CENTRAL ELECTRICITY AUTHORITY

G O & D WING
OPERATION PERFORMANCE MONITORING DIVISION

THERMAL/NUCLEAR UNITS WENT OUT OF GRID ON: 18-07-2020

Date of Maintanance
Unit
Station Capacity (MW)
No
DD/MM/YYYY HH:24MM

1 2 3 4

GOINDWAL SAHIB TPP 1 270.00 18/07/2020 11:14

SURATGARH TPS 1 250.00 18/07/2020 14:02

BARADARHA TPS 1 600.00 18/07/2020 09:08

VINDHYACHAL STPS 11 500.00 18/07/2020 04:49


CHANDRAPUR(MAHARASHTRA)
3 210.00 18/07/2020 12:15
STPS
VIZAG TPP 1 520.00 18/07/2020 14:15
VIZAG TPP 2 520.00 18/07/2020 23:59

YERMARUS TPP 2 800.00 18/07/2020 11:56


NORTH CHENNAI TPS 3 210.00 18/07/2020 10:35

KAHALGAON TPS 6 500.00 18/07/2020 09:58


BONGAIGAON TPP 2 250.00 18/07/2020 18:07
LAKWA REPLACEMENT POWER
2 9.96 18/07/2020 10:54
PROJECT
LAKWA REPLACEMENT POWER
3 9.96 18/07/2020 19:43
PROJECT
LAKWA REPLACEMENT POWER
3 18/07/2020 08:50
PROJECT
LAKWA REPLACEMENT POWER
5 9.96 18/07/2020 10:45
PROJECT
LAKWA REPLACEMENT POWER
6 9.96 18/07/2020 00:00
PROJECT
Total 4669.86
https://npp.gov.in 22/07/2020 17:26:57
Y AUTHORITY
NG
ONITORING DIVISION

Sub-Report - 15

Expected/Sync Date of return


remarks
DD/MM/YYYY HH:24MM

5 6

GRID MISCELLANEOUS
ABNORMAL BOILER OPERATIONAL
PARAMETER
20/07/2020 TURBINE VIBRATIONS HIGH

WATER WALL TUBE LEAKAGE

P.A. FANS PROBLEM


RSD/LOW SCHEDULE
RSD/LOW SCHEDULE

FURNACE DRAFT ABNORMAL


FURNACE FIRE OUT /FLAME FAILURE

TURBINE VIBRATIONS HIGH


RSD/LOW SCHEDULE

Fuel Shortage

Fuel Shortage

Fuel Shortage

Fuel Shortage

FUEL SUPPLY & OTHER MISC. PROBLEMS