You are on page 1of 1

TITLE:- TURTLE DIAGRAM

TURTLE DIAGRAM: RQC


BY WHOM
BY WHAT (EQUIPMENT MATERIAL) RISKS :
(PERSONAL, TRAINING, KNOW-HOW, SKILLS)
 Communication System  Quality : Non confirming part feed to line/assembly,  Department Personnel
 Measuring & Test equipment. RFT loss, Non availability of TME for inspection, Delay in  Appropriate knowledge of the processes
 Tools & Tackles project  Knowledge of Used Software
 Environment : Waste generation, Dust, Oil Spillage
 Software ( SAP )  Knowledge of Tools & Tackles being used
 Occ. Health & Safety :Unsafe Working of Equipment (on
job setup), unsafe act and conditions
INPUTS : PROCESS AND SUB PROCESS OUTPUTS :
 Component Drawing, Layout Inspection Plan, Layout  Quality assured parts/products, updated
Inspection Report, Plan for receiving Report from audit checklist, Summary Report of Layout
Supplier, Monthly plan, Audit checklist Receipt Quality Check Inspection, Quality Improvement Sheet,
 Calendar for receiving Functional Testing Reports, Type  Layout Inspection rejection tag (if rejected)
test report comparison sheet  Functional Testing  Updated functional testing reports
 Goods receipt Note, RQC Sampling Plan, GRN  Receipt Inspection  NC Component, SAP Rejection Tag Complete,
 CMM inspection request, CMM programme list  Geometric inspection
GRN MIS, CMM review report
 List of Instruments / Std. Gauges Requirement, List of  Procurement & stocking of TME
 Sample inspection & approval process  Min-max level list & Stock record ( with
Stock Availability
 Supplier audit. calibration due status)
 List of items –Supplier with category wise, Data sheet
for –Supplier Part Performance sheet, Quality Issues
(Supplier Wise)

How (INSTRUCTIONS, PROCEDURE, METHODS) SUPPORT PROCESSES : PERFORMANCE INDICATORS :


 SOPs/ OCPs. Standardized Work Instructions  All departments  Departmental MIS
 Checklist/Guideline / Standard  Departmental Objectives and Targets /KPIs

Page 1 of 1