Professional Documents
Culture Documents
Rev - 14 - MS - Installation of Transformers
Rev - 14 - MS - Installation of Transformers
FOR
INSTALLATION OF TRANSFORMERS
TABLE OF CONTENTS
3. LOCATION OF ACTIVITY
6. OPERATION
7. INSTALLATION
8. FIXATION
9. RESPONSIBILITIES
16. DISTRIBUTION
1. INTRODUCTION AND SCOPE
This method of statement covers the on-site installations of Transformer as
defined in the General Specification.
This procedure will define the method to off-loading and installation to be used to
ensure that the transformers are correct and acceptable and shall conform to the
Contract Documents and Specification.
Section: TRANSFORMERS
Division: Installation
3. LOCATION OF ACTIVITY
Transformer for the whole building .
6. OPERATION
Material: Material used will be as approved by the Engineer. The sizes
and routes routing will be as per the approved Shop Drawings.
7. INSTALLATION
Off-loading:
Use Fork Lifts or Mobile Crane to off-load the transformers.
Make sure that the capacity of the fork lifts or mobile crane can carry
the weight of the transformers.
Off load the transformer on the designated off loading area.
Proper care must be observed during off loading to prevent
unnecessary damage or dents on the transformers.
Ensure that the transformers are properly protected and covered with
tarpaulin.
Pre-Installation:
All materials and documentation relevant to this particular section of
works shall be checked by the Construction Department prior to the
commencement of works ensuring that these are correct and approved
type.
Before any permanent works will continue, pre-inspection on all
materials, tools and access for installation to be carried out..
Installation:
It has been presumed that all related civil works has been completed
prior to transformer installation.
1. Before the transformer will be delivered to site, ensure that the
transformer railing is fixed as per approved drawings and comply on
municipality requirement.
2. Move the transformers from the designated off-loading area or storage
area using fork lift and set them in position near to the transformer
room.
3. Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
4. Push in the transformers inside the transformer room. Set the
transformer on their final positions and make sure that they are
properly secured and protected.
5. Raise Request for Inspection for Transformer Installation.
6. Conduct on site test for the transformer.
7. Test shall include winding insulation resistance test and shall conform
to manufacturer’s recommendation and specification.
8. All tests must be recorded and conducted in the presence of
Consultant by manufacturer testing engineer.
9. Dress and terminate the incoming and outgoing cables on the
transformers.
10. Ensure that the cables were supported properly.
11. Cable glands, lugs and termination kits shall be approved type.
12. After termination works has been completed, clean the transformer
cable box and ensure that it is free from foreign materials and excess
openings must be sealed off and ensure that all the connections are
properly tight and torque.
13. Raise Request for Inspection for the cable terminations and dressing.
8. FIXATION
Inspection, Testing and Commissioning:
Cover the cable boxes.
Bolts and nuts must be tightened properly.
Make sure that the transformer room is clean and free from foreign
materials.
9. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
1. Hand Tools
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
16. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer