Professional Documents
Culture Documents
-:oOo:-
Reach proposed in the present estimate: km 0 / 0 to 0 / 000 = 0.000 kms
Center Km. of the working stretch 0.000
A) For HBG metal:
HBG metal from Rayavaram quarry Rayavaram Quarry
54.412 Kms.
7/450 3/580
a) Cart track length = = 0.000 kms
b) Metalled road length:
From km / to / of Yeleswaram - Jeddangi road = 1.900 kms
From km / to / of Yeleswaram - Yerravaram road = 6.800 kms
From km / to / of Yerravaram - Kirlampudi road = 8.470 kms
From km / to / of Samalkot - Prathipadu road = 17.400 kms
From km 1 / 945 to 0 / 000 of Samalkot - Uppada road = 1.945 kms
From km 12 / 830 to 0 / 000 of Kakinada - Rajahmundry road = 12.830 kms
Total metalled road length 49.345 kms
Lead upto km 0 / 000 of Kakinada - Rajahmundry road 49.345 kms
Add working reach = 0.000 kms
c) Total lead = 49.345 kms
Or say: 34.000 kms
d) Lead charges for 34.000 kms lead ( including stacking charges) Rs. 441.10 / cum
B) For gravel:
Gravel quarry at Km.5/1 of S-G Rd. Quarry @ Balabhadrapuram
34.285 Kms.
7/450 3/580
a) Cart track length = = 0.000 kms
b) Metalled road length:
From km / to / of Quarry to S-G road = 1.000 kms
From km 5 / 100 to 0 / 000 of Samalkota - Gokavaram road = 5.100 kms
From km 13 / 900 to 0 / 600 of Kakinada - Rajahmundry road = 13.300 kms
Lead upto km 0 / 000 of Kakinada - Rajahmundry road 19.400 kms
Total metalled road length 19.400 kms
Add working reach = 0.000 kms
c) Total lead = 19.400 kms
Or say: 20.000 kms
d) Lead charges for 20.000 kms lead ( including stacking charges) Rs. 273.10 / cum
B) For Sand :
Sand from Km.3/4 of S-U Rd.
-:oOo:-
Reach proposed in the present estimate: km 0 / 0 to 0 / 000 = 0.000 kms
Center Km. of the working stretch 0.000
15.630 Kms.
0/0 0/6
Visakhapatnam
190.493 Kms.
7/260 0/0
Asst. Executive Engineer (R&B), Dy. Executive Engineer (R&B), Executive Engineer (R&B),
(R&B) East Section : Kakinada (R&B) East Sub-divn., : Kakinada (R&B) Division : Kakinada
ROAD METAL RATES
NAME OF WORK ::- Rates at Kakinada.
Seigniorage
Deduct 14%
Lead Machine
charges
Sl. Conveyan Initial Blasting CP & OH Toal Cost
Description of Metal Source of Supply in crushing
No ce cost charges charges from per Cum
Kms charges
conveyance
A) FOR ROAD WORKS
1 60 to 63 mm IRC and MoRTH HBG metal Rayavaram 34 441.10 419.00 70.00 -- -- -54.17 875.93
2 50 to 55 mm IRC and MoRTH HBG metal -- do -- 34 441.10 456.00 70.00 -- -- -54.17 912.93
3 40 to 45 mm IRC and MoRTH HBG metal -- do -- 34 441.10 588.00 70.00 -- -- -54.17 1044.93
4 SS Revetment work 300mm 164.00 -- -- -- 0.00 164.00
5 Quarry spall (Field picked metal) Av. of rate 25mm & 40mm Rayavaram 34 441.10 45.00 -- -- -- -54.17 431.93
6 150 mm soling stone HBG metal -- do -- 34 441.10 95.00 70.00 -- -- -54.17 551.93
7 40 to 45 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 588.00 70.00 147.00 -- -54.17 1191.93
8 25 to 27 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 944.00 70.00 236.00 -- -54.17 1636.93
9 19 to 22 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 984.00 70.00 246.00 -- -54.17 1686.93
10 12 to 14 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 780.00 70.00 195.00 -- -54.17 1431.93
11 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 656.00 70.00 164.00 -- -54.17 1276.93
12 5 to 7 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 504.00 70.00 126.00 -- -54.17 1086.93
13 2.36 to 5 mm IRC and MoRTH HBG M/C metal -- do -- 34 441.10 308.00 70.00 77.00 -- -54.17 841.93
14 HBG Stone chips 2.36mm and below -- do -- 34 441.10 340.00 -- -- -- -54.17 726.93
15 Gravel Km.5/1 of S-G Rd. 20 273.10 103.00 -- -- -- -33.54 342.56
B) FOR C.D. WORKS
16 40 mm SS-5 HBG M/C metal Rayavaram 34 441.10 620.00 70.00 155.00 -- -54.17 1231.93
17 25 mm SS-5 HBG M/C metal -- do -- 34 441.10 994.00 70.00 248.50 -- -54.17 1699.43
18 20 mm SS-5 HBG M/C metal -- do -- 34 441.10 1036.00 70.00 259.00 -- -54.17 1751.93
19 12 mm SS-5 HBG M/C metal -- do -- 34 441.10 822.00 70.00 205.50 -- -54.17 1484.43
20 10 mm SS-5 HBG M/C metal -- do -- 34 441.10 692.00 70.00 173.00 -- -54.17 1321.93
21 6 mm SS-5 HBG M/C metal -- do -- 34 441.10 532.00 70.00 133.00 -- -54.17 1121.93
22 Sand for Mortar Km.3/4 of S-U Rd. 18 247.90 462.00 -- -- -- -30.44 679.46
Seigniorage
Deduct 14%
Lead Machine
charges
Sl. Conveyan Initial Blasting CP & OH Toal Cost
Description of Metal Source of Supply in crushing
No ce cost charges charges from per Cum
Kms charges
conveyance
23 Sand for Filling -- do -- 18 247.90 342.00 -- -- -- -30.44 559.46
24 HYSD Steel 44000.00
25 6mm Mild Steel 45000.00
26 Mild Steel 43000.00
27 Cement 5900.00
28 Hume pipes 600mm Dia., NP3 5 43.96 1962.43 2006.39
29 Hume pipes 800mm Dia., NP3 5 58.61 3220.83 3279.44
30 Hume pipes 1000mm Dia., NP3 5 92.80 5022.78 5115.58
Asst. Executive Engineer (R&B), Dy. Executive Engineer (R&B), Executive Engineer (R&B),
(R&B) East Section : Kakinada (R&B) East Sub-divn., : Kakinada (R&B) Division : Kakinada
COST OF BITUMEN / MT
Name of Work
Rates at Kakinada.
Ref ::- For Emulsion (Bulk) :- HINCOL Price List With Effect From Dt.01-01-2015
For Bulk Bitumen 80/100, 60/70:- HPCL Price List With Effect From Dt. 01-01-2015
Lead from
Visakhapatnam
159.00 Kms 477.00 477.00 477.00
1.50 per KM
Unit : Cum
Taking out put = 100 Cum Page 70 of MoRT&H SDB
(A) Labour
0.02 day Mate 345.00 day
0.50 day Mazdoor unskilled 295.00 day
(B) Machinery
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum
1.00 hr Motor Grador for Grading @ 100 cum per hour 3216.00 hr
4.00 hr Water tanker 6 KL 624.00 hr
1.00 hr Vibratory roller 8T 2678.30 hr
2 Forming embankment with borrowed useful earth from outside road boundary by mechanical means upto SDR
with all leads and lifts including pre-watering of soil at borrow area, removal of top soil, excavation of soils at
borrowed area, conveyance of soil, depositing the soil on the embankment, spreading soil, breaking clods,
sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement
of table 300-2 of MoRT&H, including all hire and operational charges of T&P and seigniorage charges,
complete for finished item of work as per MoRT&H specification 305 (4 th revision) (Payment will be made
based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 345.00 day
1.00 day Mazdoor unskilled 295.00 day
(B) Machinery
100.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum
Page 8
Quantity Description of Item Rate per
160.00 t.km Tipper (for 1 Km = 160x1 = 160) 4.50 t.km
Add 10% of cost of carriage to cover cost of
loading and unloading
0.50 hr Dozer 80 HP for spreading @ 200 cum per hour 2575.60 hr
1.00 hr Motor Grador for Grading @ 100 cum per hour 3216.00 hr
3 Earthwork excavation in soils upto SDR by mechanical means including trimming bottom and side slopes in
accordance with requirements of lines , grades and cross sections etc., complete including seignioarge charges
for finished item of work for trench cutting as per MoRT&H specification 301(4 th Revision) and as directed by
the Engineer-in-Charge
Unit : Cum
Taking out put = 180 Cum Page 50 of MoRT&H SDB
(A) Labour
0.08 day Mate 345.00 day
2.00 day Mazdoor unskilled 295.00 day
(B) Machinery
180.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum
(C) Seigniorage charges
180.00 Cum Seigniorage charges 0.00 cum
4 Removal of unserviceable soils upto SDR including excavation, loading and disposal upto 1000 mts etc.,
complete including seignioarge charges for finished item of work as per MoRT&H specification 301(4 th
Revision) and as directed by the Engineer-in-Charge
Unit : Cum
Taking out put = 360 Cum Page 58 of MoRT&H SDB
(A) Labour
0.08 day Mate 345.00 day
2.00 day Mazdoor unskilled 295.00 day
Page 9
Quantity Description of Item Rate per
(B) Machinery
360.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum
16.36 Hrs Tippers 5.50 cum capacity 922.00 Hr
5 Construction of Granular sub-base by providing HBG material confirming to Grading - I of MoRT&H Table
400-2 including cost, seigniorage charges and conveyance of all materials to work site and spreading in
uniform layers with motor grader or by approved means, on prepared surface mixing by mix in place method
with Rotavator / approved means at OMC and compacting with vibratory roller to achieve the desired density
etc., complete for finished item of work as per MoRT&H Specification 401 (4 th revision) and as directed by
the Engineer-in-charge. ( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum Page 95 of MoRT&H SDB
(A) Labour
0.40 day Mate 345.00 day
2.00 day Mazdoor skilled 357.00 day
8.00 day Mazdoor unskilled 295.00 day
Total
(B) Machinery
6.00 hr Motor grader 3.35M Blade @50 cum/Hr 3216.00 hr
12.00 hr Tractor with Rotavator 422.00 hr
6.00 hr Vibratory roller 8T 2678.30 hr
3.00 hr Water tanker 6 KL 624.00 hr
Total
(C) Material
Coarse graded Granular sub-base Gr.I material as
per Table 400-2 of MORT&H
53mm to 26.5mm @ 35% 1414.43 Cum
134.40 cum (Av. rate of 40-45mm & 25-27mm HBG M/C
metal)
1326.93 Cum
26.5mm to 4.75mm @ 45%
172.80 cum (Av. rate of 25-27mm, 19-22mm, 12-14mm, 9.5-
11.2mm , 5-7mm & 2.36 - 5mm HBG M/C metal)
Page 10
Quantity Description of Item Rate per
Cost per 300 cum (E) + (F)
Rate per 1 cum
Rate to be adopted
5 Construction of Granular sub-base by providing HBG material confirming to Grading - III of MoRT&H Table
400-2 including cost, seigniorage charges and conveyance of all materials to work site and spreading in
uniform layers with motor grader or by approved means, on prepared surface mixing by mix in place method
with Rotavator / approved means at OMC and compacting with vibratory roller to achieve the desired density
etc., complete for finished item of work as per MoRT&H Specification 401 (4 th revision) and as directed by
the Engineer-in-charge. ( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum Page 95 of MoRT&H SDB
(A) Labour
0.40 day Mate 345.00 day
2.00 day Mazdoor skilled 357.00 day
8.00 day Mazdoor unskilled 295.00 day
Total
(B) Machinery
6.00 hr Motor grader 3.35M Blade @50 cum/Hr 3216.00 hr
12.00 hr Tractor with Rotavator 422.00 hr
6.00 hr Vibratory roller 8T 2678.30 hr
3.00 hr Water tanker 6 KL 624.00 hr
Total
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2 of MORT&H
9.5mm to 4.75mm @ 66% 1068.60 Cum
255.00 cum (Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm
HBG M/C metal)
2.36mm and below @34% 726.93 Cum
129.00 cum
(Rate of 2.36mm & below HBG metal)
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 300 cum (E) + (F)
Rate per 1 cum
Rate to be adopted
6 Scarifying the existing granular surface to a depth of 50 mm by Manual means including all labour charges
etc., complete as per MoRT&H (4th Revision) Specn. No.305.4.3 for finished item of work.
Page 11
Quantity Description of Item Rate per
(B) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)
(C) Total of (A) + (B)
(D) Add Contractors Profit at 10% on (A)+(B)
Cost per 100 sqm
Rate per 1 sqm
Rate to be adopted
1 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified
material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4 th Revision) Specn. No.305.4.3
8 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - II - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&9 of
MoRT&H Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance
and seignorage charges and spreading in uniform thickness, hand packing, rolling with Power Road Roller 8-
10 Tonnes in stages to proper grade and camber applying and brooming requisite type ' A ' screenings as per
table 400-8&9 and binding materials as to fill up the interstices of coarse aggregates,watering and compacting
to the required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as
directed by the Engineer-in-Charge (Payment will be made based on levels for finished item of work)
Page 12
Quantity Description of Item Rate per
217.80 cum 63mm IRC&MoRT&H HBG metal 875.93 cum
200.38 cum 45mm IRC&MoRT&H HBG metal 1044.93 cum
17.42 cum 22.40 mm IRC&MoRT&H HBG M/C metal 1686.93 cum
57.60 cum Screenings 13.2mm@ 0.12cum/10sqm 1181.93 cum
(Ave of 9.5-11.2 mm & 5-7 mm M/C )
28.80 cum Binding material @ 0.06 cum / 10sqm (Rate of 726.93 cum
2.36mm & Below)
Total
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 360 cum (E) + (F)
Rate per 1 cum
Rate to be adopted per 1 cum
9 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - III - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7& 9 of
MoRT&H Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance
and seignorage charges and spreading in uniform thickness, hand packing, rolling with Power Road Roller 8-
10 Tonnes in stages to proper grade and camber applying and brooming requisite type ' B ' screenings as per
table 400-8&9 and binding materials to fill up the interstices of coarse aggregates,watering and compacting to
the required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as directed
by the Engineer-in-Charge (Payment will be made based on levels for finished item of work)
10 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - II - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 45mm and below) as per Table 400-7&9 of MoRT&H
Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance and
seignorage charges and spreading in uniform thickness, hand packing, rolling with Power Road Roller 8- 10
Tonnes in stages to proper grade and camber applying and brooming requisite type ' A ' screenings as per table
400-8&9 and binding materials as to fill up the interstices of coarse aggregates,watering and compacting to the
required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as directed by
the Engineer-in-Charge (Payment will be made based on levels for finished item of work)
11 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - III - IRC
& MoRT&H - H.B.G Machine crushed metal as per Table 400-7& 9 of MoRT&H Specification 404 of 4 th
revision for Water Bound Macadam specification including cost, conveyance and seignorage charges and
spreading in uniform thickness, hand packing, rolling with Power Road Roller 8- 10 Tonnes in stages to proper
grade and camber applying and brooming requisite type ' B ' screenings as per table 400-8&9 and binding
materials to fill up the interstices of coarse aggregates,watering and compacting to the required density for
finished item of work as per MoRT&H specification 404 (4 th revision) and as directed by the Engineer-in-
Charge (Payment will be made based on levels for finished item of work)
12 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - II - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&9 of
MoRT&H Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance
and seignorage charges and spreading in uniform thickness, hand packing, rolling with Vibratory Road Roller
8- 10 Tonnes in stages to proper grade and camber applying and brooming requisite type ' A ' screenings as per
table 400-8&9 and binding materials as to fill up the interstices of coarse aggregates,watering and compacting
to the required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as
directed by the Engineer-in-Charge (Payment will be made based on levels for finished item of work)
Page 15
Quantity Description of Item Rate per
Total
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 360 cum (E) + (F)
Rate per 1 cum
Rate to be adopted per 1 cum
13 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - III - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7& 9 of
MoRT&H Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance
and seignorage charges and spreading in uniform thickness, hand packing, rolling with Vibratory Road Roller
8- 10 Tonnes in stages to proper grade and camber applying and brooming requisite type ' B ' screenings as per
table 400-8&9 and binding materials to fill up the interstices of coarse aggregates,watering and compacting to
the required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as directed
by the Engineer-in-Charge (Payment will be made based on levels for finished item of work)
Page 16
Quantity Description of Item Rate per
14 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - II - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 45mm and below) as per Table 400-7&9 of MoRT&H
Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance and
seignorage charges and spreading in uniform thickness, hand packing, rolling with Vibratory Road Roller 8- 10
Tonnes in stages to proper grade and camber applying and brooming requisite type ' A ' screenings as per table
400-8&9 and binding materials as to fill up the interstices of coarse aggregates,watering and compacting to the
required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as directed by
the Engineer-in-Charge (Payment will be made based on levels for finished item of work)
15 Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - III - IRC
& MoRT&H - H.B.G Machine crushed metal as per Table 400-7& 9 of MoRT&H Specification 404 of 4th
revision for Water Bound Macadam specification including cost, conveyance and seignorage charges and
spreading in uniform thickness, hand packing, rolling with Vibratory Road Roller 8- 10 Tonnes in stages to
proper grade and camber applying and brooming requisite type ' B ' screenings as per table 400-8&9 and
binding materials to fill up the interstices of coarse aggregates,watering and compacting to the required density
for finished item of work as per MoRT&H specification 404 (4th revision) and as directed by the Engineer-in-
Charge (Payment will be made based on levels for finished item of work)
16 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix macadem
specification including cost,seignorage of all materials and including premixing the material with water at OMC
in Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layers with paver in
base courses on well prepared surface and compacting with Vibratory roller to acheive the desired density etc.,
as directed by the Engineer-in-Charge and as per MoRT&H specification.406 (4 th revision) for finished item of
work. (Payment based on levels for finished item of work)
Page 18
Quantity Description of Item Rate per
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 225 cum (E) + (F)
Rate per 1 cum
Rate to be adopted per 1 cum
17 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine crushed stone
aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 80/100 grade @ 0.75 kg / sqm including cost,
seigniorage and conveyance of all materials to work site and laid on prepared surface and rolling with 8-10 T
Power Road Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4 th Revision)
and as directed by the Engineer-in-charge.
18 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine crushed stone
aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 60/70 grade @ 0.75 kg / sqm including cost,
seigniorage and conveyance of all materials to work site and laid on prepared surface and rolling with 8-10 T
Power Road Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4 th Revision)
and as directed by the Engineer-in-charge.
Page 19
Quantity Description of Item Rate per
Unit = sqm Page 141,142 of MoRT&H SDB
Taking output = 9000 sqm
(A) Labour
0.44 nos. Mate 345.00 day
9.00 nos. Mazdoor 295.00 day
2.00 nos. Mazdoor skilled 357.00 day
Total
(B) Machinery
7.20 hr Mechanical broom @ 1250 sqm/hr. 357.00 hr
7.20 hr Air compressor 250 cfm 507.50 hr
6.00 hr Hydraulic self propelled chip spreader @ 1500 2567.00 hr
6.00 hr sqm/hr.
Tipper 10Tonne capacity for carriage of stone 922.00 hr
chips from stock pile on road side to chip spreader
(Rate of Tipper 5 cum
6.00 hr Front end loader 1 cum bucket capacity 1646.00 hr
6.00 hr Bitumen pressure distributor @1750 sqm/hr 1498.00 hr
6.00 hr smooth wheeled roller 8 Ton 1146.70 h
Total
(C) Material
6.75 MT Bitumen 60/70 @ 0.75 Kg / sqm 46062.10 MT
36.00 cum Crushed stone chippings 6 mm nominal size 1086.93 cum
@0.004 cum/sqm
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 9000 sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted.
X Providing B.T. patchwork using 1.20 Cum of 40mm IRC size HBG metal to get compacted quantity of 1 Cum
precoated with bitumen 80/100 grade using a total quantity of 42 Kgs. including tack coat, cost and conveyance
of all materials and stacking the metal and chips at road side for pre-measurements, sectioning to camber and
spreading 9.50mm to 11.20mm HBG machine crushed chips at the rate of 0.13 Cum. per 1 Cum. of metal as
key stone and consolidation with 8-10 T power road roller and labour charges for picking, brushing and dusting
the existing road surface and hire charges of T&P etc., complete for finished item of work as per standard
specification APSS No.1510
Unit = Cum
(A) Labour
2.86 Nos. Mazdoor (as per Cir.Memo No.Maintenance / 295.00 Cum
EE(TEC)/TA.13/AE.4/2006, Dt.18.03.2006 of the
Chief Engineer (R&B), Roads, Hyderabad.)
(B) Machinery
0.27 Hour Add Hire charges of Power roller 1146.70 Hour
L.S. towards T&P
(C) Material
1.20 Cum 40mm size IRC HBG metal (including stacking) 1376.14 Cum
Page 20
Quantity Description of Item Rate per
0.13 Cum 9.50 to 11.20 size IRC HBG chips (including 1461.14 Cum
stacking)
42.00 Kgs. Bitumen 80/100 Grade 45100.97 MT
Total
Cost per 1 Cum. (A)+(B)+(C)
Rate to be adopted
X Providing Patch work using 1.33 cum of 9.5mm to 11.20mm IRC Size HBG chipsl to get compacted quantity of
1 Cum , precoated with bitumen 80/100 grade using a total quantity of 72 Kgs including tack coat, cost and
conveyance of all materials and stacking the chips at road side for premeasurements, sectioning to camber and
spreading machine crushed chips and consolidation with 8 to 10 Power road roller and labour charges for
picking , brushingand dusting the existing road surface and hire charges of T&P etc., complete for finished item
of work as per standard specification APSS NO 1510
Unit = Cum
(A) Labour
2.86 Nos. Mazdoor (as per Cir.Memo No.Maintenance / 295.00 Cum
EE(TEC)/TA.13/AE.4/2006, Dt.18.03.2006 of the
Chief Engineer (R&B), Roads, Hyderabad.)
(B) Machinery
0.27 Hour Add Hire charges of Power roller 1146.70 Hour
LS provision towards T&P
(C) Material
1.33 Cum 9.50 to 11.20 size IRC HBG chips (including 1331.10 Cum
stacking)
72.00 Kgs. Bitumen 80/100 Grade 45100.97 MT
Total
Cost per 1 Cum. (A)+(B)+(C)
Rate to be adopted
19 Providing and applying tack coat with bitumen Emulsion (Medium settting) (Bulk) using Emulsion pressure
distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical
broom for finished item of work as per MoRT&H Specification 503 (4 th revision) and as directed by the
Engineer-in-Charge.
20 Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 20 mm thickness by hot
mix plant using hard blasted granite crushed aggregates of 13.2mm to 0.09mm (Type 'B') as per table 500-26
of specification 512 of MoRT&H (4th Revision), premixed with bituminous binder 60/70 grade @ 19 Kg per 10
Sqm area, including cost and seigniorage of all materials and transporting the hot mix to work site, laying with
mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled roller 8 to 10
Tonnes as per MoRT&H Specification 512 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-charge.
5.00 nos. Skilled Mazdoor for checking line and levels. 357.00 day
Total
(B) Machinary
12.00 hr Hot mix plant 40 to 60 TPH 19120.00 hr
6.00 hr Generator 250 KVA 1850.00 hr
6.00 hr Front end loader 1 cum capacity 1646.00 hr
6.00 hr Mechanical Paver finisher @ 100 TPH 2249.00 hr
6.00 hr Smooth wheeled roller 8-10 Tonnes 1146.70 hr
Total
(C) Material
19.48 M.T (i) Bitumen 60/70 Grade @19 kg per 10 sqm 46062.10 MT
(ii) Aggregate
For Type 'B'
HBG M/C aggregates 13.2mm to 0.09mm @ 0.27
cum per 10 sqm
276.75 cum Average rate of IRC&MoRT&H HBG M/C metal 1072.93 cum
of sizes 12-14, 9.5-11.2, 5-7mm, 2.36 - 5mm and
HBG 2.36mm&below
Total
(D) Over head charges @ 5% (10%-VAT)
4.615 % Add for Over head charges @ 4.615% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10250 Sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted
Page 22
Quantity Description of Item Rate per
21 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using hard blasted
granite crushed aggregates of Grading -2 as per table 500-15 of specification 508 of MoRT&H (4 th Revision),
premixed with bituminous binder 60/70 grade @ 5% of mix and filler, transporting the hot mix to work site,
laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth
wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification 508 (4 th
Revision) complete for finished item of work in all respects as directed by Engineer-in-charge.(Payment will be
made based on levels for finished item of work)
5.00 nos. Skilled Mazdoor for checking line and levels. 357.00 day
Total
(B) Machinary
11.00 hr Hot mix plant 40 to 60 TPH 19120.00 hr
6.00 hr Mechanical Paver finisher @ 100 TPH 2249.00 hr
6.00 hr Generator 250 KVA 1850.00 hr
6.00 hr Front end loader 1 cum capacity 1646.00 hr
3.90 hr Power road roller 8 tonne for initial break down 1146.70 hr
3.90 hr rolling
Vibratory roler 8 tonne for intermediate rolling 2678.30 hr
3.90 hr Finish rolling with 6-8 tonne smooth wheeled 1646.00
tandem roller. hr
Total
(C) Material
22.50 M.T (I) Bitumen @ 5% by weight of mix 46062.10 MT
(ii) Aggregate
For Grading II
162.450 cum IRC &MORT&H HBG M/C chips 9.5 to 4.75mm 1068.60 cum
@ 57%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 9.5-11.2, 5-7mm,2.36 - 5mm
116.850 cum IRC &MORT&H HBG M/C chips 4.75 mm and 784.43 cum
below @ 41%
Average rate of IRC&MoRT&H HBG M/C metal cum
of sizes 2.36 - 5mm and 2.36mm& below
Page 23
Quantity Description of Item Rate per
22 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average output of
37.5 tonnes per hour using hard blasted granite crushed aggregates of Grading - II as per table 500-4 of
MoRT&H specificaion 504 (4th Revision) premixed with bituminous binder of 80/100 grade @ 3.3% by weight
of total mixture, transported to site, laid over a previously prepared surface with mechanical paver finisher to
the required grade, level and alignment and rolled as per Clauses 501.6 and 501.7 to achieve the desired
compaction for finished item of work as directed by the Engineer-in-Charge including hire and opeational
charges all T&P and all other contingent charges necessary including cost of seigniorage charges on all
materials etc., complete and as per MoRTH specification No. 504(4 th Revision) .
Unit = cum
Taking out put = 205 cum (450 tonne) Page 125,126,127 of MoRT&H SDB
(A) Labour
0.84 nos. Mate 345.00 nos.
14.00 nos. Mazdoor working with HMP, mechanical broom, 295.00 nos.
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction.
Page 24
Quantity Description of Item Rate per
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 9.5-11.2mm, 5 to 7mm
58.02 cum IRC &MORT&H HBG M/C chips 5mm and 784.43 cum
below @ 20%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 2.36 to 5mm and 2.36mm& below
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 205 cum (E) + (F)
Rate per 1 cum
Rate to be adopted
23 Construction of Gravel shoulders including cost, seigniorage charges and conveyance of all materials to work
site and spreading in uniform layers by approved means, on prepared surface and compacting with vibratory
roller to achieve the desired density at OMC etc., complete for finished item of work as per MoRT&H
Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day Mate 345.00 day
2.00 day Mazdoor skilled 357.00 day
8.00 day Mazdoor unskilled 295.00 day
Total
(B) Machinery
6.00 hr Vibratory roller 8T 2678.30 hr
3.00 hr Water tanker 6 KL 624.00 hr
Total
(C) Material
384.00 cum Gravel 342.56
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 300 cum (E) + (F)
Rate per 1 cum
Rate to be adopted
XX Construction of earthen shoulders with selected earth with laboratory MDD not less than 17.5 KN / cum.
obtained from approved source by mechanical means with all leads and lifts including excavation of soils at
borrowed area, conveyance of soil, depositing the soil on the shoulder, spreading soil, breaking clods,
sectioning, grading and consolidation with 8 to 10 Tonnes Power Road Roller @ FMC to achive the desired
density, including all hire and operational charges of T&P and seigniorage charges, complete for finished item
of work as per MoRT&H specification 305 (4th revision)
Page 26
Quantity Description of Item Rate per
XX Forming shoulders with borrowed useful selected earth having MDD of not less than 1.75 Gms/CC from
outside road boundary by mechnical means with a lead of 20 kms. and lifts including pre-watering of soil at
borrow area, removal of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the soils
on the embankment, spreading soils, breaking clods, sectioning, grading and consolidation with vibratory road
roller @ OMC to meet requirement of table 300-2 of MORT&H including all hire and operational charges of
T&P and seigniorage charges, complete for finished item of work as per MORT&H specification 305 (4th
revision) (Payment will be made based on levels only)
Page 27
Quantity Description of Item Rate per
24 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos Mate 345.00 day
1.00 nos Mason 357.00 day
15.00 nos Mazdoor 295.00 day
Total
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1231.93 cum
6.75 cum Sand at site 679.46 cum
2.43 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
2.00 hr Water tanker 6 KL 624.00 hr
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted
25 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
Unit = cum
Taking output = 15 cum Page331of MoRT&H SDB
(A) Labour
0.64 nos Mate 345.00 day
1.00 nos Mason 357.00 day
15.00 nos Mazdoor 295.00 day
Total
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1231.93 cum
6.75 cum Sand at site 679.46 cum
3.45 MT Cement at site 5900.00 MT
Total
Page 28
Quantity Description of Item Rate per
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
2.00 hr Water tanker 6 KL 624.00 hr
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted
26 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, seigniorage
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item of work as
per MoRT&H specification 1500, 1700, 2100 & 2702 (4 th Revision) and as directed by the Engineer-in-
Charge for C.C Pavement.
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1321.93 cum
6.75 cum Sand at site 679.46 cum
6.33 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
Page 29
Quantity Description of Item Rate per
27 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H and using fly ash (replacing cement by fly ash to the extent
of 15% and sand by 10%) including cost, seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and operational charges
of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (4 th
Revision) and as directed by the Engineer-in-Charge for base coarse below CC Pavement.
Unit = cum
Taking output = 15 cum Page 331 of MoRT&H SDB
(A) Labour
0.64 nos Mate 345.00 day
1.00 nos Mason 357.00 day
15.00 nos Mazdoor 295.00 day
Total
(B) Material
13.50 cum Cost of 40mm SS-5 HBG M/C metal 1231.93 cum
6.075 cum Sand at site 679.46 cum
2.933 MT Cement at site 5900.00 MT
1.274 MT Fly ash
28 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) and using fly ash (replacing cement
by fly ash to the extent of 15% and sand by 10%) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,
1700, 2100 & 2702 (4th Revision) and as directed by the Engineer-in-Charge for C.C Pavement.
Unit = cum
Taking output = 15 cum Page 345,346 of MoRT&H SDB
Page 30
Quantity Description of Item Rate per
(A) Labour
0.86 nos Mate 345.00 day
1.50 nos Mason 357.00 day
20.00 nos Mazdoor 295.00 day
Total
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1321.93 cum
6.08 cum Sand at site 679.46 cum
5.381 MT Cement at site 5900.00 MT
1.576 MT Fly ash
1.576 MT Conveyance charges of fly ash cum
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
(A)+(B)+( C)
(D) Form work
3.50 % Form work @ 3.50% on (A)+(B)+( C) 71828.47 Cum
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
(F) Total of (A) + (B)+( C)+(D)+(E)
(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted
29 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc.,
complete including seignioarge charges for finished item of work as per MoRT&H specification 304(4 th
Revision) and as directed by the Engineer-in-Charge
(B) Machinery
240.00 cum Rate as per G.O. Ms No 10, Dt 26/7/2005 13.00 cum
Page 31
Quantity Description of Item Rate per
(C) Seigniorage charges
240.00 Cum Seigniorage charges 0.00 cum
30 Providing first class bedding with Granular material below the pipes of Hume pipe culverts suitably
compacted / rammed including cost, seigniorage and conveyance of materials to site etc., complete as per
drawing and MoRT&H Specification 2900 ( 4th Revision) and as directed by the Engineer-in-Charge.
(B) Material
12.00 cum Cost of Granular material 342.56 cum
Total
© Machinery
2.50 hr Plate compactor/Power rammer 48.00 hr
0.05 hr Water tanker 6 KL capacity 624.00 hr
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted
31 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for foundations of HP culverts
Page 32
Quantity Description of Item Rate per
6.75 cum Sand at site 679.46 cum
3.45 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
2.00 hr Water tanker 6 KL capacity 624.00 hr
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum
Rate to be adopted
32 Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2200 (4th Revision) and as directed by the Engineer-in-Charge for body walls of HP Culverts.
33 Providing, laying Reinforced cement concrete Hume pipes of 600mm/800mm/1000mm Dia., NP-3 class for
pipe culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of
600mm/800mm/1000mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting
etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4 th Revision) and IRC Special
Page 33
Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work.
Providing, laying Reinforced cement concrete Hume pipes of 600mm/800mm/1000mm Dia., NP-3 class for
pipe culverts
Quantityincluding cost and conveyance of Pipes
Description etc., complete and Labour
of Item Ratecharges for
perlaying, jointing of
600mm/800mm/1000mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting
etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4 th Revision) and IRC Special
Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work.
800 mm Dia.,
(A) Labour
0.18 nos Mate 345.00 nos.
0.50 nos Mason 357.00 nos.
4.00 nos Mazdoor 295.00 nos.
Total
(B) Material
12.50 RM Cost of 800mm Dia., pipes 3279.44 RM
Total
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 12.5 metre (D)+(E)
Rate for 1 RM
Rate to be adopted
1000 mm Dia.,
(A) Labour
0.18 nos Mate 345.00 day
0.50 nos Mason 357.00 day
4.00 nos Mazdoor 295.00 day
Total
(B) Material
12.50 RM Cost of 1000mm Dia., pipes 5115.58 RM
Total
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)
Page 34
Quantity Description of Item Rate per
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 12.5 metre (D)+(E)
Rate for 1 RM
Rate to be adopted
34 Filling in between body walls with gravel including cost ,conveyance and seigniorage of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200&2907 (4 th
Revision) and as per Drawing and technical specifications for finished item of work
35 Providing SS Revetment 300 mm thick including cost, seigniorage charges and conveyance of materials to site
and including labour charges for packing the stones for revetment etc., complete for finished item of work as
per MoRT&H specification 2504 ( 4th revision ) and as directed by the Engineer-in-Charge for Pitching of
slopes
Page 35
Quantity Description of Item Rate per
36 Providing and laying filter material with Gravel underneath pitching in slopes including cost, seigniorage
charges and conveyance of materials to site including labour charges etc., complete for finished item of work
as per MoRT&H Specification 2504 (4th Revision) and as directed by the Engineer-in-Charge
37 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4 th
Revision) for footings and Raft foundation .
Page 36
Quantity Description of Item Rate per
Rate for 1 cum
Rate to be adopted
38 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine mixing,
laying in position,Compacting, Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4 th Revision) for Sub
structure .
39 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as directed by the Engineer-in-Charge for
Bed blocks & Backing walls
Page 37
Quantity Description of Item Rate per
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1321.93
6.75 cum Sand at site 679.46 cum
5.12 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
Total
(D) Form work
10.00 % Form work @ 10% on (A)+(B)+( C) 70743.81 Cum
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
(F) Total of (A) + (B)+( C)+(D)+(E)
(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted
40 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P etc., complete as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished
item as per MoRT&H specification 1500,1600,1700 & 2200 (4 th revision ) and as directed by the Engineer-in-
Charge for Deck slab
Page 38
Quantity Description of Item Rate per
Rate for 1 cum
Rate to be adopted
41 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per drawing BD/1-69( A) but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2702 (4th Revision) and as directed by the Engineer-in-Charge for wearing
coat over Deck slab.
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1321.93 cum
6.75 cum Sand at site 679.46 cum
6.10 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
2.25 nos Labour for cleaning deck slab concrete 295.00 day
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum M 30 Concrete
Rate to be adopted
42 Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per Approved drawing but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the Engineer-in-Charge for
Approach slab.
Page 39
Quantity Description of Item Rate per
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1321.93 cum
6.75 cum Sand at site 679.46 cum
6.05 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
Total
(D) Form work
2.00 % Form work @ 2% on (A)+(B)+( C) 76230.81 Cum
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
(F) Total of (A) + (B)+( C)+(D)+(E)
(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum M 25 Concrete
Rate to be adopted
43 Construction of precast VRCC railing of M20 grade using HBG crushed stone aggregate of size not exceeding
12 mm and fine aggregate conforming to table 1000-2 true to line and grade, tolerance of vertical RCC post not
to exceed 1 in 500, centre to centre spacing between vertical posts not to exceed 2000mm, leaving adequate
space between vertical posts for expansion including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and
operational charges of all T&P as per approved drawings and as directed during execution but excluding cost
of steel and its fabrication charges as per approved drawings and technical specifications for finished item of
work as per MoRT&H Specification 2703, 1500, 1600, 1700(4th Revision)
Page 40
Quantity Description of Item Rate per
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
Total
(D) Form work
12.00 % Form work @ 12% on (A)+(B)+( C) 68577.06 Cum
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
(F) Total of (A) + (B)+( C)+(D)+(E)
(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Cost of Railing for one side
0.3881 Cum Cost per 6.74 RM = 5914.09 cum
Cost per 1 RM =
Rate to be adopted
44 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100,2700 (4 th
Revision) for levelling course
Page 41
Quantity Description of Item Rate per
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 33 KVA 861.70 hr
45 Providing Grouted Revetment with rough stone (HBG) of not less than 300 mm size grouted with 0.20 cum of
CC (1:4:8) including cost, seigniorage charges and conveyance of materials to site and including labour charges
for packing the stones for revetment etc., complete for finished item of work as per MoRT&H specification
2504 ( 4th revision ) and as directed by the Engineer-in-Charge for quadrential revetment.
Page 42
Quantity Description of Item Rate per
Cost per 1 cum (D)+(E)
Rate to be adopted
46 Back filling behind Abutments with gravel including cost ,conveyance and seigniorage of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (4 th Revision)
and as per Drawing and technical specifications for finished item of work
(B) Material
12.00 cum Cost of Granular material 342.56 cum
Total
© Machinery
2.50 hr Plate compactor/Power rammer/road roller 48.00 hr
0.05 hr Water tanker 6 KL capacity 624.00 hr
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted
47 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG metal
satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to athickness of not less
than 600mm with smaller size towards the soil and bigger size towards the wall and provided over the entire
surface behind the abutment, wing wall and return wall to the full height compacted to a firm condition
including cost and conveyance of all metal seignorage charges ,and all labour charges as directed by the
departmental officers as per drawing and Technical specifications as per clause 710.1.1 of IRC:78 and Clause
2200 of MoRT&H (4th Revision) for finished item of work.
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum Cost of 150mm size IRC soling stone (HBG) 551.93 cum
6.00 cum Cost of 40mm size IRC HBG metal 1044.93 cum
Total
© Machinery
Page 43
Quantity Description of Item Rate per
0.06 hr Water tanker 6 KL capacity 624.00 hr
Total
(D) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted
48 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
49 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
50 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for foundations of R.C.C items.
51 Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including
cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and
conveyance of binding wire and all handling charges and operational charges etc., and including over lapping
welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per
the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as
per I.S.1786 of 1985 .
Page 45
Quantity Description of Item Rate per
Total
(B) Material
1.05 MT Mild steel bars including overlaps 43000.00 MT
6.00 Kg Binding wire 45000.00 MT
Total
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT
Rate to be adopted
52 Sand filling in foundation including cost, seignoirage and conveyence of all materials to site and watering,
tamping etc., complete for finshed item of work as per MoRT&H specification 304 (4 th Revision) and as
directed by the Engineer - in - Charge.
(B) Material
1.20 Cum Sand for filling 559.46 cum
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)
Or say
53 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges , centering, machine
mixing, laying in position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4 th
Revision) for Dividers .
Unit = cum
Taking output = 15 cum Page 335,455 of MoRT&H SDB
(A) Labour
0.86 nos Mate 345.00 day
1.50 nos Mason 357.00 day
20.00 nos Mazdoor 295.00 day
Total
(B) Material
8.10 cum Cost of 40mm SS-5 HBG M/C metal 1231.93 cum
4.05 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
1.35 cum Cost of 10mm SS-5 HBG M/C metal 1321.93 cum
6.75 cum Sand at site 679.46 cum
4.13 MT Cement at site 5900.00 MT
Total
© Machinery
Page 46
Quantity Description of Item Rate per
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
54 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as directed by the Engineer-in-Charge for
Cover slabs over side drains
Unit = cum
Taking output = 15 cum Page 472,457 of MoRT&H SDB
(A) Labour
0.86 nos Mate 345.00 day
1.50 nos Mason 357.00 day
20.00 nos Mazdoor 295.00 day
Total
(B) Material
8.10 cum Cost of 20mm SS-5 HBG M/C metal 1751.93 cum
5.40 cum Cost of 10mm SS-5 HBG M/C metal 1321.93 cum
6.75 cum Sand at site 679.46 cum
5.12 MT Cement at site 5900.00 MT
Total
© Machinery
6.00 hr Concrete mixer 0.4/0.28 cum 453.00 hr
6.00 hr Generator set 35 KVA 861.70 hr
Total
(D) Form work
4.00 % Form work @ 4% on (A)+(B)+( C) 70743.81
(E) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B)+( C)+(D)
(F) Total of (A) + (B)+( C)+(D)+(E)
(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted
55 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials, seigniorage charges, labour
charges, curing etc complete for finished item of work as directed by the Engineer -in-Charge
Unit = 10 sqm
Page 47
Quantity Description of Item Rate per
Taking output = 10 sqm Page 452 & 333 of MoRT&H SDB
(A) Labour
0.04 day Mate 345.00 day
0.50 day Mason 357.00 day
0.50 day Mazdoor 295.00 day
(B) Material
0.144 Cum Cement Mortar (1:5) 2780.43 Cum
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 740.18
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 10 sqm (D)+(E)
Or say
Sub-Analysis
Cement Mortar (1:5)
(a) Material
0.303 MT Cement 5900.00 MT 1787.70
1.05 cum Sand for Mortar 679.46 cum 713.43
2501.13
(b) Labour
0.04 day Mate 345.00 13.80
0.90 day Mazdoor 295.00 265.50
279.30
Rate per cum 2780.43
56 Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete
surfaces
Unit = 1 sqm
Taking output = 40 sqm Page 220 of MoRT&H SDB
(A) Labour
0.12 day Mate 345.00 day
2.00 day Painter 357.00 day
1.00 day Mazdoor 295.00 day
(B) Material
6.00 Litres Paint Confirming to requirement of clause 803.3 146.50 Lit
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 1929.40
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 40 sqm (D)+(E)
Rate for 1 Sqm
Or say
Page 48
Quantity Description of Item Rate per
XX Providing weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe extending
through the full width of the structure at 1.00m C/C in both horizontal and vertical direction so that the weep
holes in each horizontal direction is staggered from the weep holes laying above and below lines as shown in
drawing including cost and conveyance of the A.C pipes and labour charges for cutting to required length,
placing the pipe with a slope of about 1V : 20H towards stream side face etc., complete for finished item of
work for weep holes as per MoRT&H specification 2706 & 2200 (4 th Revision)
XX Cost and supply of Mastic pads 20mm thick ilncluding cost and conveyance of mastic pads to the required soze
amd fixing in position etc., complete as directed by the Engineer-in-charge.
Cost as per SSR for 25.40 mm thick Mastic pad 609.80 1 Sqm
Cost as per SSR for 12.70 mm thick Mastic pad 349.00 1 Sqm
Difference in cost of 12.70mm & 25.40mm thick 260.80 1 Sqm
Now required 20mm thick Mastic Pad
Cost of 12.70mm thick difference 260.80 1 Sqm
XX Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical specifications and as
directed by the Engineer-in-charge.
XX Dismantling of existing structure comprising of Cement Concrete including T&P and scaffolding wherever
necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres as per MoRT&H Spec. No.202 and as directed by the Engineer-
in-Charge.
Unit = cum Taking output = 1.25 cum MoRT&H SDB Spec. No.202 : 2.4 (i) A (Pg.24)
(A) Labour
0.04 day Mate 345.00 day
1.00 day Mazdoor for dismantling and loading 295.00 day
Total
(B) Machinery
0.27 hr Tractor-trolley 415.00 hr
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 420.85
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost for 1.25 cum
Rate per 1 cum
Or say
XX Dismantling of existing structure comprising of Reinforced Cement Concrete including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres as per MoRT&H Spec. No.202 and as directed by the
Engineer-in-Charge.
Unit = cum Taking output = 1.25 cum MoRT&H SDB Spec. No.202 : 2.4 (i) C (Pg.25)
(A) Labour
0.15 day Mate 345.00 day
0.25 day Blacksmith 345.00 day
3.50 day Mazdoor for dismantling, loading and unloading 295.00 day
Total
(B) Machinery
0.27 hr Tractor-trolley 415.00 hr
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 1282.55
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost for 1.25 cum
Rate per 1 cum
Page 50
Quantity Description of Item Rate per
Or say
XX Dismantling of existing structure comprising of Brick masonry in Cement Mortar including T&P and
scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking
the serviceable material with all lifts and lead of 1000 metres as per MoRT&H Spec. No.202 and as directed by
the Engineer-in-Charge.
Unit = cum Taking output = 1.25 cum MoRT&H SDB Spec. No.202 : 2.4 (ii) B (Pg.27)
(A) Labour
0.03 day Mate 345.00 day
0.75 day Mazdoor for dismantling, loading and unloading 295.00 day
Total
(B) Machinery
0.27 hr Tractor-trolley 415.00 hr
(C) Over head charges @ 5% (10%-VAT)
5.00 % Add for Over head charges @ 5% on (A)+(B) 343.65
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost for 1.25 cum
Rate per 1 cum
Or say
Page 51
Amount
atering of soil , removal
g soil, breaking clods,
MC to meet requirement
nd seigniorage charges,
(Payment will be made
6.90
147.50
154.40
1300.00
3216.00
2496.00
2678.30
9690.30
0.00
492.24
10336.94
1033.69
11370.63
113.71
114.00
1 Cum
anical means upto SDR
l, excavation of soils at
ng soil, breaking clods,
MC to meet requirement
nd seigniorage charges,
(Payment will be made
13.80
295.00
308.80
1300.00
Page 52
Amount
720.00
72.00
1287.80
3216.00
2496.00
2678.30
11770.10
0.00
603.95
12682.85
1268.29
13951.14
139.51
140.00
1 Cum
ottom and side slopes in
ing seignioarge charges
ion) and as directed by
27.60
590.00
617.60
2340.00
0.00
147.88
3105.48
310.55
3416.03
18.98
19.00
1 Cum
al upto 1000 mts etc.,
H specification 301(4 th
27.60
590.00
617.60
Page 53
Amount
4680.00
15083.92
19763.92
0.00
1019.08
21400.60
2140.06
23540.66
65.39
65.40
1 Cum
g - I of MoRT&H Table
k site and spreading in
by mix in place method
ieve the desired density
sion) and as directed by
k ).
138.00
714.00
2360.00
3212.00
19296.00
5064.00
16069.80
1872.00
42301.80
190099.39
229293.50
55828.22
285121.72
16531.78
347167.30
34716.73
Page 54
Amount
381884.03
1272.95
1273.00
1 Cum
- III of MoRT&H Table
k site and spreading in
by mix in place method
ieve the desired density
sion) and as directed by
k ).
138.00
714.00
2360.00
3212.00
19296.00
5064.00
16069.80
1872.00
42301.80
272493.00
93773.97
366266.97
20589.04
432369.81
43236.98
475606.79
1585.36
1585.00
1 Cum
uding all labour charges
ork.
69.00
1475.00
-604.50
939.50
Page 55
Amount
46.98
986.48
98.65
1085.13
10.85
10.90
1 Sqm
nd disposal of scarified
o.305.4.3
3.45
73.75
77.20
33.76
329.20
212.06
575.02
32.61
68.48
753.31
7.53
7.50
1 Sqm
ates of Grade - II - IRC
per Table 400-7&9 of
luding cost, conveyance
h Power Road Roller 8-
' A ' screenings as per
atering and compacting
4 (4 th revision) and as
tem of work)
3477.60
714.00
73750.00
77941.60
13760.40
14976.00
28736.40
Page 56
Amount
190777.55
209383.07
29386.32
68079.17
20935.58
518561.69
37514.38
662754.07
66275.41
729029.48
2025.08
2025.00
Cum
ates of Grade - III - IRC
per Table 400-7& 9 of
luding cost, conveyance
h Power Road Roller 8-
' B ' screenings as per
ring and compacting to
evision) and as directed
ork)
3477.60
714.00
73750.00
77941.60
13760.40
14976.00
28736.40
373238.55
132272.18
67774.75
20935.58
594221.06
42053.94
742953.00
74295.30
817248.30
2270.13
2270.00
Page 57
Amount
Cum
tes of Grade - II - IRC
400-7&9 of MoRT&H
conveyance and
er Road Roller 8- 10
screenings as per table
and compacting to the
n) and as directed by
k)
3477.60
714.00
73750.00
77941.60
13760.40
14976.00
28736.40
190777.55
238838.93
29386.32
68079.17
20935.58
548017.55
39281.73
693977.28
69397.73
763375.01
2120.49
2120.00
Cum
tes of Grade - III - IRC
fication 404 of 4 th
rage charges and
nes in stages to proper
-8&9 and binding
quired density for
y the Engineer-in-
3477.60
Page 58
Amount
714.00
73750.00
77941.60
13760.40
14976.00
28736.40
425745.48
132272.18
67774.75
20935.58
646727.99
45204.36
798610.35
79861.04
878471.39
2440.2
2440.00
Cum
tes of Grade - II - IRC
ble 400-7&9 of
uding cost, conveyance
Vibratory Road Roller
e ' A ' screenings as per
ering and compacting
revision) and as
tem of work)
3477.60
714.00
73750.00
77941.60
16069.80
14976.00
31045.80
190777.55
209383.07
29386.32
68079.17
20935.58
Page 59
Amount
518561.69
37652.95
665202.04
66520.20
731722.24
2032.56
2033.00
Cum
tes of Grade - III - IRC
ble 400-7& 9 of
uding cost, conveyance
Vibratory Road Roller
' B ' screenings as per
ng and compacting to
ision) and as directed
ork)
3477.60
714.00
73750.00
77941.60
16069.80
14976.00
31045.80
373238.55
132272.18
67774.75
20935.58
594221.06
42192.51
745400.97
74540.10
819941.07
2277.61
2278.00
Cum
Page 60
Amount
tes of Grade - II - IRC
400-7&9 of MoRT&H
conveyance and
atory Road Roller 8- 10
screenings as per table
and compacting to the
n) and as directed by
k)
3477.60
714.00
73750.00
77941.60
16069.80
14976.00
31045.80
190777.55
238838.93
29386.32
68079.17
20935.58
548017.55
39420.30
696425.25
69642.53
766067.78
2127.97
2128.00
Cum
tes of Grade - III - IRC
fication 404 of 4th
rage charges and
Tonnes in stages to
ble 400-8&9 and
to the required density
ed by the Engineer-in-
3477.60
714.00
Page 61
Amount
73750.00
77941.60
16069.80
14976.00
31045.80
425745.48
132272.18
67774.75
20935.58
646727.99
45342.92
801058.31
80105.83
881164.14
2447.68
2448.00
Cum
to Wet Mix macadem
erial with water at OMC
m layers with paver in
the desired density etc.,
on) for finished item of
165.60
714.00
2950.00
3829.60
10863.60
7920.00
9876.00
13494.00
10445.37
1872.00
54470.97
134118.67
150273.68
64769.46
Page 62
Amount
349161.81
20373.12
427835.50
42783.55
470619.05
2091.64
2092.00
Cum
G machine crushed stone
kg / sqm including cost,
and rolling with 8-10 T
ation 510 (4 th Revision)
151.80
2655.00
714.00
3520.80
2570.40
3654.00
15402.00
5532.00
9876.00
8988.00
6880.20
52902.60
304431.55
39129.48
343561.03
19999.22
419983.65
41998.37
461982.02
51.33
51.30
1 Sqm
G machine crushed stone
kg / sqm including cost,
and rolling with 8-10 T
ation 510 (4 th Revision)
Page 63
Amount
151.80
2655.00
714.00
3520.80
2570.40
3654.00
15402.00
5532.00
9876.00
8988.00
6880.20
52902.60
310919.18
39129.48
350048.66
20323.60
426795.66
42679.57
469475.23
52.16
52.20
1 Sqm
acted quantity of 1 Cum
at, cost and conveyance
ctioning to camber and
per 1 Cum. of metal as
g, brushing and dusting
f work as per standard
843.70
309.61
40.00
349.61
1651.37
Page 64
Amount
189.95
1894.24
3735.56
4928.87
4929.00
1 Cum
t compacted quantity of
ding tack coat, cost and
ectioning to camber and
and labour charges for
mplete for finished item
843.70
309.61
40.00
349.61
1770.36
3247.27
5017.63
6210.94
6211.00
1 Cum
sing Emulsion pressure
leaned with mechanical
and as directed by the
27.60
590.00
617.60
999.60
1421.00
1720.00
4140.60
31745.60
31745.60
1825.19
38328.99
Page 65
Amount
3832.90
42161.89
12.05
12.10
1 Sqm
20 mm thickness by hot
B') as per table 500-26
0 grade @ 19 Kg per 10
o work site, laying with
h wheeled roller 8 to 10
work in all respects as
289.80
4130.00
1785.00
6204.80
229440.00
11100.00
9876.00
13494.00
6880.20
270790.20
897289.71
296933.38
1194223.09
67896.71
1539114.80
153911.48
1693026.28
165.17
165.00
1 sqm
Page 66
Amount
ant using hard blasted
MoRT&H (4 th Revision),
e hot mix to work site,
t, rolling with smooth
H Specification 508 (4 th
charge.(Payment will be
289.80
4130.00
1785.00
6204.80
210320.00
13494.00
11100.00
9876.00
4472.13
10445.37
6419.40
266126.90
1036397.25
173594.07
91660.65
0.00
4143.50
1305795.47
78906.36
1657033.53
165703.35
1822736.88
9347.37
9347.00
1 Cum
Page 67
Amount
ng an average output of
I as per table 500-4 of
rade @ 3.3% by weight
anical paver finisher to
to achieve the desired
ng hire and opeational
niorage charges on all
289.80
4130.00
1785.00
6204.80
229440.00
1116.50
13494.00
11100.00
9876.00
4472.13
10445.37
6419.40
286363.40
669749.40
175009.21
137151.16
Page 68
Amount
45512.63
1027422.40
65999.53
1385990.13
138599.01
1524589.14
7437.02
7437.00
1 Cum
of all materials to work
mpacting with vibratory
work as per MoRT&H
138.00
714.00
2360.00
3212.00
16069.80
1872.00
17941.80
131543.04
7634.84
160331.68
16033.17
176364.85
587.88
588.00
1 Cum
s than 17.5 KN / cum.
g excavation of soils at
g soil, breaking clods,
C to achive the desired
mplete for finished item
Page 69
Amount
13.80
295.00
308.80
1300.00
15750.00
1575.00
0.00
0.00
0.00
1433.38
20058.38
0.00
1018.36
21385.54
2138.55
23524.09
235.24
235.00
1 Cum
Page 70
Amount
13.80
295.00
308.80
1300.00
14400.00
1440.00
0.00
2496.00
5170.20
2678.30
27484.50
0.00
1389.67
29182.97
2918.30
32101.27
321.01
321.00
1 Cum
Page 71
Amount
220.80
357.00
4425.00
5002.80
16631.06
4586.36
14337.00
35554.42
2718.00
5170.20
1248.00
9136.20
2484.67
52178.09
5217.81
57395.90
3826.39
3826.00
1 Cum
one aggregate and fine
ance of all materials to
ding all other incidental
MoRT&H specification
base coarse below CC
220.80
357.00
4425.00
5002.80
16631.06
4586.36
20355.00
41572.42
Page 72
Amount
2718.00
5170.20
1248.00
9136.20
2785.57
58496.99
5849.70
64346.69
4289.78
4290.00
1 Cum
egate (Coarse aggregate
uding cost, seigniorage
g, vibrating, curing etc.,
nished item of work as
ted by the Engineer-in-
296.70
535.50
5900.00
6732.20
14190.63
7138.42
4586.36
37347
63262.41
2718.00
5170.20
7888.20
2725.90
4030.44
84639.15
8463.92
93103.07
6206.87
6207.00
1 Cum
Page 73
Amount
one aggregate and fine
by fly ash to the extent
site and labour charges,
and operational charges
1500,1700, 2100 (4 th
t.
220.80
357.00
4425.00
5002.80
16631.06
4127.72
17304.70
38063.48
2718.00
5170.20
1248.00
9136.20
2610.12
54812.60
5481.26
60293.86
4019.59
4020.00
1 Cum
egate (Coarse aggregate
y ash (replacing cement
e of all materials to site
all other incidental and
&H specification 1500,
avement.
Page 74
Amount
296.70
535.50
5900.00
6732.20
14190.63
7138.42
4131.12
31747.9
57208.07
2718.00
5170.20
7888.20
71828.47
2514.00
3717.12
78059.59
7805.96
85865.55
5724.37
5724.00
1 Cum
ures as per drawing and
val of stumps and other
e extent required etc.,
H specification 304(4 th
110.40
2360.00
2470.40
3120.00
Page 75
Amount
0.00
279.52
5869.92
586.99
6456.91
26.90
27.00
1 Cum
pipe culverts suitably
etc., complete as per
er-in-Charge.
96.60
2065.00
2161.60
4110.72
4110.72
120.00
31.20
151.20
321.18
6744.70
674.47
7419.17
741.92
742.00
1 Cum
one aggregate and fine
ance of all materials to
ding all other incidental
MoRT&H specification
ons of HP culverts
220.80
357.00
4425.00
5002.80
16631.06
Page 76
Amount
4586.36
20355.00
41572.42
2718.00
5170.20
1248.00
9136.20
2785.57
58496.99
5849.70
64346.69
4289.78
4290.00
1 Cum
one aggregate and fine
ance of all materials to
ding all other incidental
MoRT&H specification
lls of HP Culverts.
220.80
357.00
4425.00
5002.80
16631.06
4586.36
20355.00
41572.42
2718.00
5170.20
1248.00
9136.20
5571.14
3064.13
64346.69
6434.67
70781.36
4718.76
4719.00
1 Cum
m Dia., NP-3 class for
s for laying, jointing of
g, lowering and hoisting
vision) and IRC Special
Page 77
Amount
48.30
178.50
885.00
1111.80
25079.93
25079.93
1309.59
27501.32
2750.13
30251.45
2420.12
2420.00
1 RM
62.10
178.50
1180.00
1420.60
40992.99
40992.99
2120.68
44534.27
4453.43
48987.70
3919.02
3919.00
1 RM
62.10
178.50
1180.00
1420.60
63944.73
63944.73
3268.27
Page 78
Amount
68633.60
6863.36
75496.96
6039.76
6040.00
1 RM
e of all materials to site
on No. 2200&2907 (4 th
96.60
2065.00
2161.60
4110.72
4110.72
120.00
31.20
151.20
321.18
6744.70
674.47
7419.17
741.92
742.00
1 Cum
ance of materials to site
nished item of work as
Charge for Pitching of
13.80
124.95
221.25
360.00
164.00
86.39
250.39
30.52
640.91
64.09
705.00
705.00
1 Cum
Page 79
Amount
uding cost, seigniorage
r finished item of work
harge
17.25
89.25
295.00
401.50
411.07
40.63
853.20
85.32
938.52
939.00
1 Cum
ze HBG crushed stone
ming to table 1000-2)
r charges for machine
ncidental and all other
n 1500,1700, 2100 (4 th
296.70
535.50
5900.00
6732.20
9978.63
7095.32
1784.61
4586.36
24367.00
47811.92
2718.00
5170.20
7888.20
2497.29
3246.48
68176.09
6817.61
74993.70
Page 80
Amount
4999.58
5000.00
1 Cum
ze HBG crushed stone
ming to table 1000-2)
es for machine mixing,
nd all other operational
0 (4 th Revision) for Sub
296.70
535.50
5900.00
6732.20
9978.63
7095.32
1784.61
4586.36
24367.00
47811.92
2718.00
5170.20
7888.20
6243.23
3433.78
72109.33
7210.93
79320.26
5288.02
5288.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
proved drawings and as
or finished item as per
Engineer-in-Charge for
296.70
535.50
5900.00
6732.20
Page 81
Amount
14190.63
7138.42
4586.36
30208.00
56123.41
2718.00
5170.20
7888.20
7074.38
3890.91
81709.10
8170.91
89880.01
5992.00
5992.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
mplete as per approved
on charges for finished
cted by the Engineer-in-
296.70
535.50
5900.00
6732.20
14190.63
7138.42
4586.36
30208.00
56123.41
2718.00
5170.20
7888.20
14148.76
4244.63
89137.20
8913.72
98050.92
Page 82
Amount
6536.73
6537.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
r-in-Charge for wearing
310.50
535.50
6195.00
7041.00
14190.63
7138.42
4586.36
35990.00
61905.41
2718.00
5170.20
7888.20
663.75
3874.92
81373.28
8137.33
89510.61
5967.37
5967.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
Engineer-in-Charge for
296.70
535.50
5900.00
6732.20
Page 83
Amount
14190.63
7138.42
4586.36
35695.00
61610.41
2718.00
5170.20
7888.20
1524.62
3887.77
81643.20
8164.32
89807.52
5987.17
5987.00
1 Cum
te of size not exceeding
of vertical RCC post not
0mm, leaving adequate
all materials to site and
ther incidental hire and
ution but excluding cost
ons for finished item of
cum
cum
cum
cum
296.70
535.50
5900.00
6732.20
12023.88
7138.42
4586.36
30208.00
53956.66
Page 84
Amount
2718.00
5170.20
7888.20
8229.25
3840.32
80646.63
8064.66
88711.29
5914.09
2295.26
340.54
341.00
1 RM
cum
cum
cum
cum
4007.39
315.07
315.00
1 RM
ze HBG crushed stone
rming to table 1000-2)
r charges for machine
ncidental and all other
00,1700, 2100,2700 (4 th
296.70
535.50
5900.00
6732.20
9978.63
7095.32
1784.61
4586.36
24367.00
47811.92
Page 85
Amount
2718.00
5170.20
7888.20
3121.62
65553.94
6555.39
72109.33
4807.29
4807.00
1 Cum
outed with 0.20 cum of
ncluding labour charges
MoRT&H specification
nt.
220.80
357.00
4425.00
5002.80
16631.06
4586.36
14337.00
35554.42
2718.00
5170.20
1248.00
9136.20
49693.42
3312.89
13.80
124.95
221.25
360.00
662.58
164.00
826.58
59.33
1245.91
124.59
Page 86
Amount
1370.50
1371.00
1 Cum
e of all materials to site
No. 2200 (4 th Revision)
96.60
2065.00
2161.60
4110.72
4110.72
120.00
31.20
151.20
321.18
6744.70
674.47
7419.17
741.92
742.00
1 Cum
% of 40 mm HBG metal
o athickness of not less
provided over the entire
ed to a firm condition
es as directed by the
1 of IRC:78 and Clause
110.40
2065.00
357.00
2532.40
3311.58
6269.58
9581.16
Page 87
Amount
37.44
37.44
607.55
12758.55
1275.86
14034.41
1403.44
1403.00
1 Cum
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per
151.80
1035.00
2360.00
3546.80
46200.00
360.00
46560.00
2505.34
52612.14
5261.21
57873.35
57873.00
1 MT
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per
117.30
690.00
1917.50
2724.80
Page 88
Amount
46200.00
270.00
46470.00
2459.74
51654.54
5165.45
56819.99
56820.00
1 MT
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per
138.00
690.00
1770.00
2598.00
46200.00
270.00
46470.00
2453.40
51521.40
5152.14
56673.54
56674.00
1 MT
up bars of all diameters
reinforcement including
ete including cost and
including over lapping
andard drawings, as per
0 (4 th revision) and as
96.60
517.50
1622.50
Page 89
Amount
2236.60
45150.00
270.00
45420.00
2382.83
50039.43
5003.94
55043.37
55043.00
1 MT
ls to site and watering,
(4 th Revision) and as
3.45
88.50
91.95
671.35
38.17
801.47
80.15
881.62
882.00
1 cum
ze HBG crushed stone
ming to table 1000-2)
es , centering, machine
ncidental and all other
n 1500,1700, 2200 (4 th
296.70
535.50
5900.00
6732.20
9978.63
7095.32
1784.61
4586.36
24367.00
47811.92
Page 90
Amount
2718.00
5170.20
7888.20
2497.29
3246.48
68176.09
6817.61
74993.70
4999.58
5000.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
proved drawings and as
or finished item as per
Engineer-in-Charge for
296.70
535.50
5900.00
6732.20
14190.63
7138.42
4586.36
30208.00
56123.41
2718.00
5170.20
7888.20
2829.75
3678.68
77252.24
7725.22
84977.46
5665.16
5665.00
1 Cum
gniorage charges, labour
harge
Page 91
Amount
13.80
178.50
147.50
339.80
400.38
37.01
777.19
77.72
854.91
855.00
1 Sqm
41.40
714.00
295.00
1050.40
879.00
96.47
2025.87
202.59
2228.46
55.71
55.70
1 Sqm
Page 92
Amount
ter AC pipe extending
ection so that the weep
below lines as shown in
ting to required length,
ete for finished item of
3009.00
713.43
3722.43
13.80
265.50
279.30
4001.73
1071.00
150.00
150.00
200.09
1571.09
10.35
178.50
73.75
262.60
91.68
1925.37
192.54
2117.91
70.60
71.00
1 RM
ads to the required soze
Page 93
Amount
498.91
499.00
1 Sqm
al specifications and as
30.70
31.00
1 RM
d scaffolding wherever
tacking the serviceable
rected by the Engineer-
13.80
295.00
308.80
112.05
21.04
441.89
44.19
486.08
388.86
389.00
1 Cum
51.75
86.25
1032.50
1170.50
112.05
64.13
1346.68
134.67
1481.35
1185.08
Page 94
Amount
1185.00
1 Cum
10.35
221.25
231.60
112.05
17.18
360.83
36.08
396.91
317.53
318.00
1 Cum
Engineer (R&B),
vision : Kakinada
Page 95
LEAD CHARGES (SSR 2014-15) Cost of Materials, Labour
Earth/Gravel/ Metal
Sand SSR 2014-15
loading 52.50 105.00 Material Rates As per SSR of PR Dept.
unloading 15.90 15.90 60 to 63 mm IRC & MoRTH HBG metal 419.00 Pg. No.17, Sl.53 (Roads)
stacking xx xx 50 to 55 mm IRC & MoRTH HBG metal 456.00 Pg. No.17, Sl.52 (Roads)
0.25 xx xx 40 to 45 mm IRC & MoRTH HBG metal 588.00 Pg. No.16, Sl.51 (Roads)
0.5 xx xx Roughstone 300mm (HBG)for revetment 156.00 Pg. No.13, Sl.9 (Roads)
1 31.50 30.40 Roughstone 225mm (HBG)for revetment 154.00 Pg. No.13, Sl.8 (Roads)
2 44.10 42.60 SS Revetment work 225mm 144.00 Pg. No.13, Sl.2 (Roads)
3 58.90 58.90 SS Revetment work 300mm 164.00 Pg. No.13, Sl.3 (Roads)
4 71.50 71.50 SS Revetment work 450mm 136.00 Pg. No.13, Sl.4 (Roads)
5 84.10 84.10 Laterite for Revetment 225mm 118.00 Pg. No.13, Sl.6 (Roads)
6 96.70 96.70 Laterite for Revetment 300mm 138.00 Pg. No.13, Sl.7 (Roads)
7 109.30 109.30 Jeddy stone above 450mm to 600mm 188.00 Pg. No.13, Sl.5 (Roads)
Quarry spall(Field picked metal) (42+48)/2 Pg.18
45.00
8 121.90 121.90 Av. Of rate 25mm & 40mm Sl. No.84 & 85
9 134.50 134.50 150 mm soling stone HBG metal 95.00 Pg. No.18, Sl.79 (Roads)
10 147.10 147.10 40 to 45 mm IRC & MoRTH HBG M/C metal 588.00 Pg. No.16, Sl.51 (Roads)
25 to 27 mm IRC & MoRTH HBG M/C metal 944.00 Pg. No.16, Sl.50 (Roads)
11 159.70 159.70
19 to 22 mm IRC & MoRTH HBG M/C metal 984.00 Pg. No.16, Sl.49 (Roads)
12 172.30 172.30
12 to 14 mm IRC & MoRTH HBG M/C metal 780.00 Pg. No.16, Sl.48 (Roads)
13 184.90 184.90
14 197.50 197.50 9.5 to 11.20 mm IRC & MoRTH HBG M/C metal 656.00 Pg. No.16, Sl.47 (Roads)
15 210.10 210.10 5 to 7 mm IRC & MoRTH HBG M/C metal 504.00 Pg. No.16, Sl.46 (Roads)
16 222.70 222.70 2.36 to 5 mm IRC & MoRTH HBG M/C metal 308.00 Pg. No.16, Sl.45 (Roads)
17 235.30 235.30 HBG Stone chips 2.36mm and below 340.00 Pg. No.18, Sl.92 (Roads)
18 247.90 247.90 Gravel 103.00 Pg. No.18, Sl.90 (Roads)
19 260.50 260.50 40 mm SS-5 m/c HBG metal 620.00 Pg. No.15, Sl.30 (Roads)
25 mm SS-5 m/c HBG metal 994.00 Pg. No.15, Sl.29 (Roads)
20 273.10 273.10