Professional Documents
Culture Documents
Abhijit Bhosle
Abhijit Bhosle
BHOSLE
A-20, Mangalam Park
B/H Saurabh Park
Subhanpura, Baroda
Mobile: +91 75676 78555
E-Mail: bhosleabhijit@gmail.com
Profile:-
Personal information:-
Nationality Indian
Educational Qualifications:-
S.S.C. 84.86%
Rosary High School - March 2001
Computer Knowledge:-
Manpower Handling at
Site.
Purchasing
Drafting of site
drawings
Quality Control
Infrastructure
Development (i.e.
plumbing Work, Laying
of R.C.C.(NP-2) Pipes,
Stoneware Pipes etc.)
Quality Control
Manpower Handling at
Site
Evaluating sub-
contractor variations
Preparation of sub-
contractor claim
Assist in preparation
and adherence to
project targeting and
cost budgets
Executed and erected industrial shade as per given design starting from
foundation till the finish of the project.
Quality check for BWSC (Bar Wrap Steel Cylindrical) pipes. Laying the pipe as
per the given design. Nature of work involved excavating, laying & jointing of
pipes, valve fitting, refilling and leveling along with material check at site, third
party and consultant check. The Diameter of pipes are varies from 1800 mm
to 600mm.The project Cost was 420.00 lakhs.
Laying of Sewage Gravity Line (32 km)
Laying the RCC pipes NP3 and NP4 (non pressure) pipes as per the given design.
Nature of work involved excavating, laying & jointing of pipes, manhole
construction, refilling and leveling along with material check at site, third party
and consultant check. The Diameter of pipes varies from 1400mm to
150mm. The Project Cost was 170.65 lakh.
Executing Civil, Mechanical and Electrical Works for APS. The project was to
construct APS which is used to pump the sewage coming through gravity line to
main Sewage Trunk line which is further connected to nearby Sewage Treatment
Plant. The Capacity of APS was 13.5MLD.The Project Cost was 110.23 lakhs.
This is very unique project. This contents most of Indoor Games (i.e. Basket
Ball, volley Ball, Boxing, Table Tennis, Swimming, Badminton).The Total
Seating Capacity is 4500 in Basket Ball unit,2500 For Swimming pool &
1500 For Badminton, Table Tennis & Boxing. The Project Cost is 445.65
lakhs.
As the name of this project says,it is one of the industrial project. The capacity
of this plant is 165 to 250 MTPD.The total cost for the civil work is 450.00 lakhs.
Sports:-