8 Planning and Estimating Works


Preparatory Activities The sur vey work is a continuous
There are several stages of preparations process carried out on a regular basis
before a civil works programme can to monitor t he performa nce a nd
1 commence. These preparatory activities condition of the road network. Equally,
will need staff resources and logistical the budget preparations are normally
support in order to be carried out in carried out a year in advance and
P L A N N I N G A N D P R E PA R AT I O N O F W O R K S

a timely fashion. For this reason, a therefore based on earlier preliminary


schedule of events defining when survey assessments of the road condition and
works, design, preparation of bidding required improvement works. When
documents a nd t he tendering of specif ic road improvement or new
works will take place is prepared. The construction project are proposed, it is
figure below outlines the sequence of necessary to carry out a detailed survey
preparatory activities required in order specifically for this purpose.
to secure that the road works take place
at the right time. When the work budgets have been
secured, detailed designs and work
This time schedule should cover the plans are prepared for each road
entire period starting from when works project. With the detailed plans
the initial surveys will take place completed, it is possible to commence
u nt i l c ont rac t awa rd a nd work s t he tendering process. Once t he
implementation. This will ensure that contracts have been awarded, the
the preparatory works are completed at detailed work plans need to be updated
the correct time before the necessary to (i) reflect the actual time at which the
budgets are available and works are contractor can commence works and (ii)
intended to start. It also allows for to reflect the specific arrangements of
the necessary supervision staff to be resources which the contractor intends
mobilised when works are ready to to make. The plans of individual work
commence. projects are finally compiled into an
BUILDING RURAL ROADS

overall programme describing all works


The first step among the preparatory under the supervision of the road works
activities is to establish in detail the agency.
composition of the actua l work s
requirements. All works planning is This planning and programming exercise
based on field surveys where the actual not only applies for construction works
condition of the road is established in but also provides the basis for planning
detail. Based on what is observed in of road maintenance. The planning
the field, it is possible to make specific process should therefore result in two sets
suggestions on how to improve the road of plans, one for the annual maintenance
and on this basis calculate quantities of progra mme a nd a not her for road
work and estimate costs. improvement works.