Professional Documents
Culture Documents
Project name: Abuyog WD 5 MLD Bulk Water Supply and Expansion Project
Water Point Construction Services and Supply (WPC) for Component “B”
I. Project Description
The project involves the design and construction of a 5 MLD bulk water supply system for the
Abuyog Water District, consisting of the following components:
Component “A’: Water treatment plant (WTP) with a capacity of 5 million liters/day ( 5MLD),
inclusive of all its accessories, a diversion weir, intake structure, supply of raw water and dosing
pumps, piping, laboratory and admin building, power house, chlorination pumps and treated
water pumps, steel tank as reservoir with a total capacity of 500 cubic meters (cu.m.), supply
of standby generator rated at 250 KVA, guard house, site development, perimeter fencing with
gate and other items in Brgy. Balinsasayao, Abuyog, Leyte.
Component “B”;; Transmission facilities capable of transmitting 5 MLD of treated water from
a 500 cu.m. ground tank located in Bgy. Balinsasayao down to a defined service area of the
Abuyog Water District (AWD) via a series of pumps, transmission and distribution lines and
ancillaries, and passing through the existing ground tank in Abuyog, Leyte. As agreed upon
during the 2nd Coordination Meeting held in AWD on 21 August 2018, the WD’s desired
minimum acceptable water pressure is 7 pounds/square inch (PSI) to 10 PSI.
The project is being implemented under two separate contracts, both between WVI and AKI.
II. Key Milestones
Title Component “A” Component “B”
1 Contract Signing between WVI and AKI for 07 Feb 2018
Component “A”
Contract Signing Between WVI and AKI for 23 Jul 2018
Component “B”
3 Advance Payment Issued by WVI to AKI 15 Aug 2018 15 Aug 2018
Page
1
of
10
- Filtration House: Filtration Building is 100% complete. WVI has decided against
using the fiberglass multi-media filter tanks that have been delivered at the site. The
reported percentage accomplishment has been adjusted accordingly to exclude the
tanks. Multi-media filter tanks made of steel have already been ordered as
replacement. CAN WE SAY THAT FABRICATION OF THE STEEL OR
CONCRETE??? TANKS TO REPLACE THE DISALLOWED FIBERGLASS MULTI-
MEDIA TANKS IS ONGOING???? IS THE TANK HERE OR UNDER TREATED
WATER RESERVOIR?
- Powerhouse: Construction of the foundation for the generator set is in progress.
- Treated Water Reservoir: Steel plates for the treated water reservoir are on site
and fabrication of the steel reservoir will start as soon as power supply becomes
available. Additional electrical layout clearance was sought from the Abuyog
Municipal Engineer’s office as a requisite to obtaining an electrical connection for the
Balinsasayao plant site from DORELCO.
- Progress Payment No. 2 and partial release of the balance of the Advance Payment
were received on 8 May 2019 and 30 May 2019, respectively. With the infusion of
funds, the sub-contractor proceeded with the procurement of equipment for the
treatment plant.
- Total accomplishment as of 31 May 2019 is 33.955%. Resolution of the ownership
of the location of the weir and raw water conveyance will help speed up work for
Component “A”.
- Trenching, backfilling and compaction for the installation of HDPE pipes continued
although slowed down by inclement weather. For May 2019, a total of 1,212 meters
of pipes were installed as shown below.
- Total accomplishment increased slightly to 33.9331%. Early resolution of the ROW
issues is critical to project implementation.
Trench Excavation
Page
5
of
10
Pipe Laying
Jointing Using Butt Fusion Machine
Clearing
Backfilling/Backfilled Earthworks
Page
7
of
10
Description Status
1 Facilitate the Nation Manufacturing and Industrial Products Corp. (Nation) has
manufacturing/transport completed the production of all HDPE pipes. WPC is waiting for
of fittings by Nation Nation to complete the fittings so they could be shipped together
with the remaining two truckloads of HDPE pipes. Meanwhile,
WPC started negotiating for the purchase and delivery of G.I. pipes
and fittings from Cebu City for the bridge/drainage crossings and
interconnections.
2 Submit electronically For component A, hard and scanned copies of the WTP design
scanned copy of the plans/drawings will be furnished to WVI once approved by the
approved design for Municipal Engineer’s Office. For component B, hard copies of the
components A & B. design plans and drawings for the transmission and distribution
pipelines have been submitted earlier to WVI.
3 Obtain Building Permit The Abuyog Municipal Engineer’s office also requested
submission of a copy of the DPWH permit together with the
WVI/AWD-approved design drawings of component B as a
requisite for the issuance of the Building permit.
4 Obtain DPWH Permit The joint inspection of the pipeline route by DPWH, AWD, WVI,
AKI and WPC, which is a requisite for the issuance of the DPWH
permit has yet to be scheduled by DPWH. AWD/WVI/AKI planned
to meet with DPWH official on June 3 to speed up the issuance of
the DPWH excavation permit.
5 Prepare and implement The catch up plans for components A & B were prepared and
catch-up plan submitted to WVI. However, ROW concerns and delayed payment
releases severely affected work progress. A meeting was held
between WVI and AKI/NIC/WPC to discuss and formulate action
plan to address especially the ROW.
6 Resolve Right-of-Way Last 30 May 2019, WPC sent 2 notices of work stoppage due to
(ROW) issues ROW concerns. NIC also wrote last May 31 to inform about
stoppage of excavation for the river weir and raw water
conveyance since April 17 due to an ownership claim on the
excavation site by a Balinsasayao resident. A trip to Abuyog is
scheduled on 3 June 2019 to discuss and evaluate the issues with
AWD and DPWH.
7 Release the remaining WVI released Progress Payment #2 for Component “A” in the
50% of the stipulated amount of Php 4.111 million on 8 May 2019. The amount of Php
30% Advance Payment 2.5 million was also released on 30 May 2019 as partial payment
for Component “A” for the remaining 50% of the Advance Payment for Component
“A” stipulated in the Construction Agreement.
V. Attachments
Attachment A: Gantt Chart for Component “A”