MASTER SCHEDULE PROVISION OF ENGINEERING, FABRICATION & DELIVERY OF B11 K2400 CENTRIFUGAL COMPRESSOR ROTOR AND BUNDLE FOR

PETRONAS CARIGALI SDN BHD


ID Task Name Duration Start Finish January 2020 February 2020 March 2020 April 2020 May 2020 June 20
2 7 12 17 22 27 1 6 11 16 21 26 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10
0 PROVISION OF ENGINEERING, FABRICATION & DELIVERY OF B11 92.31 days? Thu 16/1/20 Tue 2/6/20
K2400 CENTRIFUGAL COMPRESSOR ROTOR AND BUNDLE FOR
1 PETRONAS CARIGALI SDN BHD
PO received 0 days Thu 16/1/20 Thu 16/1/20 16/1
2 Received rotor & diaphragm (uncomplete) 1 day Fri 24/1/20 Mon 27/1/20
3 Perform rotor inspection + coffin 12 days Fri 24/1/20 Tue 11/2/20
4 Repacking & prepare documentation for delivery to NJCM 12 days Fri 24/1/20 Tue 11/2/20
5 Received raw material for impeller 3rd stg. (Inconel 718) 44 days Thu 16/1/20 Fri 20/3/20
6 Shipment rotor to NJCM 6 days Tue 11/2/20 Thu 20/2/20
7 Perform dismantle, cleaning & inspection. 5 days Thu 20/2/20 Thu 27/2/20
8 Prepare as found report & submission to SKG 5 days Thu 20/2/20 Thu 27/2/20
9 Generate new impeller drawing 17 days Thu 27/2/20 Tue 24/3/20
10 Manufacture new 3rd stg. Impeller 14 days Tue 24/3/20 Tue 14/4/20
11 Manufacture shaft sleeve 10 days Tue 14/4/20 Wed 29/4/20
12 Request new material 4 days Tue 14/4/20 Mon 20/4/20
13 Machining Sleeve 10 days Tue 14/4/20 Wed 29/4/20
14 BALANCING 11 days Wed 29/4/20 Thu 14/5/20
15 Perform individual low speed balance for each of the existing 4 days Wed 29/4/20 Tue 5/5/20
impeller as per ISO 1940 std.
16 Perform individual low speed balance for each of the new impeller 4 days Wed 29/4/20 Tue 5/5/20
as per ISO 1940 std.
17 Perform rotor assembly & low speed balancing 3 days Tue 5/5/20 Fri 8/5/20
18 Perform high speed balancing 4 days Fri 8/5/20 Thu 14/5/20
19 Preserve + Packing rotor 1 day Fri 15/5/20 Mon 18/5/20
20 Transport rotor back to Malaysia (CESB) 3 days Mon 18/5/20 Thu 21/5/20
21 Receive rotor from NJCM + QA/QC 4 days Fri 22/5/20 Thu 28/5/20
22 Prepare + assemble complete compressor rotor bundle 5 days Fri 22/5/20 Fri 29/5/20
23 Preserve + Packing & ready to collect. 2 days Fri 29/5/20 Tue 2/6/20
24

Task Project Summary Manual Task Start-only Deadline

Project: PROVISION OF ENGINE Split Inactive Task Duration-only Finish-only Progress


Date: Thu 23/4/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1