01 02 B-07 LAY PVC AND CPVC PIPES IN
WALL

1. Did you obtain the required materials


and tools?
2. Did you obtain from the plan,the
relevant information about the pipe
line?
3. Did you make marks on the wall
accordingly?
4. Did you make a groove large enough
to insert the pipe,on the wall?
5. Did you place pipe in the groove and
hold it firmly?
6. If a fitting should be fixed,did you fix
the fittings before the pipe was
embedded in the wall?
7. Did you fill in the groove at several
place with plaster up to wall level?
8. Did you examine whether the pipe
was laid properly?
9. If some rectification are to be done
did you follow steps from 2 to 7?
10. Did you Clean the workplace?
11. Did you clean and store the tool and
equipment?
Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -……………………… Batch No: - …………………… Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Resource and Cost Assessment
(Hrs) Commencement Completion
Guidance
Date Date
B-08 LAY PVC AND CPVC ON WALLS

1. Did you obtain the required materials and


tools?
2 Did you obtain the relevant information of
the pipeline from the plan?
3 Did you set the pipeline on the wall
accordingly?
4 Did you mark the places where brackets
are to be fixed?
5 Did you drill the wall for wall plug?
6 Did you insert the wall plug?
7 Did you fix a few bracket using the nail
underneath?
8 After keeping the pipe on those brackets
did you fix it with the other nails?
9 Subsequently,did you examine whether it
was properly done according to the plan?
10 Did you clean the work place?
11 Did you clean and store the tool and
equipment.

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -……………………… Batch No: - …………………… Period: - From…………….To

Target Time Training


Month Week Module & Tasks Expected To Cover Resource and Cost Assessment
Hours (Hrs) Commencement Completion
Date Date
Guidance
B-09 FIX BENDS,ELBOW,PLAIN
SOCKETS,REDUCING SOCKETS AND
BUSHING
2. Did you decide on the place where
bends,sockets,reducing sockets etc to be
fixed according to the plan?
3. Did you decide on the required types of
pipes and quantities of
bends,socket,reducing socket and
bushing?
4. Did you obtain the necessary
materials,tool and equipment?
5. Did you measure and mark on the pipe,the
places where bends,sockets,reducing
sockets and bushings are to be fixed?
6. Did you cut the pipes according to
measured lengths and clean the pipe ends?
7. If a bend or a socket or a reducing socket
is to be fixed did you clean its ends?
8. Did you mark on the pipe the length to
which the fitting could be inserted inside
the pipe?
9. Did you apply adhesive on surface of one
end of the pipe and inside of one end of the
fittings mentioned here?
10. Did you insert the pipe into the fitting up
to the mark made on the pipe and hold it
for some time till it dried up?
11. Did you clean the surface of the fixed
joint?
12. Did you make measurements to required
length?
13. Did you out the other end to the required
length?
14. If there are other fitting,did you follow in
order the steps from 5 to 10 above and
joint pipes to the end of the fitting?
15. When fixing cpvc fitting did you insert the
cliplink and ring washer of the fitting to
the pipe?
16. To one end of the fitting did you insert the
pipe up to the cliplink
17. Did you firmly tighten the pipe and fitting
by the nails in the cliplink?
18. Did you measure and cut the length of the
pipe to be fixed on to other end of the
fitting?
19. Did you connect the pipe to the other end
of the fitting,by following the steps 14 and
15 above?
20. Did you clean and store the tools,material
and equipment?

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -……………………… Batch No: - …………………… Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Resource and Cost Assessment
(Hrs) Commencement Completion
Guidance
Date Date
. B-10 FIX PVC AND CPVC TEE JOINT
1. Did you decide on the place to fix the
tee joint?
2. Did you decide on the required types
of pvc pipes and their sizes
3. Did you obtain the required
materials,tool and equipment?
4. Did you measure the lengths where tee
joints are to be fixed?
5. Did you clean the pipe end cut
according to measured lengths?
6. Did you clean the inside of one end of
tee joint and outside of one end of the
pipe?
7. Did you mark on pipe the length to
which the tee joint could be inserted in
to the pipe?
8. did you apply adhesive uniformly on
outside the pipe and on the inside of
one end of tee joint?
9. Did you insert the pipe up to the
marked end into the tee joint and hold
it sometime till it dried up?
10. Did you clean the surface of the fixed
joint?
11. Did you measure the required length
of the pipe to be fixed on to the tee
joint?
12. Did you follow in order the steps from
4 to 10 above to fix pipes to other two
ends?
13. Did you clean and store tools,
equipment and materials?
14. Did you decide on the place to fix the
CPVC tee joint?
15. Did you get the required length to fix
the tee joint?
16. Did you obtain the required material,
tools and equipment?
17. Did get the required measurement to
fix the joint?
18. Did you clean the end of pipe cut
according to required measurements,
end of the CPVC pipe and inside
CPVC tee?
19. Did you mark on the pipe the length to
which it could be inserted to the Tee?
20. Did you first put in the cliplink and
then the ring washer in to the selected
CPVC pipe?
21. Did you insert the pipe up to the mark
inside the Tee?
22. Did you use the selected tools to
tighten this coupling?
23. Did you cut pipes to be connected to
other two ends according to
measurements?
24. Did you follow the above steps from 17
to 22 in order?
25. Did you clean and store the
tools,equipment

.
Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -……………………… Batch No: - …………………… Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Commencement Completion Resource and Cost Assessment
(Hrs) Guidance
Date Date
B-11 FIXFLANGE TYPE EXPANSION
COUPLING
1. Did you mark the place where
expansion coupling was to be
fixed?
2. Did you decide on the expansion
coupling and types of pipes?
3. Did you decide on the required
material,tool and equipment?
4. Did you clean the selected coupling
and the pipe?
5. Did you fix a rubber packing
between the end of the coupling?
6. To fix the rubber packing did you
use nails and tighten it as
required?
7. Did you place the coupling on the
pipe and tighten it?
8. Did you finish the work neatly?
9. If there were faults,did you fallow
the steps from 4 to 7 in oder?
10. Did you clean and store the tools
equipment and material?
Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -……………………… Batch No: - …………………… Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Resource and Cost Assessment
(Hrs) Commencement Completion
Guidance
Date Date
B-12 BEND PVC PIPES

1. Did you examine the place where


pvc bend is required?
2. Did you select the required type of
pipes?
3. Did you obtain the required tool
and materials?
4. Did you decide on the shape of the
bend at the required place?
5. Did you measure the pipe and cut
a little more than the required
length of the pipe?
6. Did you clean the both end of the
7. Did you firmly plug one end of the
pipe using a piece of paper made
as stopper?
8. Did you obtain a pan of sieved
sand?
9. Did you fill the pipe with sand?
10. Did you tap the pipe and get the
sand pressed?
11. Did you plug the other end of the
pipe with a piece of paper made as
a stopper?
12. Did you obtain an electric or gas
or blow lamp?
13. Did you mark on the pipe the place
where the bend is required ?
14. Did you make the heater or the
blow lamp ready for use?
15. Did you heat the marked place
while turning the pipe uniformly
on either of it?
16. Did you heat until it melted and
bent?
17. Did you remove the pipe from
heater and bend it to required
shape?
18. Did you cool it using water?
19. Did you remove the sand inside the
pipe?
20. Did you mark the required lenth
on the pipe and cut it?
21. Did you clean and store the tools
and equipment?
Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Resource and Cost Assessment
(Hrs) Commencement Completion
Guidance
Date Date
B-13 FIX FAUCET VALVE
SOCKETS,FAUCET ELBOW AND CAPS
1. Did you mark the places where faucet
valve sockets,faucet elbows and caps
had to be fixed?
2. Did you select fittings according to
plan/diameter of the pipe at that
place?
3. Did you obtain the tool and material?
4. Did you decide the length of the pipe
to which the socket is to be fixed?
5. Did you cut the required length of the
pipe and clean the end?
6. Did you clean the ends and apply
adhesive inside the fitting?
7. Did you clean and apply adhesive
outside the required pipe?
8. Did you insert the pipe into the
socket,up to the relevant
9. Did you Clean the joint?
10. Did you clean and store the
equipment?

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Resource and Cost Assessment
(Hrs) Commencement Completion
Guidance
Date Date
B-14 LAY UNDERGROUND PVC AND
CPVC PIPES
1. If the pipe is to be laid across a place
where light vehicles pass through,did
you mark the place where pipe is to be
laid
2. Did you obtain equipment,pipe and
fittings required for the place?
3. Did you cut the trench to the required
depth and length given in the plan?
4. Did you lay the pipes in the trench?
5. Did you Clean the ends of pipes?
6. Did you clean the inside of supplied
sockets?
7. Did you apply adhesive on out side of
the pipe and inside the sockets?
8. Did you insert the pipe into the socket
up to the mark and hold if firmly for
sometime?
9. Similary did you follow the steps 7 and
8 to fix pipes into the other end of the
socket?
10. Did you clean the joints and check
weather there are any defects?
11. Did you fill up and cover the trench
according to instructions avoid any
accidents?
12. Did you clean and store the equipment?
13. If the pipes to be laid across a place
where heavy vehicles pass through,did
you mark the place where pipes are to
be laid.?
14. Did you obtain the equipment ,G.I
pipes and fittings required for place?
15. Did you cut the trench to the required
depth and length according to
instructions and ground conditions?
16. Did you make arrangement to lay G.I
pipes in the trench

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01
Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

B-15 Fix pipelines to


massage showers

 Did you examine and prepare the


place
where the massage shower is to be
fixed, initially?
 Did you mark the proper place
and fix
the relevant drain pan?
 Did you obtain the handout of
massage
shower to be fixed and note down
the
necessary information / data?
 Did you obtain the required tools
and
material?
 Did you mark the appropriate
places
and fix the pipes according to the
given
instructions?
 Did you fix them, very often in
several
directions?
 Did you properly fix the pipelines
of required size so as to get a
uniform water pressure in the
pipes?
o Did you fix these pipes by push fit
method?
 After fixing all the pipes, did you
fix the relevant sprinkler nozzles
according to instructions?
 Did you check whether these
sprinkler
nozzles are in the relevant
direction
according to instruction?
 Did you measure the size of pipes
before the required water supply
was
connected to the pipeline system?
 Did you fix a pressure pump to the
system if the water pressure was
less
than the pressure recommended
by
manufacturer?
 If the pressure was adequate, did
you
remove one end of shower or the
flexible and wrap the thread seal
in the
opposite direction?
 If necessary, did you apply paint
at the
place where, water supply to
shower was to be fixed?
 Did you firmly fix the system?
 Did you check the seepage of
water after activating the water
supply and the massage shower?
 If there was no seepage of water
did you clean and store the tools?

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

B-17 Fix flexible hose


1. Did you check whether the socket
fitted
at the end of the pipe to which the
flexible hose was to be connected
had a
male or female thread?
2. Did you select the hose according
to the
required length?
3. Did you find whether there was a
washer in the flexible hose and
place one end of the hose in the
socket, turn and check whether it
moved freely?
4. If it moved freely into the part
with
thread, did you firmly fix it using
a
shifter?
5. Did you follow the steps 3 and 4
and fix
the other end of the flexible hose?
6. Did you check whether the two
ends of the flexible hose are
properly connected by allowing
water to flow through it?
7. If there was a water leakage did
you
disconnect them and again follow
steps
3 and 4?
8. Did you clean the place of work
and
clean the tools used and store at
proper
place?
Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Mont Wee Target Training


Hour Resource and Cost Assessment
h k Module & Tasks Expected To Cover Time (Hrs) Commencemen Completion
t Date Date
s Guidance
B-20 Conduct pressure test for
pipeline system
2 Did you examine whether
pipes, with the relevant
specific capacity of water are
used?
3 Did you find the diameter of
pipes?
4 Did you examine whether the
main
water pipe, had connecting
lines?
5 According to connectors, did
you find manner in which
these connections were
completed?
6 Did you obtain the necessary
fittings and tools accordingly?
7 Did you close the valves of the
main
water pipe?
8 Did you close the other
connecting
pipes?
9 Did you open-up the
prescribed water capacity to
the last water connection?
10 Did you fix the pressure
fittings to the system?
11 Did you adjust the pressure
values to the required level
and note them?
12 Did you maintain that value
for the
relevant time?
13 Did you obtain the pressure
value
according to the prescribed
time?
14 According to that value did
you decide whether there was /
was no leakage of water from
the system?
15 Did you conduct in the same
way the pressure test for the
sub-systems which are
connected to the main system?
16 Did you remove and clean the
fittings relevant to the
pressure test?
17 Did you clean and store the
tools and equipment?

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01
INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA
Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Mont Wee Target
Hour Module & Tasks Expected To Cover Resource and Cost Assessment
h k Time (Hrs) Commencemen Completion
s Guidance
t Date Date

Doc.No:-CON/TPD/FM/02
lr®udka; bxPSfkarewNHdiwdh;kh - fudrgqj Issue No:-01

INDUSTRIAL ENGINEERING TRAINING INSTITUTE - MORATUWA Issue Date:-2019.02.01

Scheme of training
Course: -Plumber Batch No: - PL/20/01 Period: - From…………….To

Training
Target Time
Month Week Hours Module & Tasks Expected To Cover Resource and Cost Assessment
(Hrs) Commencement Completion
Guidance
Date Date

You might also like