MANPOWER SCHEDULE
(DIRECT)
ACTIVITY PRE-PLANNING ACT DURATION LABOR NO. OF LABOR EQUIPMENTS
(WBS CODE) (PROFESSIONAL) LABOR COST
300/8HRS.

PHASE 1 COMMENCEMENT OF 1 DAY 4 HEDGE TRIMMER/


1.1 CONSTRUCTION MOWER
DEMOLITION/CLEANNIN GAS UP
G
1.2 EXCAVATION 1 DAY 3 TRACKED
LABOR EXCAVATOR
(EXCAVATOR) (CLAMPSHELL)
LEVELING
INSTRUMENT
MASON 2SC
. 6 LONNG NAILS
1.3 LAYOUT CEMENT 1 - / 2DAY/S CARPENTER 1AL
0E HAMMER
M
CONCRETE LABOR :0 RIGHT ANGEL
STEEL TAPE THIN
COTTON THREAD
BRICKS
CEMENT
SCREENSAND
LEVELING
INSTRUMENT
1.4 LAY THE FOOTING 1 - / 2 DAY/S MASON 6 LONNG NAILS
LABOR HAMMER

2|Page
RIGHT ANGEL
STEEL TAPE THIN
COTTON THREAD
BRICKS
CEMENT
SCREENSAND
REBARS
1.5 LAY ANTI TERMITE 1 DAY LABOR 4 CHEMICALS
TREATMET CHLORPYRIFOS 20
EC.
LINDANE 20 EC.
1- /2 DAY/S LEVELING
INSTRUMENT
1.6 BRICKWORK UP MASON 6 LONNG NAILS
LABOR HAMMER
RIGHT ANGEL
STEEL TAPE THIN
COTTON THREAD
BRICKS
CEMENT
SCREENSAND
BRICKS
CEMENT
1.7 DAMP PROOF COURSE 1 – 2 DAYS MASON 6 SCREENSAND
LABOR LEVELING
INSTRUMENT
RIGHT ANGEL
STEEL TAPE
BRICKS
CEMENT

3|Page
1.8 REFILLING OF EARTH 2 DAYS MASON 6 SCREENSAND
(AROUND THE WALLS) LABOR LEVELING
INSTRUMENT
RIGHT ANGEL
STEEL TAPE
TOTAL DAYS OF WORK : 1 – 2 WEEKS

SCHEDULE OF WORKS – FOUNDATION WORKS


        WEEK 1 WEEK 2        
  ACTIVITY DURATION ASSIGNED 1 2 3 4 5 6 7 1 2 3 4 5 6 7        

1.1 Demolition/ Cleaning 1 Day Mason Start                              

      Labor        

      Carpenter          
1 Day Mason
1.2 Excavation                                    

      Labor            
1 and 1/2 Days Labor
1.3 Layout Cement Concrete                                    
2 Days Mason
1.4 Lay the footing                                    

      Labor              
1 and 1/2 Day Labor
1.5 Lay Anti Termite Treatment                                    
2 Days Mason
1.6 Brickwork Up                                    

      Labor            
2 Days Mason
1.7 Damp Proof Course                                    

4|Page
      Labor              
2 Days Mason
1.8 Refilling of Earth (Around the Walls)                                    

      Labor              

                                  CLOSE  
2 weeks
TOTAL DAYS                                      