You are on page 1of 12

ABSTRACT OF COST

Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi, Parnoo,
Sanghoi, Mango, Navgoan, Darlaghat etc. in Tehsil Arki Distt. Solan (H.P)
(SH: Providing and Fixing Barbed Wire Fencing around WTP, Main Storage tanks & Pump House)
Sno. Description of item Amount
1 Providing & Fixing Barbed Wire Fencing with Gate At WTP & Pump House at Node 1-3 (Size 80 x 60 m) 2757656.00
2 Providing & Fixing Barbed Wire Fencing with Gate at Pump House at Node 5 & 7 (Size 10 x 9m) 801592.00
3 Providing & Fixing Barbed Wire Fencing with Gate around Main Storage tank at Node 4 (Size 20 x 18m) 769262.00
4 Providing & Fixing Barbed Wire Fencing with Gate around Main Storage tank at Node 5&10 (Size 10 x 9m 801592.00
5 Providing & Fixing Barbed Wire Fencing with Gate around Main Storage tank at Node 7 (16 x 14m) 616329.00
TOTAL 5746431.00

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
ABSTRACT OF COST
"Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi, Parnoo, Sanghoi, Mango, Navgoan, Darlaghat
etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around water treatment plant & Pump House at Node 1-3)
80 mtrs. X 60 mtrs.)
Sno. Description of item Qty Unit Rate Amount
1 16.44 cum 464.95 7645.00
Excavation in foundation and trenches etc. in all kind of soil such as pick work,jumper work, blasting in soft/hard rock
chiselling where blasting in prohibited ,soft/ hard rock saturated soil including dewatering stacking the excavated soil
with in all leads and liftrs clear from the edge of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each deposited layer by ramming and watering and then
disposing of all surplus excavated earth as directed within all leads and lifts complete in all respect and as directed by
the Engineer-in-charge.
2 Providing and laying cement concrete 1:4:8 ( 1 cement:4 sand: 8 graded stone agg. 40mm nominal size) and curing 16.44 cum 6160.70 101300.00
complete excluding cost of form work in foundation and plinth within all leads and lifts and as per direction of Engineer
in charge.

3 Steel work in single section including cutting hoisting and fixing in position and applying a priming coat of red led paint 1124.64 K.G 64.88 72969.00
in R.S. joist, channel, Angle tee for fencing posts within all leads and lifts and as per direction of Engineer in charge.

4 Supplying and fixing Gavanised steel barbed wire (IS:278-1962 Type 1) weighing 9.38kg/100mtr. minimum. Strained & 3343.60 Rmt 770.35 2575742.00
fixed to any type of standard rails straining bolts including securing with and provision of galvanised mild steel wire
stapples or steel pins etc. as directed (post and struts of steel and straining bolts shall be measured & paid seprately
within all leads and lifts and as per direction of Engineer in charge.

TOTAL 2757656.00

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
DETAIL OF MEASURMENT
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi,
Parnoo, Sanghoi, Mango, Navgoan, Darlaghat etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around water treatment plant & Pump House at Node 1-3)
80 mtrs. X 60 mtrs.) "
Sno. Description of item No. L B H/D Quntity Unit
1 Excavation in foundation and trenches etc. in
all kind of soil such as pick work,jumper
work.

At node no.--- LW = 1x2x80=160.00 mtr.


SW = 1x2x60=120.00 mtr.
Total=280.00 mtr.
No. of posts =280/2.50 mtr. Centre to centre
=112 Nos.
For struts at corners = 1x4=4 No.
Total=116.00 mtr. 116.00 0.45 0.45 0.70 16.44 Cum
TOTAL 16.44 Cum
2 Providing and laying cement concrete 1:4:8
( 1 cement:4 sand: 8 graded stone agg. 40mm
nominal size) and curing complete excluding
cost of form work in foundation and plinth.

For angle posts 116.00 0.45 0.45 0.70 16.44 Cum


TOTAL 16.44 Cum
3
Steel work in single section including cutting
hoisting and applying a priming coat of red
led paint in R.S. joist, channel, Angle tee for
fencing posts. Angle post =50x50x5mm

116x2.40x3.80 Kg/ Rmt. 1057.92 Kg.

MS Sheet 1 mm thick 5.76M2


as per the rate 7.80 Kg/M2=45.216 Kg 36.00 Kg.
Wastage 10% =4.522 Kg
Total=49.738 Kg
1 Sqm = 8.635 Kg 1x2.00x1.20 = 2.40 Sqm
2.40 sqm x 8.635 Kg 20.72 Kg.
Pully 25 mm and handle locking arrangment
L----S = 10 Kg 10.00 Kg.
bolts and rivets etc.
TOTAL 1124.64 Kg.

or 3.70 Qtls
4

Supplying and fixing Gavanised steel barbed


wire (IS:278-1962) type 1) weighing
9.38kg/100mtr. Strained & fixed to any type
of standard rails straining bolts including
securing wiyh and provision of galvanised
mild steel wire stapples on steel pins etc. as
directed (post and struts of steel and straining
bolts shall be measured & paid seprately
Horizontal wire 9 x 280 2520.00 Rmt
No. Rmt
Diagonal (2x3.05 = 7.10 mtrs.) 116.00 x 7.10 823.60 Rmt
No. Rmt
TOTAL 3343.60 Rmt

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
ABSTRACT OF COST
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi, Parnoo, Sanghoi, Mango, Navgoan, Darlaghat
etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Pump House at Node 5,7
10 mtrs. X 9 mtrs.)
Sno. Description of item Qty Unit Rate Amount
1 2.69 cum 464.95 1252.00
Excavation in foundation and trenches etc. in all kind of soil such as pick work,jumper work, blasting in soft/hard rock
chiselling where blasting in prohibited ,soft/ hard rock saturated soil including dewatering stacking the excavated soil
with in all leads and liftrs clear from the edge of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each deposited layer by ramming and watering and then
disposing of all surplus excavated earth as directed within all leads and lifts complete in all respect and as directed by
the Engineer-in-charge.
2 Providing and laying cement concrete 1:4:8 ( 1 cement:4 sand: 8 graded stone agg. 40mm nominal size) and curing 2.69 cum 6160.70 16592.00
complete excluding cost of form work in foundation and plinth within all leads and lifts and as per direction of Engineer
in charge.

3 Steel work in single section including cutting hoisting and fixing in position and applying a priming coat of red led paint 240.00 K.G 64.88 15572.00
in R.S. joist, channel, Angle tee for fencing posts within all leads and lifts and as per direction of Engineer in charge.

4 Supplying and fixing Gavanised steel barbed wire (IS:278-1962 Type 1) weighing 9.38kg/100mtr. minimum. Strained & 476.90 Rmt 770.35 367380.00
fixed to any type of standard rails straining bolts including securing with and provision of galvanised mild steel wire
stapples or steel pins etc. as directed (post and struts of steel and straining bolts shall be measured & paid seprately
within all leads and lifts and as per direction of Engineer in charge.

TOTAL 400796.00

TOTAL for 2 801592.00

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
DETAIL OF MEASURMENT
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi,
Parnoo, Sanghoi, Mango, Navgoan, Darlaghat etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Pump House at Node 5,7
10 mtrs. X 9 mtrs.) "
Sno. Description of item No. L B H/D Quntity Unit
1 Excavation in foundation and trenches etc. in
all kind of soil such as pick work,jumper
work.

At node no.--- LW = 1x2x10=20.00 mtr.


SW = 1x2x9=18.00 mtr.
Total=38.00 mtr.
No. of posts =38/2.50 mtr. Centre to centre
=15 Nos.
For struts at corners = 1x4=4 No.
Total=19.00 mtr. 19.00 0.45 0.45 0.70 2.69 Cum
TOTAL 2.69 Cum
2 Providing and laying cement concrete 1:4:8
( 1 cement:4 sand: 8 graded stone agg. 40mm
nominal size) and curing complete excluding
cost of form work in foundation and plinth.

For angle posts 19.00 0.45 0.45 0.70 2.69 Cum


TOTAL 2.69 Cum
3
Steel work in single section including cutting
hoisting and applying a priming coat of red
led paint in R.S. joist, channel, Angle tee for
fencing posts. Angle post =50x50x5mm

19x2.40x3.80 Kg/ Rmt. 173.28 Kg.

MS Sheet 1 mm thick 5.76M2


as per the rate 7.80 Kg/M2=45.216 Kg 36.00 Kg.
Wastage 10% =4.522 Kg
Total=49.738 Kg
1 Sqm = 8.635 Kg 1x2.00x1.20 = 2.40 Sqm
2.40 sqm x 8.635 Kg 20.72 Kg.
Pully 25 mm and handle locking arrangment
L----S = 10 Kg 10.00 Kg.
bolts and rivets etc.
TOTAL 240.00 Kg.

or 3.70 Qtls
4

Supplying and fixing Gavanised steel barbed


wire (IS:278-1962) type 1) weighing
9.38kg/100mtr. Strained & fixed to any type
of standard rails straining bolts including
securing wiyh and provision of galvanised
mild steel wire stapples on steel pins etc. as
directed (post and struts of steel and straining
bolts shall be measured & paid seprately
Horizontal wire 9 x 38 342.00 Rmt
No. Rmt
Diagonal (2x3.05 = 7.10 mtrs.) 19.00 x 7.10 134.90 Rmt
No. Rmt
TOTAL 476.90 Rmt

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
ABSTRACT OF COST
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi, Parnoo, Sanghoi, Mango, Navgoan, Darlaghat
etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Main storage tank at Node 4
20 mtrs. X 18 mtrs.)
Sno. Description of item Qty Unit Rate Amount
1 4.82 cum 464.95 2241.00
Excavation in foundation and trenches etc. in all kind of soil such as pick work,jumper work, blasting in soft/hard rock
chiselling where blasting in prohibited ,soft/ hard rock saturated soil including dewatering stacking the excavated soil
with in all leads and liftrs clear from the edge of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each deposited layer by ramming and watering and then
disposing of all surplus excavated earth as directed within all leads and lifts complete in all respect and as directed by
the Engineer-in-charge.
2 Providing and laying cement concrete 1:4:8 ( 1 cement:4 sand: 8 graded stone agg. 40mm nominal size) and curing 4.82 cum 6160.70 29691.00
complete excluding cost of form work in foundation and plinth within all leads and lifts and as per direction of Engineer
in charge.

3 Steel work in single section including cutting hoisting and fixing in position and applying a priming coat of red led paint 376.80 K.G 64.88 24448.00
in R.S. joist, channel, Angle tee for fencing posts within all leads and lifts and as per direction of Engineer in charge.

4 Supplying and fixing Gavanised steel barbed wire (IS:278-1962 Type 1) weighing 9.38kg/100mtr. minimum. Strained & 925.40 Rmt 770.35 712882.00
fixed to any type of standard rails straining bolts including securing with and provision of galvanised mild steel wire
stapples or steel pins etc. as directed (post and struts of steel and straining bolts shall be measured & paid seprately
within all leads and lifts and as per direction of Engineer in charge.

TOTAL 769262.00

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
DETAIL OF MEASURMENT
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi,
Parnoo, Sanghoi, Mango, Navgoan, Darlaghat etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Main storage tank at Node 4
20 mtrs. X 18 mtrs.) "
Sno. Description of item No. L B H/D Quntity Unit
1 Excavation in foundation and trenches etc. in
all kind of soil such as pick work,jumper
work.

At node no.--- LW = 1x2x20=40.00 mtr.


SW = 1x2x18=36.00 mtr.
Total=76.00 mtr.
No. of posts =76/2.50 mtr. Centre to centre
=30 Nos.
For struts at corners = 1x4=4 No.
Total=34.00 mtr. 34.00 0.45 0.45 0.70 4.82 Cum
TOTAL 4.82 Cum
2 Providing and laying cement concrete 1:4:8
( 1 cement:4 sand: 8 graded stone agg. 40mm
nominal size) and curing complete excluding
cost of form work in foundation and plinth.

For angle posts 34.00 0.45 0.45 0.70 4.82 Cum


TOTAL 4.82 Cum
3
Steel work in single section including cutting
hoisting and applying a priming coat of red
led paint in R.S. joist, channel, Angle tee for
fencing posts. Angle post =50x50x5mm

34x2.40x3.80 Kg/ Rmt. 310.08 Kg.

MS Sheet 1 mm thick 5.76M2


as per the rate 7.80 Kg/M2=45.216 Kg 36.00 Kg.
Wastage 10% =4.522 Kg
Total=49.738 Kg
1 Sqm = 8.635 Kg 1x2.00x1.20 = 2.40 Sqm
2.40 sqm x 8.635 Kg 20.72 Kg.
Pully 25 mm and handle locking arrangment
L----S = 10 Kg 10.00 Kg.
bolts and rivets etc.
TOTAL 376.80 Kg.

or 3.70 Qtls
4

Supplying and fixing Gavanised steel barbed


wire (IS:278-1962) type 1) weighing
9.38kg/100mtr. Strained & fixed to any type
of standard rails straining bolts including
securing wiyh and provision of galvanised
mild steel wire stapples on steel pins etc. as
directed (post and struts of steel and straining
bolts shall be measured & paid seprately
Horizontal wire 9 x 76 684.00 Rmt
No. Rmt
Diagonal (2x3.05 = 7.10 mtrs.) 34.00 x 7.10 241.40 Rmt
No. Rmt
TOTAL 925.40 Rmt

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
1.80 M HIGH BARBED WIRE FENCING WITH ANGLE POSTS 50 X 50 X 6 MM

NOT TO SCALE

Angle 50 X 50 X 6 mm
50 9

200 8

200 7
TWO DIAGONAL WIRE
200 6

200 5
BARBED WIRE
200 4

200 3 250

200 2

200 1
G 150 L
150 150

550 650
C.C. 1:3:6 ( 40 MM STONE AGGREGATE)

100

450 450

ASSISTANT ENGINEER EXECUTIVE ENGINEER


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
ABSTRACT OF COST
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi, Parnoo, Sanghoi, Mango, Navgoan, Darlaghat
etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Main storage tank at Node 5,10
10 mtrs. X 9 mtrs.)
Sno. Description of item Qty Unit Rate Amount
1 2.69 cum 464.95 1252.00
Excavation in foundation and trenches etc. in all kind of soil such as pick work,jumper work, blasting in soft/hard rock
chiselling where blasting in prohibited ,soft/ hard rock saturated soil including dewatering stacking the excavated soil
with in all leads and liftrs clear from the edge of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each deposited layer by ramming and watering and then
disposing of all surplus excavated earth as directed within all leads and lifts complete in all respect and as directed by
the Engineer-in-charge.
2 Providing and laying cement concrete 1:4:8 ( 1 cement:4 sand: 8 graded stone agg. 40mm nominal size) and curing 2.69 cum 6160.70 16592.00
complete excluding cost of form work in foundation and plinth within all leads and lifts and as per direction of Engineer
in charge.

3 Steel work in single section including cutting hoisting and fixing in position and applying a priming coat of red led paint 240.00 K.G 64.88 15572.00
in R.S. joist, channel, Angle tee for fencing posts within all leads and lifts and as per direction of Engineer in charge.

4 Supplying and fixing Gavanised steel barbed wire (IS:278-1962 Type 1) weighing 9.38kg/100mtr. minimum. Strained & 476.90 Rmt 770.35 367380.00
fixed to any type of standard rails straining bolts including securing with and provision of galvanised mild steel wire
stapples or steel pins etc. as directed (post and struts of steel and straining bolts shall be measured & paid seprately
within all leads and lifts and as per direction of Engineer in charge.

TOTAL 400796.00

TOTAL for 2 801592.00

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
DETAIL OF MEASURMENT
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi,
Parnoo, Sanghoi, Mango, Navgoan, Darlaghat etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Main storage tank at Node 5,10
10 mtrs. X 9 mtrs.) "
Sno. Description of item No. L B H/D Quntity Unit
1 Excavation in foundation and trenches etc. in
all kind of soil such as pick work,jumper
work.

At node no.--- LW = 1x2x10=20.00 mtr.


SW = 1x2x9=18.00 mtr.
Total=38.00 mtr.
No. of posts =38/2.50 mtr. Centre to centre
=15 Nos.
For struts at corners = 1x4=4 No.
Total=19.00 mtr. 19.00 0.45 0.45 0.70 2.69 Cum
TOTAL 2.69 Cum
2 Providing and laying cement concrete 1:4:8
( 1 cement:4 sand: 8 graded stone agg. 40mm
nominal size) and curing complete excluding
cost of form work in foundation and plinth.

For angle posts 19.00 0.45 0.45 0.70 2.69 Cum


TOTAL 2.69 Cum
3
Steel work in single section including cutting
hoisting and applying a priming coat of red
led paint in R.S. joist, channel, Angle tee for
fencing posts. Angle post =50x50x5mm

19x2.40x3.80 Kg/ Rmt. 173.28 Kg.

MS Sheet 1 mm thick 5.76M2


as per the rate 7.80 Kg/M2=45.216 Kg 36.00 Kg.
Wastage 10% =4.522 Kg
Total=49.738 Kg
1 Sqm = 8.635 Kg 1x2.00x1.20 = 2.40 Sqm
2.40 sqm x 8.635 Kg 20.72 Kg.
Pully 25 mm and handle locking arrangment
L----S = 10 Kg 10.00 Kg.
bolts and rivets etc.
TOTAL 240.00 Kg.

or 3.70 Qtls
4

Supplying and fixing Gavanised steel barbed


wire (IS:278-1962) type 1) weighing
9.38kg/100mtr. Strained & fixed to any type
of standard rails straining bolts including
securing wiyh and provision of galvanised
mild steel wire stapples on steel pins etc. as
directed (post and struts of steel and straining
bolts shall be measured & paid seprately
Horizontal wire 9 x 38 342.00 Rmt
No. Rmt
Diagonal (2x3.05 = 7.10 mtrs.) 19.00 x 7.10 134.90 Rmt
No. Rmt
TOTAL 476.90 Rmt

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
ABSTRACT OF COST
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi, Parnoo, Sanghoi, Mango, Navgoan, Darlaghat
etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Main storage tank at Node 7
16 mtrs. X 14 mtrs.)
Sno. Description of item Qty Unit Rate Amount
1 3.97 cum 464.95 1845.00
Excavation in foundation and trenches etc. in all kind of soil such as pick work,jumper work, blasting in soft/hard rock
chiselling where blasting in prohibited ,soft/ hard rock saturated soil including dewatering stacking the excavated soil
with in all leads and liftrs clear from the edge of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each deposited layer by ramming and watering and then
disposing of all surplus excavated earth as directed within all leads and lifts complete in all respect and as directed by
the Engineer-in-charge.
2 Providing and laying cement concrete 1:4:8 ( 1 cement:4 sand: 8 graded stone agg. 40mm nominal size) and curing 3.97 cum 6160.70 24452.00
complete excluding cost of form work in foundation and plinth within all leads and lifts and as per direction of Engineer
in charge.

3 Steel work in single section including cutting hoisting and fixing in position and applying a priming coat of red led paint 322.08 K.G 64.88 20897.00
in R.S. joist, channel, Angle tee for fencing posts within all leads and lifts and as per direction of Engineer in charge.

4 Supplying and fixing Gavanised steel barbed wire (IS:278-1962 Type 1) weighing 9.38kg/100mtr. minimum. Strained & 738.80 Rmt 770.35 569135.00
fixed to any type of standard rails straining bolts including securing with and provision of galvanised mild steel wire
stapples or steel pins etc. as directed (post and struts of steel and straining bolts shall be measured & paid seprately
within all leads and lifts and as per direction of Engineer in charge.

TOTAL 616329.00

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki
DETAIL OF MEASURMENT
Name of Work: Providing Drinking Water Facilities to village in GP Kashlog, Sewra Chandi,
Parnoo, Sanghoi, Mango, Navgoan, Darlaghat etc. in Tehsil Arki Distt. Solan (H.P)
(Sub Head :- P/F Bar bed wire fencing around the Main storage tank at Node 7
16 mtrs. X 14 mtrs.) "
Sno. Description of item No. L B H/D Quntity Unit
1 Excavation in foundation and trenches etc. in
all kind of soil such as pick work,jumper
work.

At node no.--- LW = 1x2x16=32.00 mtr.


SW = 1x2x14=28.00 mtr.
Total=60.00 mtr.
No. of posts =60/2.50 mtr. Centre to centre
=24 Nos.
For struts at corners = 1x4=4 No.
Total=28.00 mtr. 28.00 0.45 0.45 0.70 3.97 Cum
TOTAL 3.97 Cum
2 Providing and laying cement concrete 1:4:8
( 1 cement:4 sand: 8 graded stone agg. 40mm
nominal size) and curing complete excluding
cost of form work in foundation and plinth.

For angle posts 28.00 0.45 0.45 0.70 3.97 Cum


TOTAL 3.97 Cum
3
Steel work in single section including cutting
hoisting and applying a priming coat of red
led paint in R.S. joist, channel, Angle tee for
fencing posts. Angle post =50x50x5mm

28x2.40x3.80 Kg/ Rmt. 255.36 Kg.

MS Sheet 1 mm thick 5.76M2


as per the rate 7.80 Kg/M2=45.216 Kg 36.00 Kg.
Wastage 10% =4.522 Kg
Total=49.738 Kg
1 Sqm = 8.635 Kg 1x2.00x1.20 = 2.40 Sqm
2.40 sqm x 8.635 Kg 20.72 Kg.
Pully 25 mm and handle locking arrangment
L----S = 10 Kg 10.00 Kg.
bolts and rivets etc.
TOTAL 322.08 Kg.

or 3.70 Qtls
4

Supplying and fixing Gavanised steel barbed


wire (IS:278-1962) type 1) weighing
9.38kg/100mtr. Strained & fixed to any type
of standard rails straining bolts including
securing wiyh and provision of galvanised
mild steel wire stapples on steel pins etc. as
directed (post and struts of steel and straining
bolts shall be measured & paid seprately
Horizontal wire 9 x 60 540.00 Rmt
No. Rmt
Diagonal (2x3.05 = 7.10 mtrs.) 28.00 x 7.10 198.80 Rmt
No. Rmt
TOTAL 738.80 Rmt

Assistant Engineer Executive Engineer


Jal Shakti Vibhag Arki Jal Shakti Vibhag Arki