7 Laboratory Testing
7.1 Soil Tests
Particle Size Distribution Tests (all) No. 12 2,250.00 27,000.00
Atterberg Limit (includes LL, PL and Linear Shrinkage) (all) No. 8 2,160.00 17,280.00
pH, Chloride and Sulphate Content Tests (Bulk and Rock) No. 2 6,600.00 13,200.00
8 Logging (Geologist)
8.1 Logging Boreholes in contractor's yard m 60 825.00 49,500.00
9 Factual/Engineering Reports
9.1 Factual Report LS 1 50,000.00 50,000.00
2. Time Periods:
Mobilization to site from award of contract 4 Days
Field work 10 Days
Laboratory tests 15 Days
Draft report 7 Days after end of fieldworks works
Final report (from receipt of Engineer's comments) 4 Days after receipt of Lab Test results
3. Payments Terms:
Mobilization 30%
Completion of fieldwork 40%
Final Report 30%
Yours faithfully,