Professional Documents
Culture Documents
1 Scope
All Vodafone Employees, Contractors and Authorized subcontractors working for Vodafone, with
special attention for those employees executing lifting and installation work at the site and within the
drop zone.
Resources engaged in Lifting must be medically fit & trained on material lifting.
PTW process must be adhered to for any material lifting activity
Team must have at least one Supervisor and two rigger / hauler
A lifting plan must be prepared & kept ready for the lifting activity which will have all relevant controls
for the activity
Tool box talk must be conducted and all personnel involved in the lift should understand the lifting plan
to complete the lift within the expected duration
Hand signals to be used must be explained to the team members.
A drop zone must be identified and demarcated.
No lifting must be done in inclement weather conditions like rain, fog, snowy and windy.
A Pre- Lift readiness Assessment must be conducted which must include check on load limit, PPEs, tools
and equipment requirement. This must also include suitability of the anchor point for the pulley
checked
Check the integrity and fitness of the lifting aids and equipment like rope, sling, carabiners, pulley and
the strength and suitability of the anchor point
All tools tied off using appropriate tool lanyards for working at height to prevent fall of tools
Minimum freeboard must always be considered in order to lift the load to the required height
Appropriate anchoring procedures and methods should always be used when connecting rope rigging
equipment to the load and structure
Check if the load is within the Safe Working Load (SWL) of the equipment like Crane, Pulley, rope
Sharp edge protection or lifting blocks must be used to prevent the slings being pinched or damaged
Date: May 11, 2018 Page 1 of 3
Technology HSW
LIFTING WORK METHOD STATEMENT
Ensure only approved EN standard PPE available – Harness, Helmet, Gloves, Shoes, Goggles
Test and balance the load with its center of gravity. Slowly raise making sure that load is safe and stable.
If load is not balanced, lower the load and adjust. Repeat as necessary until the load is evenly balanced.
Emergency process discussed & made known to all members
Ensure a confirmation from the Rigger & Supervisor that tools are tethered/secured,
Get confirmation from the rigger that they are connected to the tower 100% of the time,
Resources have asked themselves if after all listed conditions have been satisfied they believe it is safe
to proceed.
4 Lifting Methods & Pulley System - right combination to be chosen considering the load
and the manpower available
Weight of Load Pulley System
08 kg < 20 kg 1:1
20Kg < 40Kg 2:1
40 Kg to 100 kg 3:1
4:1
4:1
5 PPEs required
Hard hat Full body harness & lanyards Gloves & Shoes Safety goggles Kernmantle rope &
Pulley
Note: This is only a site reference document and must be read along with the Vodafone policies on Work @
Height, Personal Protective Equipment & Guidelines on Material Lifting