. The inspector should
tractor, or inspector. splices (-11⁄2 inches), and embedded perceive his job as supplementary to
lengths (-1 inch for bar sizes from #3 the workers in support of good con-
Coatings to #11). Tolerances also are stated for struction techniques and practice.
Inspectors should not reject rebar beam and column form dimensions.
with a light coating of rust. Howev- Potential problems develop when References
er, dirt, grease, or other deleterious tolerances of fabricated bars and form- For further information on inspection,
adhesions must be removed before work conflict. For example, in a 16x16- tolerances, industry standard prac-
tices, placing, fabricating, welding,
concrete placement. Water-soluble inch interior column with specified 11⁄2 and mechanical connections, consult
cutting oils do not significantly af- inch cover to ties, the fabrication toler- the following references:
fect bond. Review the contract doc- ance on stirrup size is 1⁄2 inch and the
Standard Specifications for Tolerances
uments for acceptance or rejection form size tolerance is +1⁄2 /-3⁄8 inch. If for Concrete Construction and Materi-
criteria if there is damaged epoxy or the ties are +1⁄2 and the forms are -3⁄8, als (ACI 117-90), American Concrete
damaged galvanized coating. Cor- the concrete cover would be reduced Institute (ACI).
rective actions should follow rec- to 7⁄16 inch, which conflicts with provi- ACI Detailing Manual—1988, ACI. In-
ommended touch-up procedures sion 2.2.2 of ACI 117 that permits only cludes Details of Concrete Reinforce-
and should be completed before ac- a 1⁄2-inch reduction in cover for this ex- ment (ACI 315-80) (Revised 1986).
ceptance by the inspector. ample. Conflicts like this are best re- Building Code Requirements for Rein-
solved with assistance from the de- forced Concrete (ACI 318-89) (Revised
signer and when discovered early. 1992), ACI.
Standard Specification for Deformed
and Plain Billet-steel Bars for Concrete
Reinforcement (A 615-92b), ASTM,
Philadelphia.
Standard Specification for Low-alloy
Steel Deformed Bars for Concrete Re-
inforcement (A 706-92b), ASTM.
Standard Specification for Epoxy-
coated Reinforcing Steel Bars (ASTM
A 775-92), ASTM.
Manual of Standard Practice, 25th ed.,
CRSI, 1990.
Placing Reinforcing Bars, 6th ed.,
CRSI, 1992.
Reinforcement: Anchorages, Lap
Splices and Connections, 3rd ed.,
CRSI, 1990.
Field Corrections to Rebars Partially
Embedded in Concrete, Engineering
Data Report No. 12, CRSI.
Guidelines for Inspection and Accep-
tance of Epoxy-coated Reinforcing
Bars at the Job Site, CRSI, 1986.

Structural Welding Code—Reinforcing


Steel (ANSI/AWS D1.4-92), American
Welding Society, Miami, 1992.

Acknowledgment
This article is adapted from CRSI’s En-
gineering Data Report No. 36, Field In-
spection of Rebar. For a copy of the
report, contact CRSI, 933 N. Plum
Grove Rd., Schaumburg, IL 60173
(708-517-1200; fax: 708.517.1206).

PUBLICATION #C930027
Copyright © 1993, The Aberdeen Group
All rights reserved

You might also like