Description of Work Qty Unit Rate in LKR Amount in LKR

1 Geotechnical investigation
1.1 Boreholes
1.1.1 Gurunagar
Mobilization of jack up/pontoon and
drilling rig,necessary equipment,
1.1.1.1 personnel and accessories for execution 1 LS 3,000,000.00 3,000,000.00
of work (shift from Silawatturai to
Gurunagar)
Demobilization of jack up/pontoon and
drilling rig,necessary equipment,
1.1.1.2 1 LS 1,500,000.00 1,500,000.00
personnel and accessories for execution
of work
Per
1.1.1.3 Setting & shifting of drilling rig at each borehole
16 700,000.00 11,200,000.00
borehole
Drilling PQ size boreholes in soil at
various locations up to depths as per
1.1.1.4 tender document. Includes collection of 19 Lin meters 22,000.00 418,000.00
undisturbed and disturbed samples and
their transport to the laboratory
Coring in Rock PQ size using
double/triple core barrel up to depths as
1.1.1.5 per tender document. Includes collection 18 Lin meters 35,000.00 630,000.00
of samples and their transport to the
laboratory
1.1.1.6 Provision of core boxes for preserving the samples
4 Nos 3,000.00 12,000.00
Conducting laboratory tests on soil as Per
1.1.1.7 19 120,000.00 2,280,000.00
per tender documents sample
Conducting laboratory tests on rock as Per
1.1.1.8 18 25,000.00 450,000.00
per tender documents sample
Preparation of factual/compilation report
1.1.1.9 1 LS 200,000.00 200,000.00
(BH logging)
1.1.2 Silawatturai
Mobilization of jack up/pontoon and
drilling rig,necessary equipment,
1.1.2.1 1 LS 2,500,000.00 2,500,000.00
personnel and accessories for execution
of work
Demobilization of jack up/pontoon and
drilling rig,necessary equipment,
1.1.1.2 1 LS 1,750,000.00 1,750,000.00
personnel and accessories for execution
of work
Setting & shifting of drilling rig at each Per
1.1.2.3 6 700,000.00 4,200,000.00
borehole borehole
Drilling PQ size boreholes in soil at
various locations up to depths as per
1.1.2.4 tender document. Includes collection of 60 Lin meters 22,000.00 1,320,000.00
undisturbed and disturbed samples and
their transport to the laboratory
Coring in Rock PQ size using
double/triple core barrel up to depths as
1.1.2.5 per tender document. Includes collection 0 Lin meters 35,000.00 0.00
of samples and their transport to the
laboratory
Provision of core boxes for preserving
1.1.2.6 0 Nos 3,000.00 0.00
the samples
Conducting laboratory tests on soil as Per
1.1.2.7 60 120,000.00 7,200,000.00
per tender documents sample
Conducting laboratory tests on rock as Per
1.1.2.8 0 25,000.00 0.00
per tender documents sample
Preparation of factual/compilation report
1.1.2.9 1 LS 150,000.00 150,000.00
(BH logging)
Standby charges for equipment and
1.1.2.9 personnel - on instruction of the Client - 1 Per day 30,000.00 30,000.00
at both sites
Total Borehole campaign 36,840,000.00
1.2 Vibrocores
1.2.1 Gurunagar
Mobilization of VC equipment and
suitable vessel,necessary equipment,
1.2.1.1 personnel and accessories for execution 1 LS 1,500,000.00 1,500,000.00
of work (shift from Silawatturai to
Gurunagar)
Demobilization of VC equipment and
suitable vessel,necessary equipment,
1.2.1.2 1 LS 750,000.00 750,000.00
personnel and accessories for execution
of work
Setting & shifting of VC set up at each Per
1.2.1.3 18 80,000.00 1,440,000.00
location location
Coring at the different locations up till Per
1.2.1.4 18 150,000.00 2,700,000.00
depth as per tender document location
Conducting laboratory tests on soil as per Per
1.2.1.5 36 85,000.00 3,060,000.00
tender documents sample
1.2.1.6 6 meters long 75 mm dia PVC lines Actual cost + 15% 950.00 Rate Only
Preparation of factual/compilation
1.2.1.7 1 LS 175,000.00 175,000.00
report
1.2.2 Silawatturai 0.00
Mobilization of VC equipment and
suitable vessel,necessary equipment,
1.2.1.1 1 LS 2,000,000.00 2,000,000.00
personnel and accessories for execution
of work
Setting & shifting of VC set up at each Per
1.2.1.2 7 80,000.00 560,000.00
location location
Per
1.2.1.3 Coring at the different locations up till depth as per
7 tender document150,000.00 1,050,000.00
location
Conducting laboratory tests on soil as per Per
1.2.1.4 28 85,000.00 2,380,000.00
tender documents sample
1.2.1.5 6 meters long 75 mm dia PVC lines Actual cost + 15% 950.00 Rate Only
Preparation of factual/compilation
1.2.1.6 1 LS 175,000.00 175,000.00
report
Standby charges for equipment and
1.2.1.6 personnel - on instruction of the Client - 1 Per day 30,000.00 30,000.00
at both sites
Total VC campaign 15,820,000.00
1.3 Trial pits
1.3.1 Gurunagar
Mobilization of excavator incl operator
1.3.1.1 1 LS 100,000.00 100,000.00
and staff
Demobilization of excavator incl
1.3.1.2 1 LS 50,000.00 50,000.00
operator and staff
1.3.1.3 Exavation of pit and sampling, all incl 2 Per pit 25,000.00 50,000.00
Conducting laboratory tests on soil as Per
1.3.1.4 4 80,000.00 320,000.00
per tender documents sample
1.3.2 Silawatturai
Mobilization of excavator incl operator
1.3.2.1 1 LS 100,000.00 100,000.00
and staff
Demobilization of excavator incl
1.3.2.2 1 LS 50,000.00 50,000.00
operator and staff
1.3.2.3 Exavation of pit and sampling, all incl 5 Per pit 25,000.00 125,000.00
Conducting laboratory tests on soil as Per
1.3.2.4 10 80,000.00 800,000.00
per tender documents sample
Preparation of factual/compilation report
1.3.2.5 1 LS 100,000.00 100,000.00
for both sites
Total Trial pits 1,695,000.00
Total Geotechnical 38,535,000.00
2 Bathymetric and topographic surveys
2.1 Bathymetric survey
2.1.1 Gurunagar
Mobilization of single beam survey
equipment as per tender document and
2.1.1.1 1 LS 120,000.00 120,000.00
suitable vessel , incl of all personnel and
accessories
Demobilization of single beam survey
equipment as per tender document and
2.1.1.2 1 LS 110,000.00 110,000.00
suitable vessel , incl of all personnel and
accessories
Bathymetric survey as per tender
2.1.1.3 document conform with the grid 40 km 18,500.00 740,000.00
requested
2.1.2 Silawatturai
Mobilization of single beam survey
equipment as per tender document and
2.1.2.1 1 LS 100,000.00 100,000.00
suitable vessel , incl of all personnel and
accessories

Demobilization of single beam survey


equipment as per tender document and
2.1.2.2 1 LS 90,000.00 90,000.00
suitable vessel , incl of all personnel and
accessories
2.1.2.3 Bathymetric survey as per tender document conform
70 with
km the 18,500.00 1,295,000.00
grid requested
2.2 Topographic survey
2.2.1 Gurunagar
Mobilization & demobilization of
2.2.1.1 topographic survey equipment , incl of 1 LS 250,000.00 250,000.00
all personnel and accessories
Topographic survey as per tender
2.2.1.2 document conform with the grid 6.5 km 120,000.00 780,000.00
requested
2.2.2 Silawatturai
Mobilization & demobilization of
2.2.2.1 topographic survey equipment , incl of 1 LS 200,000.00 200,000.00
all personnel and accessories
2.2.2.2 Topographic survey as per tender document conform
4.6 with
km the grid120,000.00
requested 552,000.00

2.2.2.3 Preparation of report incl of all raw data, bench marks,


1 LS
drawings, ..
300,000.00
For all survey works
300,000.00
at both sites
Total Surveys 4,537,000.00
Total GeoTechnical and Total Surveys 58,892,000.00