Organisational set up
Introduction A Chief engineer heads P.W.D. He is also technical
advisor to the govt. 4 additional chief engineer, 10.
Aim Superintending engineer, 18 executive engineer, 18 sub
This article is written to give an understanding of the divisional engineer, 26 assistant engineer and 40 sub
construction process of apartment buildings in a Govt. assistant engineers assist the chief engineer for planning
project, implemented by Public Works Depertment in design and monitoring of work. In the field level there are
Bangladesh. The project described and analysed in this 4 zonal additional chief engineers, 22 superintending
article comprises construction of 100 residential flats for engineers, 107 executive engineers, 255 sub divisional
senior govt. official at Dhaka City. The client of the engineers, 142 assistant engineers and 1307 nos. sub-
project is the Directorate of Accommodation under the assistant engineers and 19,361 nos.skiled &unskilled
Ministry of Housing and Public Works. employees for executing civil electrical and mechanical
I am a project manager in field level serving under works.
Public Works Department and my duties are supervision,
quality control, monitoring the progress of work from CE
field level, checking the bill of quantities submitted by the
contractor and administration of sub ordinate staff of my
office.
By competitive tender, nine enlisted contractors of ACE ACE ACE ACE
P.W.D have been selected to construct 10 nos. of
Buildings.The time schedule of completion of the work is
ACE ACE ACE ACE
10 months. The project is a turnkey basis. The
Department of Architecture prepared the architectural
drawings and the structural drawings are prepared by
P.W.D design division-II. The Planning Commission of
Bangladesh Govt. approved the project. The work of the SE SE
project started from October’98 and it is supposed to be
finished by July’99. But due to shortage of fund
disbursement and in the country the project will be EE
delayed. The article also includes the information about
the country and it’s various features.
SDE
2
Construction of Apartment Buildings under Government sector in Bangladesh
3
Md Mahabub Hassan
Design Stage WA WA WA
Project Organisation
The Department of Architecture under Ministry of Figure.-2 Organogram of PWD Maintenance Division
Housing and Public Works prepared the architectural
working drawings and Design div-II of P.W.D prepared E.E=Executive Engineer, S.D.E=Sub Divisional Engineer
S.A.E=Sub Assistant Engineer, W.A=Work Assistant
the structural designs of the highlighted project. The
implementation of the project is entrusted under P.W.D
Maintenance Division, Dhaka.
The Division office is the main basis of project
Purchasing, Procurement and Contacting
implementation in Public Works Department. The Forms
tendering, procurement, purchasing, contracts signing, As per tender clause of the project supply of all materials
payment to the contractors, issuing Govt. Cheque and requires for the works will be taken from the concern
continuous supervision of works is done by this unit of contractor.
organisation. Executive engineer heads the division. The contract agreement with the contractor is done
There are either two or three Sub-divisional engineers, under Form-2911 basis. It is a prefixed govt. form, used
one Assistant engineer and three Sub assistant engineers in every govt. constriction work.
under one Executive engineer. In the sub division office The main feature of the contract documents is as below: -
under one Sub-divisional engineer there are three sub- 1. The document contains bill of quantities, items of
assistant engineers &six work assistants to assist him. The works, rates and quantities.
sub assistant engineers mainly do the works of quantity 2. Quoting of rates is on percentage above or less of
survey. The Sub Divisional engineer is mainly responsible total cost.
for the quality and quantity of works done in the project. 3. Time schedule of completion of project work.
The S.D.E also does the works of cash purchase .For the 4. Specification of works.
underconsidered project a committee is formed headed by 5. Condition of payment of bill.
the Chief Engineer of P.W.D to monitor the projects one 6. Condition for acceptance of tender.
in every one-month. The organisation of the P. W.D 7. Condition for payment of S.T. items and NT. Items
Maintenance Division may be shown as Figure. -2 that evolved during execution of work.
8. Amount of taxes and security for the warranty period.
Condition & specification for site management.
4
Construction of Apartment Buildings under Government sector in Bangladesh
The figure: -3 shows the contract procedure followed of the project,project cost,financing,effect of the project
in the project. ,financial return ,employment opportunity ,production
,enviromental impact,recuring expenditure,project
Client impemention period etc.
The Ministry of Planning Approved the P.C.P of the
project. The final estimated cost for 100 flats standed to
256.9 million Taka.Accordingly the Department of
P.W.D Contractor Architecture prepared the working architectural drawing
and P.W.D Design Div.-11 done structural design.
Tender
Tender documents
Document preperation Project Financing
The project is financed from annual development
Tender Tender programme of Bangladesh Government.The enter amount
opening submission is in local currency.
Negotiation
Budget and Budget control
The estimated cost for the project considered 256.9
Acceptance
million Taka.No price escalation is included in the project
cost considering P.W.D’s schedule of rates will be
Contract unchanged during the implementation of the project.
Contract form signing But the budget flow and disbursement was curtailed in
the middle of project completion due to great loss of govt.
Revenue by the devastating flood.
Work order Work starts
Inspection
Progress of Information Technology
works
Most of the information technology using in this project is
Submission of in form of office letters. Use of modern information
Payment of bill
bill of quantity technology like computer and fax machines are used in
compilation of data and monitoring progress of works to
Ministry only. The flow of information within different
Warranty period Warranty offices and the contractor may be shown by following
flow chart.
Project Planning
To solve the housing problem of senior govt. officials in
the Dhaka city the Ministry of Housing and Public Works CHIEF ENGINEER
on it’s meeting on 30-10-94 decided to constructs 100 Administrative,
nos. flats at different places of Dhaka City It is also Financial decision level
decided that the flats will be in the vacant places within
the govt. houses so that the price of land can be excluded
from the project cost. The buildings will be 4 –storied, ADDL.C.E
Technical
load bearing brick structure. Initially the cost of the Decision level
project estimated around 200.3 million Taka. But
considering the high cost of land, and to provide parking
facilities in the ground floor the decision has been
changed by the concern ministry to built 6-storied frame SUPERINTENDING
ENGINEER
structure buildings with lift and parking facilities.
Project director
Accordingly the preliminary architectural drawing is
prepared by Department of Architecture.Based on the
EXECUTIVE
preliminary drawings a rough estimates is prepared by ENGINEER CONTRACTOR
P.W.D Maintenance Div., which form the basis of project Execution level
concept paper, the rough estimate is prepared on the basis
of P.W.D schedule of rates effective in 1998.The S.D.E
Project concept paper contains aim, objective, and Field level
description
Figure.-4, Informatiom flow chart.
5
Md Mahabub Hassan
Production Stage
Tendering and Contract Document
P.W.D Maintenance Div. Prepared the model estimate of
the project on the basis of P.W.D schedule of rates’1998.
The model estimate contains the civil construction work,
Sanitary and water supply work and electrical work. The
project director of the project invites the tender. The
special class contractors (Prequalified for turnkey
contract) were illegible to participate in the tender and the
time schedule of completion of work was 10 months. For A view of one of the newly constructed apartment building. Only
construction of 10 nos. of building 9nos of construction the structural part is completed
firms came out successful in the tender biding. The
workorder is issued by the Executive Engineer
Maintenance on the following contract document basis. Quality Assurance
. The project’s Quality Assurance is mentained by two
1. 2911 form is used in every contract. phases. First the Quality of material supplied to the site
2. Rates are in percent above or less on the estimated and Second during the execution of work. In the first
cost phase, when the concerned contractors arranged the
3. Time of completion of the project is 10 month construction materials to the site, the Sub Divisional
from the date issue of work order. Engineer checks first and if required approval from
4. Work specification, Design procedure and quality Executive Engineer or Superintending Engineer should be
control rules are in the contract. taken. In the case of stone, cement and reinforcing steel
5. Payment of bill of quantities are-Measure-and- the samples are taken from work site and tested in the
Value contract method. laboratory of Bangladesh University of Engineering
Technology.The physical properties of bricks and sands
are tested at the site by S.D.E concern and for Checking
the chemical properties it is sent to the laboratory.
6
Construction of Apartment Buildings under Government sector in Bangladesh
In the second face during execution of works, the items • Prefabrication of standardise large quantity
of works are checked and verified. All the concrete works units.Like doors,windows,partitions e.t.c
are done in presence of Sub assistant engineer and the
random samples are collected by S.D.E concern. These
random samples are regularly sent to testing laboratory.
Any items failed to attain the desired strength are Property Management
removed from the structure. Moreover Executive
Engineer, Project Director i.e. Superintending Engineer
and often Additional Chief Engineer Inspected the site to Life-cycle Economy
co-ordinate the quality and progress of the works P.W.D has it’s own “standard specification” of
construction work and “schedule of rates” for
construction. These are used as the benchmark of national
Economic Control, Budget Review and construction, and respectively standard and competitive in
Reconciliation price considering the present market condition of country.
During the contact period the rates of bill of quantity All the buildings that P.W.D used to construct are belongs
would be remain same. So if the required fund is available to govt. And financed from state revenue budget. Since
within this year, there is little chance to change the project the buildings of said project will be used by the
cost. But if the fund disburcement dalyed the contractors govt.officers in subsidise rate of rent it is difficult to
may not interested to continue the work. Then fresh calculate the life cycle economy in the formulated way.
tender is required for further construction, which may But for economic and efficient use of state money the life
require more time and money. Under the project 10nos.of cycle economy should be measured in advance before
buildings are constructed in 10 different place of Dhaka implementing the project.
City.Due to change of soil condition the volume work of
foundation varies to 4% of total cost of the project. But
the tenders are excepted 5% less than the estimated costs Maintenance Planning
this variation does not affect the project cost. Since the P.W.D maintains most of the govt. Buildings in a
project is on going one, we cannot to the budget review. standardise way. The “division” unit of P.W.D of a
If the entire required fund available in time the project particular area under the disposal of “executive
would be finished in schedule time also within the budget. engineer”is mainly responsible for maintenance work of
all the govt. structure of that area. The maintenance works
are divided into three parts.
Experiences to use in Future Projects 1. Daily maintenance and house keeping work. Which
Project should be design with clear picture of fund includes repair to small defects, maintaining the
disbursement in a single fiscal year. Advance method of utility lines and attending the complains of users.
construction like concrete batch plant is very much 2. Annual Maintenance, done once in a year. Which
required for better quality control of concrete. includes all type painting, small structural repair e.t.a.
Procurement of material should be bulk quantity for 3. Quarterly Maintenance, done once in every 4 year.
uniformity in construction. By standardising some parts Which includes small-scale renovation, changing old
of construction components like doors and window, service lines, major repair to doors windows and
ventilators etc and prefabricate it in industries the onsite toilets.
production can be reduced and quality control can be When major renovation required for a building a special
simplified. repair estimate is required for approval of concerned
authority for that and after getting fund the renovation
work is taken up.
Conclusions Following procedures are required to maintain a building
By gathering the experience in production stage we got Under P.W.D maintenance programme. After
the idea that project should have following criteria to completion of building, P.W.D sent a completion report to
improve the implementation process. the Director of Accommodation through the Secretary of
• Fair idea about fund. the Minitry.Secretary plays an important role as the
• Turnkey system of tender.i.e’s civil constraction, chairman of the Board of Accommodation and Chief
sanitary and water supply and electrical work Account Officer of the Ministry.as a Chairman he is
should be done by a single contractor in one responsible for the allotment of flats/residence and as a
project. Chief Account Officer he takes the responsibilities of all
• Quality control should be entrusted on contractors expenditure of the Ministry.
with ISO 9002 certificates. The Govt. Employees are getting additional 40 to 50%
• Monitoring the project work by computer from the of their salary as house rent allowance. The person, who
field level. gets a govt. accommodation, cannot receive this house
• Design and planning by CAD.Inrtoducing CPM rent allowance, moreover he has to pay 5 to 7.5% of his
and other modern method both in the design and salary as ahouse rent to govt. In this way govt. collects the
site. revenue and compensates maintenance cost.
7
Md Mahabub Hassan
First year is the warranty period of newly constructed Connection to the Design Stage—
building. During this warranty period the concerned
contractor is responsible for any maintenance of the Feedback
building. The first three years there is no maintenance During execution of work as a project manager I have
fund except house keeping and daily maintenance only. suggested some new product like concrete hollow blocks
From the 4th year the Ministry of Finance starts to place the to be used as a partition wall instead of normal bricks to
maintenance fund in every fiscal year. Normally 1% of minimise the cost of building as well as lowering the
the present cost of the building is calculated annual building load
maintenance fund requirement. In addition to that in every
4 years another 2% of building cost are calculated as
quarterly maintenance fund. In some special cases it may Experience to use in Future Project
rises to 4%. New building materials that has been introduced in the
The executive engineer is empowered to give sanction market should be included in the next P.W.D Schedule of
to daily maintenance work. The superintending engineer Rates so that the cost of building and as well as time of
has got the power of annual repair and quarterly repair construction can be reduced.
upto 100000.00 Taka for a single stucture. Approval for
special repair and any amount are given by Additional
Chief Engineer subjected to availability of fund. Conclusion
The Running cost of building i.e. payment for Life cycle economy is very much important issue to
utilisation of electricity and cooking gas is made by construct a building. Though in P.W.D scope of
residing person. The municipal taxes, water and sewerage calculating the life cycle economy in a formulated way is
service difficult, means to be introduced to calculate the life cycle
Charges are paid by govt, a small amount for these economy of building before construction.
facilities are deducted from the monthly salary.
References
FUND
Ministry of Finance a. Model estimate of the Project.
b. P.W.D Standard Manuel
c. PCP of the Project
d. Govt.Contract Form no. 2911
e. Different lecture scripts of ICM, LCHS.
f. Statistical yearbook of Bangladesh.
g. Contemporary Architecture Bangladesh
Other
Ministry of
Ministries
Housing and
Public Works
P.W.D
Users