Location/ Sulaiman Jewellery, Elevator No- 1123. Date 14/11/2019 Approved By PM: Basil
Department: Developed:
Task/Activity: Main Rope & Main Sheave replacement Date of Last 06/05/2019 Signature of Person Giridharan
Review: Authorizing SWMS:
Legislation, Codes of Practice, Standards used in development of SWP:
Required PPE to
carry out the
activity:
Helmet Boots Eye Vest Gloves Hearing Respirator Harness
PHOTO /SKETCH WORK ACTIVITY HAZARDS PRESENT RISK RISK CONTROL MEASURES RESIDUAL RISK
(Show the correct process) (Steps in the activity/task) (What could cause injury) SCORE (What can be done to minimize the risk of injury) SCORE
• Check and verify both the upper and the lower
pit Stop switches.
• Rest the counterweight on the prop in the pit • Put the main switch OFF. Lock out and Tag out.
(prop is made of about 6 feet steel pipe which is • Use required PPEs like helmet, gloves etc.
Unintentional movement M13
1 verified for its load capacity. The said prop is also L3
of car • Lower the counter weight on the pipe by
supported from the counter weight rails for
cranking method.
proper vertical support below counterweight).
• Put the main switch OFF. Lock out and Tag out.
• Use required PPEs like helmet, gloves etc.
• Cut the rope after taking the required • Wear protective gloves, helmet, goggles and
measurement from the car hitch. other required PPEs etc.
• Fix thimble for the rope end and fix it on car hit • Assign Fire Warden in place
• Molding of Rope with Lead Melt spoon torch Cut and bruise hazard • Fire extinguisher
Hot Rope tip, Burn, Fire • Fire blanket
hazard • Remove all hazard materials from site
• Maintain Proper Housekeeping
M13
7 L2
• Release the car from safety action by hoisting the • Wear protective gloves, helmet, goggles etc.
Cut and bruise hazard
9 car a little by chain block. M13 • Take care of sprain while removing the chain L2
Sprain hazard
• Release the car from hanging on chain block. block.
10 • Remove the scaffolding in pit Fall Hazard E21 • Use full body harness and life line. M11
PHOTO /SKETCH WORK ACTIVITY HAZARDS PRESENT RISK RISK CONTROL MEASURES RESIDUAL RISK
(Show the correct process) (Steps in the activity/task) (What could cause injury) SCORE (What can be done to minimize the risk of injury) SCORE
• Ensure the main switch OFF. Lock out and Tag
out.
• Use required PPEs like helmet, gloves etc.
Unintentional movement
M13
11 • Remove the prop from below the counterweight. of car L3
This SWMS has been developed to reduce and manage the risks that are known to be on the above work site. All members of the team working on this site have read, understood and signed this SWMS.
Consequences Signature:
Serious injury Name:
Life threatening
Injuries or causing
Minor injury or Death or
Personal ailments not hospitalization
injury or multiple multiple life Date:
Harm requiring or multiple
First Aid serious injuries threatening
Criteria medical medical
Treatment. causing injuries.
treatment. treatment
hospitalization. Signature:
cases.
Insignificant Minor Moderate Major Catastrophic Name:
Probability: 1 2 3 4 5
Is expected to
Almost Date:
occur in most 5 M (9) H (16) E (22) E (24) E (25)
Certain
circumstances
Will probably Signature:
4 Likely M (6) M (13) H (19) E (21) E (23)
occur
Name:
Might occur at
Likelihood
Date: