You are on page 1of 7

METHOD STATEMENT

FOR
INSTALLATION OF TRANSFORMERS

 TABLE OF CONTENTS

1. INTRODUCTION AND SCOPE

2. APPLICABLE PROJECT SPECIFICATION

3. LOCATION OF ACTIVITY

4. HEALTH AND SAFETY

5. HEALTH AND SAFETY HAZARDS

6. OPERATION

7. INSTALLATION
8. FIXATION

9. RESPONSIBILITIES

10. MANPOWER REQUIRED

11. MATERIALS REQUIREMENTS

12. EQUIPMENTS REQUIREMENTS


13. WASTE MANAGEMENT
14. SPECIAL CONTROL MEASURES

15. SUPPORTING DOCUMENTATION

16. DISTRIBUTION
1. INTRODUCTION AND SCOPE
 This method of statement covers the on-site installations of Transformer as
defined in the General Specification.
 This procedure will define the method to off-loading and installation to be used to
ensure that the transformers are correct and acceptable and shall conform to the
Contract Documents and Specification.

2. APPLICABLE PROJECT SPECIFICATION

 Section: TRANSFORMERS

 Division: Installation

 Sub Division: Subdivision

3. LOCATION OF ACTIVITY
 Transformer for the whole building .

4. HEALTH AND SAFETY


 Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials. Ensure all
involved personnel shall be aware of the same.

5. HEALTH AND SAFETY HAZARDS


 Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.

6. OPERATION
 Material: Material used will be as approved by the Engineer. The sizes
and routes routing will be as per the approved Shop Drawings.

 Storage and Protection: Deliver components parts to site, completely


identified in accordance with shop and certified CAD Drawings prepared
for this work. Store in accordance with the manufacturer’s instructions,
above ground, properly protected from the weather and construction
activities.

7. INSTALLATION
 Off-loading:
 Use Fork Lifts or Mobile Crane to off-load the transformers.
 Make sure that the capacity of the fork lifts or mobile crane can carry
the weight of the transformers.
 Off load the transformer on the designated off loading area.
 Proper care must be observed during off loading to prevent
unnecessary damage or dents on the transformers.
 Ensure that the transformers are properly protected and covered with
tarpaulin.

 Pre-Installation:
 All materials and documentation relevant to this particular section of
works shall be checked by the Construction Department prior to the
commencement of works ensuring that these are correct and approved
type.
 Before any permanent works will continue, pre-inspection on all
materials, tools and access for installation to be carried out..

 Installation:
 It has been presumed that all related civil works has been completed
prior to transformer installation.
1. Before the transformer will be delivered to site, ensure that the
transformer railing is fixed as per approved drawings and comply on
municipality requirement.
2. Move the transformers from the designated off-loading area or storage
area using fork lift and set them in position near to the transformer
room.
3. Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
4. Push in the transformers inside the transformer room. Set the
transformer on their final positions and make sure that they are
properly secured and protected.
5. Raise Request for Inspection for Transformer Installation.
6. Conduct on site test for the transformer.
7. Test shall include winding insulation resistance test and shall conform
to manufacturer’s recommendation and specification.
8. All tests must be recorded and conducted in the presence of
Consultant by manufacturer testing engineer.
9. Dress and terminate the incoming and outgoing cables on the
transformers.
10. Ensure that the cables were supported properly.
11. Cable glands, lugs and termination kits shall be approved type.
12. After termination works has been completed, clean the transformer
cable box and ensure that it is free from foreign materials and excess
openings must be sealed off and ensure that all the connections are
properly tight and torque.
13. Raise Request for Inspection for the cable terminations and dressing.

8. FIXATION
 Inspection, Testing and Commissioning:
 Cover the cable boxes.
 Bolts and nuts must be tightened properly.
 Make sure that the transformer room is clean and free from foreign
materials.

9. RESPONSIBILITIES

 PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.

2. To ensure that the progressing of works is carried out according


to the planned program and as per the approved method of
statement.

3. To ensure that all the equipment and material required


executing the work are available according to the planned
construction program.

4. To co-ordinate with the Main contractor, MEP coordinator,


Safety Officer for a safe and proper execution of the works.

 SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.

2. To provide all necessary information and distribute


responsibilities to his construction.

3. To monitor the progress of work in relation with the work


program and to report to the Project Manager.

4. To co-ordinate with the safety officer and to ensure that the


works are carried out in safe practicing method.

 FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.

2. To ensure that his assistant foreman/ charge hand are aware of


the job requirements and they have enough information to carry
out their duties properly.
3. To ensure that the daily work is progressing as planned and
advice the site engineer of any requirement for additional
resources.

4. To ensure in consultation with the site engineer that the


manpower involved in the works are moving as agreed and
planned for the work.

5. To control disposal of waste materials according to the


instructions received from the site engineer.

6. To ensure full coordination with the safety officer to maintain


safe working and proper house keeping of the site, following the
proved safety measures and further ensure that all his working
team are aware of the same to prevent accident and losses.

7. To inform the site engineer regarding areas ready for inspection.

8. Foreman and the storekeeper are responsible for the distribution


and control of materials.

 SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.

2. Ensure all the implemented safety measures are adequate to


maintain safe working on the site.

3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.

10. MANPOWER REQUIRED


 Charge hand and Experienced Technicians

11. MATERIALS REQUIREMENTS


 Transformer and its accessories.
12. EQUIPMENTS REQUIREMENTS
 The equipments that will be engaged for Transformer Installation will be as
follows:

1. Hand Tools

2. Power Tools (if required)

3. Diagonal-Cutting Pliers

4. Wire Stripper/Cutter with Spring

5. Side-Cutting Pliers

6. Shank Screwdriver/Flat screw driver

7. Compression lug crimp tool

8. Necessary conduit for System Cabling

9. Knock out set (for conduit)

10. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves


& safety vest )

13. WASTE MANAGEMENT


 The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.

14. SPECIAL CONTROL MEASURES


 The following general control measures against Safety, Environment and
Quality shall be required for our scope of work and special control
measures are not applicable for us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made
available to site.
 All workers doing the work shall be briefed on this method statement
and risk assessment.

15. SUPPORTING DOCUMENTATION


 This method Statement should be read in conjunction with the below
referenced documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.

16. DISTRIBUTION
 Copy of this method statement shall be issued to the following for
information/ action/ comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer

You might also like