Reach 1 2 3 4
Rolling / Plain Rolling / Plain Rolling / Plain Rolling / Plain
Road terrain
Terrain Terrain Terrain Terrain
Two-lane single Two-lane single Two-lane single Two-lane single
Carriageway lanes carriageway road carriageway road carriageway road carriageway road
Reach 1 2 3 4
For 5 Years 9.71 9.71 9.71 9.71
For 6 Years 11.94 11.94 11.94 11.94
For 7 Years 14.3 14.3 14.3 14.3
For 8 Years 16.77 16.77 16.77 16.77
For 9 Years 19.36 19.36 19.36 19.36
For 10 Years 22.09 22.09 22.09 22.09
Suresh SE Cbe 94441 57725
(MD-662) including upkeeping for a period of 60
5
Rolling / Plain
Terrain
Two-lane single
carriageway road
5
1
2020
2020
5
1832
BOTH direction
1.380
6332.40
7421.56
NO
9
1924
5.00
0.5
5
9.71
11.94
14.3
16.77
19.36
22.09
zoorace@yahoo.com
Pavement Composition
(Strengthening)
Design Life 5 years
Strengthening to Puduchathiram - Portonovo road at km 29/2-32/8 (MD-662) including upkeeping for a period of 60 months
20.07 V (05.04.20)
Proposed
Required
BM
Reach Deflection Msa BM Overlay BM DBM BC Remarks
thickness
Thickness
in mm
Reach 1 2 3 4 5
Rolling / Plain Rolling / Plain Rolling / Plain Rolling / Plain Rolling / Plain
Road terrain Terrain Terrain Terrain Terrain Terrain
Two-lane Two-lane Two-lane Two-lane Two-lane
single single single single single
Carriageway lanes carriageway carriageway carriageway carriageway carriageway
road road road road road
Construction period 1 1 1 1 1
Reach 1 2 3 4 5
For 5 Years
9.71 9.71 9.71 9.71 9.71
Strengthening only
For 10 Years 22.09 22.09 22.09 22.09 22.09
20.07 V (05.04.20) S.Suresh SE Coimbatore 94441 57725
Pavement Composition (Strengthening) zoorace@yahoo.com
Strengthening
NametoofPuduchathiram
work : - Portonovo road at km 29/2-32/8 (MD-662) including upkeeping for a p
20.07 V (05.04.20)
1 0 50 VG 30 30 VG 30
2 0 50 VG 30 30 VG 30
3 0 50 VG 30 30 VG 30
4 0 50 VG 30 30 VG 30
5 0 50 VG 30 30 VG 30
Reach 1
Terrain ---------- Rolling / Plain Terrain
Two-lane single
Carriageway lanes --------
carriageway road
Constuction period in Years ---------- 1
Year of Traffic Census Taken ---------- 2020
Current year ---------- 2020
Annual growth rate of CV ---------- 5
For 15 Years
15
= 365 x ( ( 1+0.05 ) -1) x 1924 x 5 x 0.5
0.05
= 37.88 MSa
For 10 Years
10
= 365 x ( ( 1+0.05 ) -1) x 1924 x 5 x 0.5
0.05
= 22.09 MSa
For 5 Years
5
= 365 x ( ( 1+0.05 ) -1) x 1924 x 5 x 0.5
0.05
= 9.71 MSa