PLANT - DAILY MAINTENANCE SCHEDULE 5/27/2019

Planning Execution Permit Status TOTAL MANPOWER 67 Absent % 6% Other Manpower Engineers
(A+B+C)
% Manpower Planned VS Utilized
% Actual % Actual Unplanned
Job Type Manpower Manhours Manhours Manpower Idle Manpower Manpower Idle Manpower Planned Permits Permits Permit Permit in Unplanned Unplanned Permits In Manpower OT Jobs Completed % Jobs Jobs Cancelled % Unplanned Trade Total Deployed Worker Present Sup. Present Total Present as Trade Worker Present Sup. Present Desg. Present
160% 136% 125% Available Available Plannned Loading Manpower Utilized Utilized Issued Closed Progress Permits Permits Closed Progress Idle MHRS Manhours InProgress % % on today
120% 105% 100% 95% 100% 100% 100% 110% 100%
80% HT 10 80 84 105% -1 10 100% 0 4 4 3 1 0 0 0 0 75% 25% 0% 0% Hot Work 16 10 1 11 Catalyst 0 0 Planning Eng. 1 RECEIVED COMPLETED A
40% ST 27 216 205 95% 1 27 100% 0 14 14 12 2 4 3 0 4 86% 14% 0% 29% Static 27 27 1 28 Retubing 0 0 Static Eng. 1 CANCELLED CANCELLED B
0% RT 14 112 152 136% -5 14 100% 0 12 9 5 4 2 2 0 0 56% 44% 25% 22% Rotary 14 14 1 15 Shut down 0 0 Rotary Eng. 0 INPROGRESS G
1 2 3 4 5 6
IN 0 0 0 #DIV/0! 0 0 #DIV/0! 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! Insulation 0 0 0 0 QA/QC Eng. 1
% Manpower % Actual Manpower Utilized SC 8 64 80 125% -2 8 100% 0 3 2 2 0 0 0 0 0 100% 0% 33% 0% Scaffolding 10 8 1 9 Safety Eng. 1
Loading Total 59 472 521 110% -6 59 100% 0 33 29 22 7 6 5 0 76% 24% 12% 21% Total ( A ) 67 59 4 63 Total ( B ) 0 0 Total ( C ) 4

Planning Phase Reporting Phase Scaffolding - 199.72

Daily Weekly Permit Permit Job No. Of


Sl No:

Approx. No of Time Actual permit Manpower Idle Maximo Work


Notification/Work Order Description Area Shift Planned Planned Job Type
Time persons
MNHRS Engineer Permit No. Permit Received
suppose to Opened to
Received start Completion MHRS
Manpower Idle Reason Manpower No. of Hrs OT done OT Manhours OT Reason Permit status L B H Erection Removal Remarks Order No.
/Unplanned /Unplanned the work timing done OT
open
1 100002052384 Nitrogen Tanker Hose Connection & disconnection to be done JDU-UTI-752 G Planned Planned ST 4 2 8 DEVA 1-7030719 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.08 0 12:00:00 AM Completed 02 Tanker 100000478668
2 100002059008 Caustic tanker connection and disconnection to be done JDU-UTI-656-MP-RS656-P001A G Planned Planned ST 4 2 8 DEVA 1-7030721 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.08 0 12:00:00 AM Completed 02 Tanker 100000478669
3 100002056638 Sea water supply line ARV passing at AV-F street-7 junction to be attend JDU-UTI-681 G Planned Planned ST 4 3 12 DEVA 1-7031535 received 09:00:00 AM 09:00:00 AM 09:05:00 AM 06:00:00 PM 0.01 0 12:00:00 AM Inprogress ARV Fitup done
4 100003546089 STRAINER CLEANING OF MP-EE734-P001B JDU-UTI-734-MP-EE734-P001B G Planned Planned ST 4 3 12 DEVA 1-7037055 received 09:00:00 AM 09:00:00 AM 09:15:00 AM 06:00:00 PM 0.03 0 12:00:00 AM Completed Found 50% choked 100000478670
5 100002082173 736-SSF-B XV-112 FLTO to be attend JDU-UTI-736-736XV112 G Planned Planned ST 4 2 8 DEVA 1-7040475 received 09:00:00 AM 09:00:00 AM 09:15:00 AM 06:00:00 PM 0.02 0 12:00:00 AM Inprogress Valve removal done
6 100001980851 Desal-2 manway boxup to be done. JDU-UTI-927-2 G Planned Planned ST 6 4 24 DEVA 1-7031543 received 09:00:00 AM 09:00:00 AM 11:00:00 AM 06:00:00 PM 0.33 0 12:00:00 AM Completed Manhole and drain boxup done 100000478671
7 100003464638 INSPECTION OF FLAME ARRESTOR PYFR714-012 JDU-UTI-714-PYFR714-012 G Planned Planned ST 3 3 9 DEVA 1-7033176 received 09:00:00 AM 09:00:00 AM 09:40:00 AM 06:00:00 PM 0.08 0 12:00:00 AM Completed Removal & Boxup done 100000478672
8 100003465265 INSPECTION OF FLAME ARRESTOR PYFR714-011 JDU-UTI-714-PYFR714-011 G Planned Planned ST 3 3 9 DEVA 1-7033177 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Completed Removal & Boxup done 100000478673
9 100003465278 INSPECTION OF FLAME ARRESTOR PYFR714-014 JDU-UTI-714-PYFR714-014 G Planned Planned ST 3 3 9 DEVA 1-7033178 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Completed Removal & Boxup done 100000478674
10 - Acid tanker connection/disconnection JDU-UTI G Unplanned Unplanned ST 4 2 8 DEVA 1-7037070 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.08 0 12:00:00 AM Completed 01 Tanker 100000478675
11 - 721-P101C Strainer cleaning JDU-UTI G Unplanned Unplanned ST 4 3 12 DEVA 1-7044910 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Completed Cleaning done 100000478676
12 - 6" portable water line blinding JDU-UTI G Unplanned Unplanned ST 5 3 15 DEVA 1-7046208 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Completed Blinding done 100000478677
13 - CO2 tanker connection/disconnection JDU-UTI G Unplanned Unplanned ST 4 2 8 DEVA 1-7038368 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.08 0 12:00:00 AM Inprogress No tanker yet
14 100002021175 3" DM line leak prefabrication to be done in container area JDU-UTI-681 G Planned Planned HT 6 4 24 DEVA 1-7031534 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.17 0 12:00:00 AM Inprogress 3/4" 2nos joint completed
15 100002079520 736 plant air line leak near west side chlorine house at utlity station to be attend JDU-UTI-736 G Planned Planned HT 5 4 20 DEVA 1-7031356 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.17 0 12:00:00 AM Completed 1" 10 joint completed, 6mtr pipe replacement 100000478678
16 100002077105 Flow setting handle/knob is broken JDU-UTI-722-MP-RU722-P102B G Planned Planned HT 4 3 12 DEVA 1-7031537 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Completed 1/2" 1 joint done 100000478679
17 100002069441 Pump coupling to be done. JDU-UTI-675-MP-RS675-P008A G Planned Planned RT 5 3 15 ASHWIN 1-7033179 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Inprogress Pump removal done.
18 100002073370 Pump boxup to be done. JDU-UTI-752-MP-RU752-P002 G Planned Planned RT 5 3 15 ASHWIN 1-703154 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Inprogress assembly i/p
19 100003546090 P011B Boxup to be done JDU-UTI-656-MP-RS656-P011B G Planned Planned RT 6 3 18 ASHWIN 1-7037059 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.13 0 12:00:00 AM Inprogress allignment i/p
20 100002085048 Seal cooling line dechocking , blinding and pump removal for jamming . JDU-UTI-656-MP-RS656-P003A G Planned Planned RT 6 4 24 ASHWIN 1-7035357 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.17 0 12:00:00 AM Inprogress Dismentaling done. Spare needed
21 100002078829 Desal-2 -P204B oil cup leak to be attend. JDU-UTI-927-2-MP-EE927-P204B G Planned Planned RT 2 2 4 ASHWIN 1-7031538 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.08 0 12:00:00 AM Completed 204B completed 100000478680
22 100002070950 Scaffolding removal from Condensate tank line valve replacement job JDU-UTI-722-MV-RU722-V001 G Planned Planned SC 5 4 20 DEVA 1-7031054 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.17 0 12:00:00 AM Completed 2.7 2.7 2.7 98.415 2.7*2.7*2.7 x 5 nos removal done 100000478681
23 100001466724 S021A Scaffolding removal to be done. JDU-UTI-722-ME-RU722-S021A G Planned Planned SC 5 4 20 DEVA 1-7031055 received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.17 0 12:00:00 AM Completed 3.7 3.7 3.7 101.306 3.7*3.7*3.7 x 2nos removal done 100000478682
24 100002075178 766 V002A scaffolding Erection to be done for Media removal-SOFTNER UNITS- A JDU-UTI-766-MV-RU766-V002A G Planned Planned SC 5 8 40 DEVA not received 09:00:00 AM 09:00:00 AM 10:00:00 AM 06:00:00 PM 0.33 0 12:00:00 AM Cancelled Manpower diverted for yard housekeeping
ETP
1 100001634027 P022A/B suction duplex filter cleaning work. JDU-UTI-761-MP-RU761-P022A/B G PLANNED PLANNED ST 5 3 15 DEVA 1-7027774 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478683
2 100001936525 P410A Strainer cleaning to be done. JDU-UTI-761-MP-RU761-P410A G PLANNED PLANNED ST 4 3 12 DEVA 1-7030104 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478684
3 100001933729 P410B Strainer cleaning to be done. JDU-UTI-761-MP-RU761-P410B G PLANNED PLANNED ST 4 3 12 DEVA 1-7027772 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478685
4 100002024821 HTDS CL2 tonner connection work JDU-UTI-761-MS-RU761-105 G PLANNED PLANNED RT 0 not received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.00 0 12:00:00 AM cancelled
5 100003546131 PM OF MP-RU761-P702A JDU-UTI-761-MP-RU761-P702A G PLANNED PLANNED RT 5 3 15 ASHWIN 1-7035509 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478686
6 100002086041 Acid discharge pipe open/box up work after Modification by HHW near predoiler JDU-UTI-762 G PLANNED PLANNED RT 0 not received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.00 0 12:00:00 AM cancelled
7 100002048976 675-P002A pump assembly work JDU-UTI-675-MP-RS675-P002A G PLANNED PLANNED RT 6 3 18 ASHWIN 1-7032141 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478687
8 100002086902 MA-RU761-M401B MOTOR REMOVAL JOB JDU-UTI-761-MA-RU761-M401B G PLANNED PLANNED RT 5 3 15 ASHWIN 1-7035513 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478688
9 Notification STP spool removal work from discharge of P052D pump for flushing work JDU-UTI-761-MP-RU761-P052D G PLANNED PLANNED RT 0 not received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.00 0 12:00:00 AM cancelled
10 100002064361 P090A strainer cleaning to be Done JDU-UTI-761-MP-RU761-P090A G PLANNED PLANNED ST 4 3 12 DEVA 1-7035521 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478689
11 100002064362 P090C strainer cleaning to be Done JDU-UTI-761-MP-RU761-P090C G PLANNED PLANNED ST 4 3 12 DEVA 1-7032144 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478690
12 100002025535 Container area HHW for SS 600-26 BASE FRAME fabrication work JDU-UTI-600-26-HV-RU600-26-SS-01 G PLANNED PLANNED HT 7 4 28 DEVA 1-7032147 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.17 0 12:00:00 AM Completed 100000478691
13 100002015966 DAF Flight rectification to be done. JDU-UTI-761-MF-RU761-Y406 G Unplanned Unplanned RT 4 2 8 ASHWIN 1-7035524 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.08 0 12:00:00 AM Completed 100000478692
14 Notification DAF Flight rectification to be done. JDU-UTI-762-MF-RU762-Y406 G Unplanned Unplanned RT 4 2 8 ASHWIN 1-7032146 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.08 0 12:00:00 AM Completed 100000478693
15 100003631505 761-P409A -SPIDER REPLACE -L-225- 1 NOS JOB DONE. JDU-UTI-761 G Planned Planned RT 4 3 12 ASHWIN 1-7043008 received 09:00:00 AM 09:30:00 AM 10:00:00 AM 12:00:00 PM 0.13 0 12:00:00 AM Completed 100000478694