AHU SCHEDULE.

SNO ACTIVITY
1 Room data Sheet Preparation & Approval
2 AHU BOQ Receive
3 BOQ Review & Approval
4 Floating enquiry
5 Technical comparision
6 PR crea
7 Column raising for Third floor along with Slab
8 Block work Construction for 3rd floor
9 Equipment Installation & Piping
10 HVAC Installation & Ducting work
11 Civil Finishing & Painting
12 Area Validation
AHU SCHEDULE.
Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
Apr-20
SEP OCT
S.No Description of works week-1 week-2 week-3 week-4 week-1 week-2 week-3
1 Civil works
2 Room Data sheet Preparation
3 BOQ Preparation
4 BOQ Review & approval
5 URS preparation
6 Receive Quote
7 Technical comparaision Preparation
8 PR creation
9 PO release
10 GAD review & approval
11 DQ Preparation
12 Fabrication
13 Inspection FAT
14 HVAC Installation & Ducting work
15 Facilty qualification
16 Validation
OCT Nov Dec Jan
week-4 week-5 week-1 week-2 week-3 week-4 week-1 week-2 week-3 week-4 week-1 week-2
Jan Feb March
week-3 week-4 week-5 week-1 week-2 week-3 week-4 week-1 week-2 week-3 week-4
April
week-1 week-2 week-3 week-4