PRE-COMMISSIONING CHECK SHEET


INSTRUMENTS

Safeguarding System Acceptance


PROJECT
PROJECT No.
DESCRIPTION
SYSTEM
SYSTEM No.
DESCRIPTION
SERVICE
TAG No.
DESCRIPTION

MANUFACTURER MODEL No.


SERIAL No. REQN. No.
LOCATION AREA

Item Description of check Result

1. All Panel / Cabinet / Console Installation Acceptance check sheets completed and certified
2. Power Supply Voltage correct as per Project Specifications
3. Redundant Power Supply operating correctly
4. Redundant Safeguarding System operating correctly
5. Panel / Cabinet / Console HVAC / Heating System operating correctly
6. Panel / Cabinet / Console energised and operational as per Project Design
7. All Loop / Function Checks completed and certified
8. Safeguarding Logic tested & operational as per Project Design and C & E Diagrams
9. Graphics correct as per Project Drawings and Specification
10. Software operational without failure as per Project Design
11. Communications with Control System correct as per Project Specifications
12. Communications with SCADA System correct as per Project Specifications
13. All System Printers operating correctly
14. ‘As Built’ drawings correct
15.
REMARKS / OBSERVATIONS: