Menghitung Volume Pembesian Shear Wall 4

1. Tulangan Utama (D19)


Panjang batang = 8.2 m
Jumlah batang = 28 batang
Berat ØD19 per m (SNI) = 2.226 kg
Total berat = Jumlah besi * Panjang batang * Berat besi
= 28 * 8.2 * 2.226
= 511.0896 kg
2. Tulangan Utama (D13)
Panjang batang = 8.2 m
Jumlah batang = 4 batang
Berat ØD13 per m (SNI) = 1.042 kg
Total berat = Jumlah besi * Panjang batang * Berat besi
4 * 8.2 * 1.042
34.1776 kg
2. Tulangan Begel (D13)
Panjang batang = 1.6 + 1.6 + 0.4 + 0.4 + 0.2
= 4.2 m
Jumlah batang = (8.2/0.2) + 1
= 84 baris
Berat Ø13 per m (SNI) = 1.042 kg
Total berat = Jumlah besi * Panjang batang * Berat besi
= 42 * 4.2 * 1.042
= 367.6176 kg

3. Tulangan Sengkang(D13)
Panjang batang = 1.6 * 2
= 3.2 m
Jumlah batang = (8.2/0.2) + 1
= 42 baris
Berat Ø13 per m (SNI) = 1.042 kg
Total berat = Jumlah besi * Panjang batang * Berat besi
= 84 * 3.2 * 1.042
= 140.0448 kg

4. Tulangan Ikat(D10)
Panjang batang = 0.8 * 10
= 8 m SW 4
Jumlah batang = (8.2/0.2) + 1
= 42 baris
Berat Ø10 per m (SNI) = 0.617 kg
Total berat = Jumlah besi * Panjang batang * Berat besi
= 420 * 0.8 * 0.617
= 207.312 kg

Menghitung Volume Beton Shear Wall 4


Dimensi = 1.75 m * 0.5 m
Tinggi Shear Wall = 3.5 m
Tcor = Tinggi SW - Tinggi balok
= 3.5 - 0.5
=3 m
Volume beton = Tcor * PSW * LSW * jumlah SW
= 3 * 1.75 * 0.5 * 4
= 10.5 m3

Menghitung Volume Bekisting Shear Wall 4


Dimensi = 1.75 m * 0.5 m
Luas permukaan = 1.75 + 0.5 +1.75 + 0.5
= 4.5 m
Volume Bekisting = Lpermukaan * TSW * jumlah SW
= 4.5 * 3.5 * 4
= 63 m2
PERHITUNGAN BESTAT SHEAR WALL 4
UKURAN BESI JENIS TULANGAN DIAMETER (m) PANJANG TULANGAN (m)
D19 TULANGAN UTAMA 0.019 8.2
D13-20 TULANGAN BEGEL 0.013 4.2
D13-20 TULANGAN SENGKANG 0.013 3.2
D10-20 TULANGAN IKAT 0.01 8
4
JUMLAH TULANGAN BERAT TOTAL (kg)
32 584.1024
42 183.8088
42 140.0448
42 207.312