You are on page 1of 3

Project: J17082 Employer: ITP Ref No.

ITP-I-04

Engineer: Contractor: Date: August / 23 /2020

PO# 201902600 NEGEMCO Job No.: JV19-016 Rev: 00


Project: Aqaba Screening Project task 5 of APC storing
Inspection test Plan Medium Voltage Power Cable Installation
Inspected By 1- APC Amin Mohammad/Eyad N. Abu Adi
1-Employer APC QCP Approval
2- DAR
MV Cable Installation 2-Engineer DAR
3- Contractor NEGEMCO ( )- Approved without Comment
4- Vendor ( )- Approved With Comment- Proceed
5- Third party ( )- Not Approved-Resubmitted
Control Activity
W: Witness
H: Hold
I: Inspection
Item Activity Description Inspection/Test method Referance standard R: Review Verification Documentation
T: Testing
N/A: Not Applicable
ENG CONT TH.P VEN
1 Documentation
1_1 HSE Plan Document review HSE Policy R H N/A N/A Project requirment
1_2 Related Installation insturuction Document review Vendor Procedure R H N/A N/A Vendor Procedure
1_3 Installation Method of Statement Document review Contractor Procedure R H N/A N/A Method of Statement

1_4 Shop Drawing Document review Contractor Drawing R H N/A N/A Shop Drawing
2 Execution

Check Material Receipt inspection Project Requirement and


2_1 have been done on Delivery Visual inspection specification R+I I N/A N/A Material Receiving Report

Check Cable Drum Position before Project Requirement and


2_2 visual inspection I I N/A N/A Visual Inspection
pulling with drum. specification
Project Requirement and
2_3 Visual Inspection of the Cable visual inspection specification I I N/A N/A Visual Inspection
Inspection of cable trench
2_4 dimesnion and soft sand layer visual inspection Approved shop drawing I I N/A N/A Visual Inspection
below direct burried cable.

Check that route of power cable


2_5 ladder is complete before pulling visual inspection Approved shop drawing I I N/A N/A Visual Report

Mark (well, not same place)


temperary cabel labels 3 pcs to both
2_6 Invoiding cables mixing Cable schedule I I N/A N/A Visual Report
end. Also destination (from --> to) is
marked

Verfy enough number of cable roller


2_7 in open excavation and in cable visual inspection Specification and Drawings I I N/A N/A Visual Report
ladder for pulling.

Check that right size of cable is to be


2_8 pulled for the designated visual inspection Cable schedule I I N/A N/A Visual Report
equipment .

Check that route of cable ladder is


2_9 visual inspection Project Electrical Drawings I I N/A N/A Visual Report
complete before pulling

Cable insulation resistance test 5000 volt insulation Project Requirement and
2_9 before pulling. resistance tester. specification I I N/A N/A Visual Report

Check the cable is fixed with the Shope drawing and


2_10 visual inspection I I N/A N/A Visual Report
specified cable cleat . approved submittal.

Using approved type of cold shrink


2_11 termination on both side with the visual inspection Approved submittal I I N/A N/A Visual Report
use of specified cable gland.

Using specified stainless steel gland


Project requiement and
2_12 on stainless steel instrumet Power visual inspection I I N/A N/A Visual Report
specification
Panel.
Verify that the cable is to be
2_13 terminated in the right equipment visual inspection Cable schedule I I N/A N/A Visual Report
from both ends.

Check the cable is labeled with


specified tag and correct tag no.
2_14 from both ends. And in every 15 m visual inspection Cable schedule I I N/A N/A Visual Report
on cable ladder.

High Potential test for the cable


Project requiement and
2_15 after completion of termination kit High D.C pitential tester. specification I I R N/A Testing Report
not connected from both sides.

Check that colour coding applied Project requiement and


2_16 visual inspection I I N/A N/A Visual Report
the cores of the cable. specification

Check that warning tape, cable ties


Project requiement and
2_17 and propoer backfilling. After final visual inspection I I N/A N/A Visual Report
specification
laying of cable.

You might also like