You are on page 1of 6

Stage 1B

ThyssenKrupp Elevator ( India ) Guide Rail Alignment Report Job No.

Layout Drawing No.:


Project Name and Location :
Wing No. Lift No.

BRACKET DBG Landing sill Rail twist Fixing of Smoothn


Floor Name / Rail Diagonal CTL CTC
No. from diagonal car / cwt ess of rail
Nos. Car Cwt Car Cwt
pit A B B1 B2 C D E F A1 A2 Left Right Left Right
bracket joints

Reading as per GAD

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Name & signature of Contractor with Date Name & signature of NI Engineer with Date Name & signature of FQA-in-charge with Date
Doc. No. : 0095OP999901360 Page 18
Stage 1B Date :
ThyssenKrupp Elevator ( India )
Guide Rail Alignment Report Job No.

Layout Drawing No.:


Project Name and Location :
Wing No. Lift No.

BRACKET DBG Landing sill Rail twist Fixing of Smoothn


Floor Name / Rail Diagonal CTL CTC
No. from diagonal car / cwt ess of rail
Nos. Car Cwt Car Cwt
pit A B B1 B2 C D E F A1 A2 Left Right Left Right
bracket joints

Reading as per GAD

21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Name & signature of Contractor with Date Name & signature of NI Engineer with Date Name & signature of FQA-in-charge with Date
Doc No : 0095OP999901360 Page 19
Doc. No. : 0095OP999901360 Page 19