You are on page 1of 1

Project: Camella Homes - Gensan

Location: Phase 2, Blk. 9 Lot 12, Camella Homes Gensan, San Isidro, GSC
Subject: Concreting Works of Pathway in front of Unit
Date: March 9, 2017

Qty. Unit Unit Cost Total Cost


I.Concreting works: 19.50 sq.m.
Clearing Works: 1.50 cu.m. 250.00 375.00
Holcim Cement, Excel 13.00 bags 240.00 3,120.00
Sand 1.50 cu.m. 250.00 375.00
Gravel: 3.00 cu.m. 600.00 1,800.00
Rebar 14.00 lengths 113.00 1,582.00
Tiewire 2.00 kg 55.00 110.00
Subtotal: 6,987.00

Labor Cost: 3,000.00

Grand Total: 9,987.00

Prepared by:

Michael Jan de Celis


Project Engineer