Professional Documents
Culture Documents
PROJECT
PROCUREMENT
MANAGEMENT
PROJECT PROCUREMENT
MANAGEMENT
• Project procurement management includes the processes
necessary to purchase or acquire products, services, or
results needed from outside the project team.
• Project procurement management includes the contract
management and change control processes required to
develop and administer contracts, or purchase orders
issued by authorized project team members.
1
11/29/2014
NEGOTIATION
STRATEGIES
• Deadline.
• Extreme demands.
• Good guy, bad guy.
• Missing man (limited authority)
• Attack
• Withdrawal
• Fair and reasonable
2
11/29/2014
PROJECT PROCUREMENT
MANAGEMENT
Project procurement
Management overview
PLAN PROCUREMENTS
• Plan procurements is the process of documenting project
purchasing decisions, specifying the approach, and
identifying potential sellers.
• Plan procurements process also includes consideration of
potential sellers, particularly if the buyer wishes to
exercise some degree of influence over acquisition
decisions.
• Plan procurement process includes consideration of the
risks involved with each make-or-buy decision.
3
11/29/2014
PLAN PROCUREMENTS
INPUTS
1. Project management plan
2. Requirements documentation
3. Risk register TOOLS & TECHNIQUES
4. Activity resource requirements
5. Project schedule 1. Make-or-buy analysis
6. Activity cost estimates 2. Expert judgment
7. Stakeholder register 3. Market research
8. Enterprise environmental factors 4. Meetings
9. Organizational process assets
OUTPUTS
1. Procurement management plan
2. Procurement statement of work
3. Procurement documents
4. Source selection criteria
5. Make-or-buy decisions
6. Change requests
7. Project documents updates
PLAN PROCUREMENTS
• Make-or-buy analysis.
• Determine whether particular work can be best accomplished by the
project team or must be purchased from outside sources.
• Capability.
• Secrecy.
• Control.
4
11/29/2014
PROJECT PROCUREMENT
MANAGEMENT
Example
Purchase investment cost is $2000, Daily cost is $40 and
Daily Lease cost $240. How long will it take for the lease cost
to be the same as the purchase cost?
• 2000 + 40 * X = 240 * X
• 2000 = 240*x - 40*x
• 2000 = (240-40) x
• X = 2000 / 200 = 10 days
PROCUREMENT
DOCUMENTS
• Procurement documents are used to solicit proposals from
prospective sellers.
• Terms such as bid, tender, or quotation are generally used when the
seller selection decision will be based on price.
• The term proposal is generally used when other considerations such
as technical capability or technical approach are paramount.
• The common types of procurement documents may include:
• Request for information (RFI)
• Invitation for bid (IFB)
• Request for proposal (RFP)
• Request for quotation (RFQ)
5
11/29/2014
CONTRACT STATEMENT
OF WORK
• Each individual procurement item requires a separate contract
statement of work (SOW)
• SOW for each contract is developed from the project scope statement,
the project WBS, and the WBS dictionary
• The contract (SOW)
•Describe the procurement item in sufficient detail to allow prospective
sellers to determine if they are capable of providing the item.
•Written to be clear, complete, and concise.
•Can be revised and refined as required as it moves through the
procurement process until it is incorporated into a signed contract.
•Multiple products or services may be grouped as one procurement
item with a single contract SOW
PROJECT PROCUREMENT
MANAGEMENT
CONTRACTS
‐ Contracts are a legally binding documents (formal agreement),
should state all requirements.
‐ Contract must be followed and everything provided in it must
be done.
‐ Any change must be written and formally controlled and
approved by both parties.
‐ Contracts are legal relationships subjects to remedy in the
courts.
‐ the project management team may seek support early from
specialists in contracting, purchasing, law, and technical
disciplines.
6
11/29/2014
PROJECT PROCUREMENT
MANAGEMENT
CONTRACTS
‐ Contracts types are :
• Fixed Price
• Cost Plus
• Time & Material
FIXED PRICE
CONTRACTS
• Firm fixed price contracts (FFP)
‐ The most commonly used contract type is the FFP.
‐ It is favored by most buying organizations.
7
11/29/2014
FIXED PRICE
CONTRACTS
• Fixed price incentive fee contracts (FPIF)
‐ this fixed‐price arrangement gives the buyer and the seller
some flexibility in that it allows for deviation from performance,
with financial incentives tied to achieving agreed to metrics.
‐ Under FPIF contracts, a price ceiling is set, and all costs above
the price ceiling are the responsibility of the seller who is
obligated to complete the work responsibility of the seller, who
is obligated to complete the work.
‐ Fixed price with economic price adjustment contracts (FB‐EPA)
This contract type is used whenever the sellers performance
period spans a considerable period of years, as is desired with
many long‐term relationships
COST-REIMBURSABLE
CONTRACTS
• This category of contracts involve payments to the seller
for all legitimate actual costs incurred for completed work,
plus a fee representing seller profit.
• A cost‐reimbursable contract gives the project flexibility to
redirect a seller whenever the scope of work cannot be
precisely defined at the start and needs to be altered, or
when high risks may exist in the effort.
8
11/29/2014
COST-REIMBURSABLE
CONTRACTS
• Cost plus fixed fee contracts (CPFF)
The seller is reimbursed for all allowable costs for performing the
contract work, and receive a fixed fee payment calculated as a
percentage of the initial estimated project costs.
• Cost plus award fee contracts (CPAF)
The seller is reimbursed for all legitimate costs, but the majority of the
fee is only earned based on the satisfaction of certain broad subjective
performance criteria defined and incorporated into the contract
• Cost plus incentive fee contracts (CPIF)
The seller is reimbursed for all allowable costs for performing the
contract work and receives a predetermined incentive fee based upon
achieving certain performance objectives as set forth in the contract
9
11/29/2014
EXAMPLE 2 …
Seller EXCEEDED cost!
They will get penalized!
Excess Cost= 150 – 160 = ($10K)
Seller’s share (penalty) of loss = 20% *
10K = ($2K)
Seller’s total fees = 20 ‐ 2 = $18K
Final price = cost + fees
= 160 + 18 = $178k
10
11/29/2014
EXAMPLE 4 ..
Seller EXCEEDED cost!
They will get penalized!
Excess Cost= 250 – 200 = ($50K)
Seller’s share (penalty) of loss = 40% *
50K = ($20K)
Seller’s total fees = 50‐ 20 = $30K
Final price = cost + fees
= 250 + 30 = $280k
The seller will only get the ceiling $260k
EXAMPLE 5 ..
Seller is right on target cost! Bulls eye!
No incentives. No penalty.
Seller’s total fees = 50
Final price = cost + fees
= 200 + 50 = $250k
11
11/29/2014
EXAMPLE 6 ..
Seller saved on cost.
Cost savings = 200 – 190 = $10k
Incentive = 40% * 10 = $4k
Seller’s total fees = 50 + 4 = $54k
Final price = cost + fees
= 190 + 54= $244k
12
11/29/2014
TYPES OF CONTRACTS
(SUMMARY)
• Fixed
• For a well‐defined product
or requirements
• May include incentives?
• Reimbursement
• Payment of actual COST +
PROFIT
• Include direct & indirect
costs
• Time and Material
• Fixed price per unit
• Variable quantity
RANGE OF CONTRACT
TYPES VERSUS RISK
13
11/29/2014
CONDUCT PROCUREMENTS
INPUTS
1. Procurement management plan TOOLS & TECHNIQUES
2. Procurement documents
3. Source selection criteria 1. Bidder conference
4. Seller proposals 2. Proposal evaluation techniques
5. Project documents 3. Independent estimates
6. Make-or-buy decisions 4. Expert judgment
7. Procurement statement of work 5. Advertising
8. Organizational process assets 6. Analytical techniques
7. Procurement negotiations
OUTPUTS
1. Selected sellers
2. Agreements
3. Resource calendars
4. Change requests
5. Project management plan updates
6. Project documents updates
BIDDER CONFERENCES
•Bidder Conferences are meetings with prospective sellers
prior to preparation of a proposal.
•They are used to ensure that all prospective sellers have a
clear, common understanding of the procurement.
•Responses to questions may be incorporated into the
procurement documents as amendments.
14
11/29/2014
EVALUATION CRITERIA
• Criteria developed and used to rate or score proposals; may be objective
or subjective.
• Often included as part of the procurement documents.
• If price is not the overriding factor then the buyer must identify and
document the criteria; for example:
•An understanding of need - As demonstrated by the seller’s proposal.
•Overall or life cycle cost - Does the selected seller produce the lowest total
cost (purchase cost plus operating cost)?
•Technical capability - Does the seller have, or can the seller be reasonably
expected to acquire, the technical skills and knowledge needed ?
•Management approach - Does the seller have an approach that will ensure a
successful project ?
•Financial - Does the seller have adequate financial resources to do the job ?
15
11/29/2014
CONTROL PROCUREMENTS
• The process of managing procurement relationships,
monitoring contract performance, and making changes and
corrections as needed.
CONTROL PROCUREMENTS
INPUTS
1. Project management plan TOOLS & TECHNIQUES
2. Procurement documents
3. Agreements 1. Contract change control system
4. Approved Change requests 2. Procurement performance reviews
5. Work performance reports 3. Inspections and audits
6. Work performance data 4. Performance reporting
5. Payment systems
6. Claims administration
7. Records management system
OUTPUTS
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets
updates
16
11/29/2014
CLOSE PROCUREMENTS
• The process of completing each procurement and finalizing
open claims, updating records to reflect final results and
archiving such information for future use.
CLOSE PROCUREMENTS
INPUTS
1. Procurement audits
2. Procurement negotiations
3. Records management system
OUTPUTS
1. Closed procurements
2. Organizational process assets
updates
17
11/29/2014
QUESTIONS
18
11/29/2014
2 ) The seller has filed a delay claim against the buyer, asking
for a change order, saying that the buyer took longer than
allowed in the contract to review and approve a deliverable.
Who has the authority to sign the change?
A ) Project manager.
B ) Contracting officer.
C ) Senior manager.
D ) Team and project manager.
19
11/29/2014
20
11/29/2014
21
11/29/2014
22
11/29/2014
23