Required Section
Capacity Temperature Size
Duration or Rating Factor Derating (3) x (6) x (7)
Load Time to End of Section
Period Change in Load (amperes) Period at t Min Rate Factor for t = Rated Amp-Hrs
(amperes)
(minutes)
(minutes) LOAD
(Kt) Min Rate (Tt)
Positive Negative
Values Values A1
Section 1 - First Periods only - if A2 is greater than A1, go to Section 2. A2
1 A1= 1.32 A1-0= 1.32 M1= 1440 t= M1= 1440 26.10 1.03 35.37 *** A3
Sec 1 Total 35.37 *** A4
Section 2 - First Two Periods only - if A3 is greater than A2, go to Section 3. A5
1 A1= 1.32 A1-0= 1.32 M1= 1440 t= M1+M2= 7200 120.13 1.03 162.81 A6
2 A2= 0.34 A2-A1= -0.97 M2= 5760 t= M2= 5760 96.86 1.03 -97.24 AR
Sec Sub Total 162.81 -97.24 A8
2 Total 65.57 ***
Section 3 - First Three Periods only - if A4 is greater than A3, go to Section 4.
1 A1= A1-0= M1= t= M1+M2+M3= 0 AR
2 A2= A2-A1= M2= t= M2+M3= 0
3 A3= A3-A2= M3= t= M3=
Sec Sub Total 0.00 0.00
3 Total 0.00 ***
Section 4 - First Four Periods only - if A5 is greater than A4, go to Section 5.
1 A1= A1-0= M1= t= M1+...M4= 0
2 A2= A2-A1= M2= t= M2+M3+M4= 0
3 A3= A3-A2= M3= t= M3+M4= 0
4 A4= A4-A3= M4= t= M4=
Sec Sub Total 0.00 0.00
4 Total 0.00 ***
Section 5 - First Five Periods only - if A6 is greater than A5, go to Section 6.
1 A1= A1-0= M1= t= M1+...M5= 0
2 A2= A2-A1= M2= t= M2+…M5= 0
3 A3= A3-A2= M3= t= M3+…M5= 0
4 A4= A4-A3= M4= t= M4+M5= 0
5 A5= A5-A4= M5= t= M5= 0
Sec Sub Total 0.00 0.00
5 Total 0.00 ***
Section 6 - First Six Periods only - if A7 is greater than A6, go to Section 7.
1 A1= A1-0= M1= t= M1+...M6= 0
2 A2= A2-A1= M2= t= M2+…M6= 0
3 A3= A3-A2= M3= t= M3+…M6= 0
4 A4= A4-A3= M4= t= M4+…M6= 0
5 A5= A5-A4= M5= t= M5+M6= 0
6 A6= A6-A5= M6= t= M6= 0
Sec Sub Total 0.00 0.00
6 Total 0.00 ***
Section 7 - First Seven Periods only - if A8 is greater than A7, go to Section 8.
1 A1= A1-0= M1= t= M1+...M7= 0
2 A2= A2-A1= M2= t= M2+…M7= 0
3 A3= A3-A2= M3= t= M3+…M7= 0
4 A4= A4-A3= M4= t= M4+…M7= 0
5 A5= A5-A4= M5= t= M5+…M7= 0
6 A6= A6-A5= M6= t= M6+M7= 0
7 A7= A7-A6= M7= t= M7=
Sec Sub Total 0.00 0.00
7 Total 0.00 ***
Random Equipment Load Only (if needed)
R AR= 0.00 AR-0= 0.00 MR= 0 t=MR= 0 0.00 0.00 0.00 ***
Solenoid Valves 2 2
GOV Valve Positioner 1 1
Indicating Light 2 1
Control Relays 2 3
MOV Panel Indicating Lights 2 1
Site Processor 20 1
Leak Detection System
Grand total 7
Continuous Loads: L2 for 1440 minutes
Equipment Steady State Power (W) QTY Total
Site Processor 20 1 20
Leak Detection System
Grand total 20
Random Load
Equipment Steady State Power (W) QTY Total
Grand total 0
DC Load Profile
Period Period scenarios Total Amperes Duration (min) Capacity Removed (Ah)
A1 LI + L2 1.32 1440 31.58
A2 L1 0.34 5760.00 32.75
A3 0.00 0.00 0.00
A4 0.00 0.00 0.00
A5 0.00 0.00 0.00
A6 0.00 0.00 0.00
A7 0.00 0.00 0.00
A8 0.00 0.00 0.00
AR 0.00 0.00 0.00
Total 64.33
CELL TYPE PV185 CAPACITY RATING FACTORS
(1) (2)
Time t1 from Cell Time t2 from Cell Factor Kt1 for time Factor Kt2 for time
Discharge Time, t Factor Kt
Performance Performance t1, t2,
(Minutes) Amperes for time Amperes for time for time t
Tables (Minutes) Tables (Minutes) t1 t Batt. AH / (1) Batt. AH / (2)
2
Objective
Determine the Size of Solar Array and Charge Controller ARAMCO Standards
for the 24V DC Photovoltaic System per ARAMCO Standards
Indicates data input required
Data: Indicates calculated value
DC CONTINUOUS LOADS
24.00 V E System voltage
20.52 V E End-of discharge voltage
Qty.
0.97 A 1 x 20 Watts E LDS
0.00 A 0 x 24 Watts E RTU
0.34 A 1 x 7 Watts E GOV Relay Panel
1.32 A E Sum of Loads
10% E Spare Capacity
1.45 A E Total Continuous Load (to be re-validated per actual installed load/s)
BATTERY INFORMATION
185 AH @ C120 E Battery AH Capacity PV185 Alcad E Vendor Catalog number
171 AH @ C5 E Battery AH Capacity
120.0 hrs E BT Required battery backup time in hours per SAES-P-103 Table 1 330C
330C
Comment:
This calculation is preliminary only. It is the responsibility of the Construction Contractor and the Photovoltaic-System
Vendor to re-design and re-validate this Photovoltaic Array and Charge Controller Sizing Calculations per actual installed DC
continuous loads. 350C
MIV STATION AT KM 120.00 AND 294.00 (PER IEEE 1115)
(1) (2) (3) (4) (5) (6) (7) (8)
Required Section
Capacity Temperature Size
Duration or Rating Factor Derating (3) x (6) x (7)
Load Time to End of Section
Period Change in Load (amperes) Period at t Min Rate Factor for t = Rated Amp-Hrs
(amperes) (minutes)
(minutes) (Kt) Min Rate (Tt)
Positive Negative
Values Values
Section 1 - First Periods only - if A2 is greater than A1, go to Section 2.
1 A1= 2.49 A1-0= 2.49 M1= 1440 t= M1= 1440 26.13 1.03 66.89 ***
Sec 1 Total 66.89 ***
Section 2 - First Two Periods only - if A3 is greater than A2, go to Section 3.
1 A1= 2.49 A1-0= 2.49 M1= 1440 t= M1+M2= 7200 119.94 1.03 307.05
2 A2= 1.51 A2-A1= -0.97 M2= 5760 t= M2= 5760 96.96 1.03 -97.34
Sec Sub Total 307.05 -97.34
2 Total 209.70 ***
Section 3 - First Three Periods only - if A4 is greater than A3, go to Section 4.
1 A1= A1-0= M1= t= M1+M2+M3= 0
2 A2= A2-A1= M2= t= M2+M3= 0
3 A3= A3-A2= M3= t= M3=
Sec Sub Total 0.00 0.00
3 Total 0.00 ***
Section 4 - First Four Periods only - if A5 is greater than A4, go to Section 5.
1 A1= A1-0= M1= t= M1+...M4= 0
2 A2= A2-A1= M2= t= M2+M3+M4= 0
3 A3= A3-A2= M3= t= M3+M4= 0
4 A4= A4-A3= M4= t= M4=
Sec Sub Total 0.00 0.00
4 Total 0.00 ***
Section 5 - First Five Periods only - if A6 is greater than A5, go to Section 6.
1 A1= A1-0= M1= t= M1+...M5= 0
2 A2= A2-A1= M2= t= M2+…M5= 0
3 A3= A3-A2= M3= t= M3+…M5= 0
4 A4= A4-A3= M4= t= M4+M5= 0
5 A5= A5-A4= M5= t= M5= 0
Sec Sub Total 0.00 0.00
5 Total 0.00 ***
Section 6 - First Six Periods only - if A7 is greater than A6, go to Section 7.
1 A1= A1-0= M1= t= M1+...M6= 0
2 A2= A2-A1= M2= t= M2+…M6= 0
3 A3= A3-A2= M3= t= M3+…M6= 0
4 A4= A4-A3= M4= t= M4+…M6= 0
5 A5= A5-A4= M5= t= M5+M6= 0
6 A6= A6-A5= M6= t= M6= 0
Sec Sub Total 0.00 0.00
6 Total 0.00 ***
Section 7 - First Seven Periods only - if A8 is greater than A7, go to Section 8.
1 A1= A1-0= M1= t= M1+...M7= 0
2 A2= A2-A1= M2= t= M2+…M7= 0
3 A3= A3-A2= M3= t= M3+…M7= 0
4 A4= A4-A3= M4= t= M4+…M7= 0
5 A5= A5-A4= M5= t= M5+…M7= 0
6 A6= A6-A5= M6= t= M6+M7= 0
7 A7= A7-A6= M7= t= M7=
Sec Sub Total 0.00 0.00
7 Total 0.00 ***
Random Equipment Load Only (if needed)
R AR= 0.00 AR-0= 0.00 MR= 0 t=MR= 0 0.00 0.00 0.00 ***
Solenoid Valves 2 2
GOV Valve Positioner 1 1
Indicating Light 2 1
Control Relays 2 3
MOV Panel Indicating Lights 2 1
Site Processor 20 1
Leak Detection System
Grand total 31
Continuous Loads: L2 for 1440 minutes (1 day)
Equipment Steady State Power (W) QTY Total
Site Processor 20 1 20
Leak Detection System
Grand total 20
Random Load
Equipment Steady State Power (W) QTY Total
Grand total 0
DC Load Profile
Period Period scenarios Total Amperes Duration (min) Capacity Removed (Ah)
A1 L1 + L2 2.49 1440 59.65
A2 L1 1.51 5760.00 145.03
A3 0.00 0.00 0.00
A4 0.00 0.00 0.00
A5 0.00 0.00 0.00
A6 0.00 0.00 0.00
A7 0.00 0.00 0.00
A8 0.00 0.00 0.00
AR 0.00 0.00 0.00
Total 204.68
CELL TYPE PV415 CAPACITY RATING FACTORS
(1) (2)
Time t1 from Cell Time t2 from Cell Factor Kt1 for time Factor Kt2 for time
Discharge Time, t Factor Kt
Performance Performance t1, t2,
(Minutes) Amperes for time Amperes for time for time t
Tables (Minutes) Tables (Minutes) t1 t Batt. AH / (1) Batt. AH / (2)
2
Objective:
Determine the Size of Solar Array and Charge Controller ARAMCO Standards
for the 24V DC Photovoltaic System per ARAMCO Standards
Indicates data input required
Data: Indicates calculated value
DC CONTINUOUS LOADS
24 V E System voltage
20.52 V E End-of discharge voltage 350C
Qty.
0.97466 A 1 x 20 Watts E LDS
1.16959 A 1 x 24 Watts E RTU
0.34113 A 1 x 7 Watts E GOV Relay Panel
2.49 A E Sum of Loads
10% E Spare Capacity
2.73 A E Total Continuous Load (to be re-validated per actual installed load/s)
BATTERY INFORMATION
415 AH @ C120 E Battery AH Capacity PV415 Alcad E Vendor Catalog number
384 AH @ C5 E Battery AH Capacity
120.0 hrs E BT Required battery backup time in hours per SAES-P-103 Table 1 330C
330C
350C
330C
350C
Comment:
This calculation is preliminary only. It is the responsibility of the Construction Contractor and the Photovoltaic-System
Vendor to re-design and re-validate this Photovoltaic Array and Charge Controller Sizing Calculations per actual installed DC
continuous loads. 350C
BATTERY DUTY CYCLE DIAGRAM
L2
CURRENT
L1
R
TIME ( SEC )