Professional Documents
Culture Documents
Abstract - Most utilities use a standard small generator II. DEFINING THE COMPARISON METRICS
interconnection procedure (SGIP) process that includes a screen
for placing potential PV interconnection requests on a fast track In order to calculate the accuracy of the 15% of peak load
that do not require more detailed study. One common screening screen, metrics must be defmed for comparison between the
threshold is the 15% of peak load screen that fast tracks PV
PV scenarios (sizes, feeders, and locations) that do not cause
below a certain size. This paper performs a technical evaluation
of the screen compared to a large number of simulation results
problems and the interconnection screen threshold (1ST). The
for PV on 40 different feeders. Three error metrics are developed rest of this section explains the motivation for each error
to quantify the accuracy of the screen for identifying metric, provides the metric formulas, and demonstrates
interconnections that would cause problems or incorrectly examples of the calculation. The figures in this section are
sending a large number of allowable systems for more detailed only for demonstration purposes and are not reflective of any
study.
one distribution feeder or screening threshold.
Index Terms - distributed power generation, photovoltaic
systems, power distribution, power system interconnection A. SCREEN ACCURACY RATIO (SAR)
The fust metric investigates how close the 1ST is relative to
I. INTRODUCTION the minimum hosting capacity (HC) for each feeder. The
hosting capacity is determined for each feeder by using the
Large PV installations on the distribution system can have
methodology described in Section IV. Both the 1ST and HC
many potential impacts to local customer power quality and
will vary for each feeder depending on the load level, feeder
reliability, such as high or low voltages [1, 2], system losses
characteristics, voltage regulator settings, etc. A screen
[3], harmonics [4], increased wear to regulation equipment [5],
accuracy ratio (SAR) of the two numbers will be used to
voltage flicker [6], and protection [7, 8]. Therefore, before PV
determine the closeness of the screen to the fust PV size that
systems are allowed to interconnect with the grid, they must be
could potentially cause issues, equation (1).
studied to analyze and mitigate any impacts. These
interconnection policies vary from utility to utility, but many
He -1ST
utilities use a standard small generator interconnection SAR =
* 100 (1)
procedure (SGIP) process for PV that includes a screen for 1ST
placing requests on a fast track that do not require more
detailed study [9-11]. One common interconnection screening This number could be positive or negative, and it is similar
threshold (1ST) fast tracks PV smaller than 15% of peak load. to a percent error calculation with respect to the 1ST for how
Previously, very little work has been done to research and far it is above or below the He. Like each of the error metrics
perform technical evaluation of the interconnection screening defined in this paper, the optimal SAR value is near zero.
methods. In [12], 100 small generator interconnection Larger values for each of the error metrics means that the
procedure (SGIP) studies were analyzed to determine if PV screen is performing worse. In the case of SAR, the value is
caused adverse impacts on the electric power system. In [13, hopefully positive. 1ST values should be designed to be
14], EPRI compared the minimum hosting capacity of 18 conservative and smaller than the hosting capacity to ensure
feeders to the 15% of peak load 1ST. This paper expands on that any PV sizes and locations that could potentially cause
that concept to a larger number of feeders and develops issues are studied in more detail.
quantitative metrics for calculating the accuracy of the In order to provide graphical examples of the error metric
screening methods. Metrics will also be introduced to not only calculations, figures similar to [15, 16] are used to show the
compare the screen to the feeder's minimum PV hosting percent of scenarios at each PV size that would cause issues on
capacity, but to also analyze the distribution of the feeder's the feeder. For example, in Figure 1 the hosting capacity is 2.3
locational hosting capacity and the number of violations and MW because a PV of that size could be placed anywhere on
false-positives that the screen allows. This is an important the feeder without causing issues. In contrast, only 42% of the
concept because it analyzes the overall risk by how much of locations on the feeder could support a 10 MW PV system
the feeder could handle various sized PV interconnections. without violations. In Figure 1, the SAR is approximately
There are many locations of a distribution system that can equal to 70%, meaning that the 1ST could be raised by 70%
allow significantly more PV than the worst case location for this example system. In Figure 2, the 1ST is higher than
(feeder hosting capacity) or what is allowed by the 1ST. the HC, and SAR""-40%, meaning that the 1ST should be
lowered by 40%.
I
CI)
> the accuracy of the 1ST are not specific to only one feeder or
� 40
�
only specific types of feeders.
(.)
!G For this analysis, 40 real feeders from various utilities
W
-;
VI 20
�
/ around the United States were simulated using the detailed
.2 methodology described in Section IV. The 40 feeders range in
/
:u length from 1.8 km to 29.4 km. The number of buses in each
c VSA
Q)
(.) feeder also varies significantly from 142 buses to 6001 buses
CI)
2 4 6 8 10 per feeder. The peak load for each of the feeders ranges from
PVSize(MW) 0.6 MW to 28.5 MW. Of course the feeder peak load is highly
Figure 2. Example of an interconnection screen threshold (1ST) that
correlated with the voltage class of the feeder. The range of
passes PV systems that cause violations the screen allowed (VSA).
voltage classes is shown in Table I. There is also a range in
the incoming high-voltage transmission system at the
B. ViOLATiO NS THE SCREEN ALLO WED (VSA) substation for each feeder from 46 kV to 230 kV.
For the case that SAR is negative, this is caused by the 1ST
being too high. When this occurs, the screening criteria will TABLE I FEEDER VOLTAGE CLASSES
12 ,----- 8
10
� 10 +---- ---q---
"0
7
QI 8 +----
of 6
�
'0 6 +--5-- 6 �
CI)
... N
QI
.Q 4 iii
E 5 >
2 2 Q.
� 2
4
o
o 1 2 3 4 5 6 7
3
Number of Capacitors
2
Figure 4. Histogram of the number of capacitors on each of the 40
feeders. Figure 5. Ckt5 locational PV hosting capacity.
6
� �15% of Peak Load
--e- PV Hosting Capacity
I �
signature [16] shown in Figure 6. The feeder PV hosting I
capacity (HC) is shown in green for the largest PV that can be 5
interconnected anywhere on the feeder without causing issues. 3:
� 100
�4
Q)
N
I��
en 3
rt(
I/J _ Hosting Capacity
>
�
c
90
0 _ No Violations 1:)0/P �
AI I' I \
c.. t:l..
:;::; 2
�� �
co
80 c::::::J Only Voltage II
"0
:>
_ Only Thermal ?t �
1
��
-
.c 70 - I ll.
� 60
Ji\..,Gl "" l(\� ¥
Q)
0
N Feeders
en 50
Figure 8. The 15% of peak interconnection screen threshold (1ST)
>
D.. 40 and the first PV size with issues (hosting capacity) for each feeder.
.c
u
co 30
w
- Figure 9 shows the hosting capacity vs. 15% of peak load
co 20
1ST for each feeder. To the upper left of the diagonal line
:g
.;: 10 represents the 1ST being larger than the HC, which is a
co
c
Q) negative SAR error value. The negative SAR values are
u
(J) 2 4 6 8 10 concerning because the screen allows PV interconnections that
PV Size (MW)
Figure 6. Ckt5 feeder risk impact signature.
would potentially cause problems. Feeders to the lower right
in Figure 9 that are particularly far from the dashed black line
This type of analysis is performed for each of the 40 would result in high SAR values, which means unnecessarily
feeders. The hosting capacity of each feeder is shown in increased study time for the utility.
Figure 7, along with which type of violation limited the PV
hosting capacity.
"
"
,
x
4
"
x
co
5 f----I--t--�-i���L
� i�m�it�
e� d�b�y�T�h� e�r�
m�a�
I --4 o
� I ..J /1<.
�
,/
u
4 f----.--+--�--__1_�._r_-_+--+_-�
:ll 2
,/
[
co
c..
x� /
o
3 f·---.__-+--�--��'_r_-_+--+_--� �.... 1
,/ x x
x
�
/Xv
c
:;::;
I/J
o 2 I:;'� I x iXx >0<.
:I:
�� l �.
1 3 2 4 5 6 7
Hosting Capacity (MW)
o Figure 9. Comparison of hosting capacity vs. 15% of peak load 1ST.
Feeders
Figure 7. Hosting capacity of 40 feeders.
The SAR error value is calculated for each feeder, and the
distribution of errors for the 15% of peak load screen is shown
V. RESULTS in Figure 10. With a max of SAR=418%, the HC for that
feeder is more than 4 times larger than 15% of peak screen.
A. SCREEN ACCURACY RATIO (SAR)
There is also a feeder with SAR=-95%, which means the 1ST
The detailed analysis was performed for all 40 feeders to is much higher than the feeder's hosting capacity. On average,
determine the fIrst PV size that caused issues on the feeder, or SAR=83%.
the feeder hosting capacity. The results are compared to the
15% of peak load PV 1ST. These two numbers for each feeder
are shown in Figure 8, sorted by the feeder peak load. Figure
8 also demonstrates that the feeder hosting capacity is not well
correlated with the load.
1
�
(5 35 v
�
:>
30 /'
E
0 100 200 300 400 �
:g 25 /
Screen Accuracy Ratio (SAR) (%) .;:
L
V
Figure 10. The screen accuracy ratio (SAR) error distribution for the � 20
15% of peak load screen. Q)
� 15 L
B. VIOLATIONS THE SCREEN ALLO WED (VSA) '0
10 V
/
_
c:
Q)
The feeders with negative SAR values result in passing a � 5
certain number of PV interconnections that will cause Q)
Il.
0 �
operational problems on the distribution system. The 0 50 100 150 200
violations the screen allowed (VSA) are calculated based on Size of PV as Percent of Screening Threshold (%)
the percent of the feeder where a PV system that is 15% of Figure 12. Violations the screen allowed (VSA) for the 15% of peak
peak load would have been problematic. Figure 11 shows the load interconnection screen threshold (1ST).
VSA error metric for each of the 40 feeders individually. C. PO TENTIAL PERCENT INCREASE (PPI)
.10
0
;;
nJ
(5
:> 0 II I •• -
if 4000 "-- "
Feeders �
Q)
Figure 11. The VSA error metric for each feeder for the 15% of peak til
nJ 3000
load 1ST. �
<..l
.E
-
While the screen accuracy ratio (SAR) is calculated by c:
Q)
2000
averaging the individual values for each of the 40 feeders, this �
Q)
Il.
method is not recommended to obtain the average VSA. SAR 1000
is a one to one comparison of feeder hosting capacity to feeder �
"E
1ST. On the other hand, VSA includes the percentage of the $
0
feeder that can support the PV interconnection size. In order Il. 0
Feeders
to appropriately weight the violations based on feeder size, the Figure 13. Potential percent increase (PPI) for each feeder.
violations the screen allowed (VSA) is calculated for all
feeders together. For example, the 40 feeders have a total of Similar to the VSA metric, in order to calculate the average
14,207 buses for potential PV placement. The VSA is the PPI for the metric, it is not appropriate to average the
percent of all of those buses that, when connected with the individual PPI for each feeder. Instead the allowed
maximum PV size allowed by the screen, will result in issues interconnections (AI) are summed across all feeders and
on the feeder. Creating the curve from Figure 2 for all feeders divided by the summation of potentially allowable
results in Figure 12. interconnections (PAl) of all feeders. The potential percent