Quotation for Geotechnical Investigation for Eight Story Hostel Construction Project,

in Insein Township, Yangon

Project :Eight Story Hotel Construction Project


Client Simple Tech One Co.,Ltd. Ref. No.: Q/ SI -095/19
Work Title : Geotechnical Investigation Work ( 3Boreholes: 30m) Date: June 10,2019
TOTAL
No. DETAIL WORK ITEM UNIT Qty RATES (Kyat) REMARKS
AMOUNT (Kyat)
Geotechnical Investigation
A Field work
Mobilization & demobilization of drill rig Man power & 0ne Drilling
1 including manpower Lump Sum 1 140,000.00 140,000.00 Machine
2 Meal, safety, security, and medical cover Lump Sum 1 - - For 5 ppl
3 Daily transportation for crews, Sample sending and LS 1 80,000.00 80,000.00 aprroximately 10 days
4 Rotary drilling (0-30)m in soil m 90 25,000.00 2,250,000.00 (4 ppl, 2 or 3 days/BH)
5 Rotary drilling (30<depth<40)m in soil m 1 30,000.00 -
6 Shifting BH to BH Nos 1 - -
7 Standard Penetration Test Nos 60 - -
8 Rotary drilling Rock m 1 95,000.00 If any , 3 m to confirm
9 Bentonite Nos 9 7,500.00 67,500.00
10 Drilling Water L.S 1 45,000.00 45,000.00
B Laboratory testing
1 Moisture content test Tests 15 - - 5/6 nos or layers encounter
2 Grain size distribution test and Hydrometer test Tests 15 - - 5/6 nos or layers encounter
3 Atterberg limit test Tests 15 - - 5/6 nos or layers encounter
4 Specific gravity Tests 15 - - 5/6 nos or layers encounter
5 Density Test Tests 15 - - 5/6 nos or layers encounter
6 Triaxial testing (UU)( Undisturbed) Tests 6 35,000.00 210,000.00 2UD samples
7 Consolidation Test Tests 3 15,000.00 45,000.00 UD sample
8 Organic content test Tests 1 - - If any,not included
C Factual report (including boring logs + soil profile + summary
of laboratory test + Shallow& deep foundation bearing
capacity analysis + liquefaction analysis) Lump sum 1.00 75,000.00 75,000.00
1CD+ 2 Hard copies
Total 2,912,500.00
Tax (5)% 145,625.00
Grand Total 3,058,125.00
PTO
Terms and Condition

*Under this quotation, The client is referred to "Simple Tech One Co.,Ltd. " and contractor is Strata Geotechnical Investigation co.,ltd.

*The Client shall provide the construction drawing , drilling water, removing obstructions and the borehole location points on the ground.

*The geotechnical soil report shall complrises boring logs, photographs of site activities, borehole locations,

*cross section profile, field test result and summary of laboratory test data.

*The number of in-situ tests and laboratory tests will be changed according to actual ground

condition and to get the design specification of greater depth and the addational payment will be charged on them.

* The standard penetration test is conducted then 1.5m interval up to end of borehole.

*The whole process of investigation ( lab + report ) will take 2 -3weeks after finished the borehole drilling.

*The client shall supply water for drilling or the cost of water for drilling shall be paid by client.

*If the secrity of night is not provided by the client, the price for night security shall be claimed.

*Client have to pay 30% down payment when starting the project and the next 40 % will have to pay after finished the site

investigation (Borehole Drilling). And then the last 30 % down payment will have to pay all testing finished,

including with Laboratory testing and reporting.