JSO Septic Tank (28 Aug.'07)
JSO Septic Tank (28 Aug.'07)
Describe in detail the Job Safety Observation: (including scenarios and recommendations)
_________________________________________________________________________________________________
Date of Job Safety Observation: 28, August’ 07 Time of JSO: 10:00 am
Person Involved: Management Company Name: Qatar Al Atiyah
Nationality: Indian, Nepali & Bangladesh Badge Number: Sub Contractor
Location of Incident: 33kV sub station Urinal IMCO Worksite Supervisor: Mhd. Abdul Rahman
At around 10:00 am a portable septic tank was already full and causing of sewage overflow, it will create a bad
smell in the surrounding and pollutant or contaminating the hazards.
Action Taken:
Immediately close and padlock the toilet room and inform to the site engineer the condition of the urinal of
their workers.
State actions taken to correct and prevent such occurrence: If closed what evidence have you to verify:
If still OPEN state measures for closure:
Recommendation;
If closed sign: Safety Officer: I hereby confirm that the Job Safety Observation has been closed and corrective preventive
methods applied