CONCRETE POURING SCHEDULE

BLOCK BUILDING WIR Ref. # STRUCTURE ELEMENT ESTIMATED QTY TIME OF BATCH PLANT IN-CHARGE PERSON DETAILS REMARKS
(m3) CASTING
TODAY CASTING: 18-Apr- 2020

12 12.2 28297 Retaining wall from Lower Basement to Upper 200 5:00PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (22501, 22493,28301)- Ongoing
Basement at NOC

Ground to First Floor Staircase-2 (Part-2) at Fire


18 18.1 27328 9 4:40PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (27325, 27326,27327)- OK
Station BUILDING

FORECASTED CASTING ON 19-Apr- 2020

Lower Roof Floor Beam (Part 3) at Fire Station


18 18.1 28304 26 3:30PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (28303, 28302,28301, 27805)- Ongoing
BUILDING

12 12.2 22509 Columns from Lower Basement to Upper 7 4:30PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (22507, 22508,27324)- Ongoing
Basement at NOC building

Columns from Elev.+29.80 to Elev.+32.80m at


28 28.3 28406 4 8:30 AM TAYONEH Concrete Mr Atheer-31272903 Related IR"s (28407, 28409,27324)- Ongoing
Main Masjid building

42 42.1.1 GF Slab On Grade (Part 4/2) 30 9:30 AM TAYONEH Concrete Mr Atheer-31272903 Related IR"s ()- Ongoing

18 18.1 25776 Rev. 1 Blinding under SOG (Part 1) at Fire Station 18 4:00PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (25775R1,27806)- OK
BUILDING
ACTUAL CONCRETE CASTED
DATE OF CASTING: 17-March- 2020

ESTIMATED QTY TIME OF


BLOCK BUILDING WIR Ref. # STRUCTURE ELEMENT BATCH PLANT IN-CHARGE PERSON DETAILS REMARKS
(m3) CASTING

42 42.1 26500 Mezzanine Columns to Roof Floor Part 6/5 at 9 1:00PM TAYONEH Concrete Mr. Atheer-31272903 Related IR"s (26497,26498,26499)- ok
MAIN SPORTS COMPLEX

42 42.1.1 26634 Slab/Beam (Part 6) at Mezzanine Floor MAIN 63 9:00AM TAYONEH Concrete Mr. Atheer-31272903 Related IR"s (26506,26507,26508,26509)- On Going
SPORTS COMPLEX

6-nos 2nd Lift Ground Columns Grid(A/1-6) at


12 12.1 23547 Rev. 1 2:00PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (23510_1,23545_1,23546_1)- On Going
North Gate

18 18.1 26641 First Floor level Column at Fire Station 2:30PM TAYONEH Concrete Mr Ellie-66293384 Related IR"s (26639,26640)- On Going