Professional Documents
Culture Documents
Abstract
This section provides guidance in the design and installation of typical piping
systems. It is intended for all users of this manual.
How to properly size piping systems is discussed, and good layout practices are
illustrated. Methods of analyzing piping stresses and providing pipe stops and
supports are reviewed. Design and support of small diameter piping are discussed.
Considerations for design of buried piping are also given.
Contents Page
Liquids 25 to 30 psi
Gases 10 to 15 psi
150-psig steam 4 or 5 psi
Low pressure steam 1 or 2 psi
Under special conditions and for short lines, higher pressure drops than the recom-
mended limits given can be tolerated. An example of this would be a very short pipe
fixed between two vessels.
It is the responsibility of the engineer to assure that his project economic conditions
do not alter the line size selected. However, it should be noted that wide variations
in costs result in very little change to the economic diameter. This is because the
economic diameter is inversely proportional to the 1/6th power of the ratio rF/KS.
For example, doubling the installed cost of piping (such as using stainless steel
piping) results in only an 11% decrease in economic diameter. This is generally not
enough of a change to alter the nominal pipe size selected. Therefore, unless
unusual project economics exist, it should not be necessary to correct the
economic velocity. If those conditions do occur, Figures 300-1 and 300-2 have been
provided as a quick method to correct the suggested economic velocity provided
above (10-12 fps for on-plot lines) using actual project cost data. Otherwise, a more
rigorous calculation may be performed using the following method.
3
FD – 6 KSQ f
C = -------- + 7.85 × 10 -----------------
r 5
D
(Eq. 300-1)
where:
F = (1 + X) L
Yk
K = ------- + 8760 ct
r
(Eq. 300-2)
C = Amortization of investment cost and annual operating cost
c = Power costs converted to dollars per hydraulic horsepower
D = Internal pipe diameter, in.
EDMI = Engineering Department Materials Index
Current EDMI
= 255 ------------------------------------- for centrifugal pumps
720
Current EDMI
= 495 ------------------------------------- for compressors
720
(Eq. 300-3)
L = Group II costs of installed piping, dollars per diameter inch per
foot of pipe (Group II costs are material costs plus direct field
expenses)
Q = Flow rate, gpm
r = Payout period (before taxes), years
S = Specific gravity (water at 60°F = 1.0)
T = Temperature, °F
t = Load factor,%/100 of the year the machinery will operate
X = Group 1B costs as a fraction (%/100) of Group II costs (Group 1B
costs are indirect field expenses)
Y = Multiplier applied to machinery purchase cost to account for
installation of complete unit (includes foundation, piping mani-
fold, auxiliary piping, power distribution, Group II and Group 1B
costs)
changes or corrections. The added advantage of lower operating costs may also
suggest selecting the larger size pipe. On the other hand, this is an opportunity to
reduce investment costs. Engineering judgement should be used in selecting
nominal pipe size. Some problems to consider are:
• Does going to a smaller line size result in pressure drops in excess of those
allowed above?
• Does going to a smaller size pipe result in an erosion problem for fluids such as
DEA? Consult a materials engineer if there is concern.
• Does added pressure drop in the system caused by going to a smaller size pipe
result in increasing the rating of the piping system (i.e., from ANSI Class 150
to Class 300) or increase the design pressure of columns, vessels, and heat
exchangers in the system?
• If the line is steam traced, does going to a smaller line result in fewer tracers?
• Is there an excessive surge pressure problem caused by quick closing valves
shutting off against too high a velocity? See Section 600 and the Fluid Flow
Manual.
• Special consideration should be given to gas velocity. High gas velocities
cause noise problems, so velocity should generally be limited to about
100 (V).5 ft/sec, where V is the specific volume in ft3/lbm. However, for most
conditions, this limit will not be reached.
• It should be noted that, for low flow rates (gpm) the economic line sizing calcu-
lations will indicate undersized lines. That is, the diameters suggested result in
pressure drops which are higher than the suggested limit of 30 psi per 1000 ft
for liquids and 15 psi per 1000 ft for gases. As a result, for low flow rates, most
process lines should be sized to meet the highest allowable pressure drop. In
any circumstance, the pressure drop should always be checked in the Fluid
Flow Manual to see that it is under the allowable limit.
The importance of accurate definition of these data will depend upon the effect of
variations in them on the capacity of the system. High accuracy is usually important
only for pump suction with boiling liquids, or high static pressures or elevations
compared with system friction losses.
valves still gives total line loss less than is available. For more information on
economic valve sizing, see Section 316.
Frequently, where gravity is the source of energy, lines larger than normally
economic may be required. In some instances, particularly where lines are long, it
may be most economical to install a pump and then employ the smaller piping this
makes possible. Where pumps and compressors are the energy source, economic
line sizing, followed by pressure drop calculations to assure that proper pressure is
supplied by the machine, is required.
Liquid Traps
Liquid traps, pockets, and dead ends should be avoided in all piping, particularly
lines conveying water, caustic acid, materials which may congeal or freeze, fluids
which may form a corrosive condensate, and fluids containing solids which may
settle out. Where low spots and dead ends cannot be avoided, install a drain valve
for system cleanup.
To “knockout” liquids in a vapor line, one option is to create a “wide spot in the
line.” A knockout (K-O) pot or slug-catcher may be used for this purpose. (A
knockout pot usually refers to a vessel in a processing facility; a slug-catcher
usually refers to a knockout pot in a pipeline or production gathering system.)
Water Hammer
When a valve is suddenly closed against a flow, a very heavy knocking sound may
be heard as the entire pipe vibrates. The inertia of the flowing fluid increases the
pressure at the valve (surge pressure) and the pressure wave propagates along the
pipe, sometimes with enough force to fracture the pipe. This phenomenon is called
water hammer, although any fluid may cause this effect. Refer to the Fluid Flow
Manual, Section 800 for more information about how to calculate surge pressure.
Water hammer may be prevented by using a slow-action control valve. Where a
quick-closing valve is necessary, many of the problems associated with water
hammer may be circumvented by the use of a surge drum. A surge drum upstream
of the control valve will slow down the acceleration and deceleration of the fluid in
a piping system subject to constant sudden opening and closing of a control valve.
Pump Suction
Always check NPSH available at the pump unless it is obviously adequate (short
lines, large submergence with liquids sub-cooled more than 100°F below their
boiling points). Always check NPSH at least 10% above maximum flow. Required
NPSH increases and available NPSH decreases, both varying about as the square of
the flow rate. An inadequate suction line can very effectively choke the capacity
of an entire plant. Refer to Section 200 of the Pump Manual.
When NPSH is not governing, pump suction lines should be the same size as for the
discharge line. When NPSH is governing, suction lines will usually be one size
larger, perhaps two. This is particularly true of liquids being pump at or near their
boiling point such as:
• Column bottoms, reboiler, and reflux
• LPG or other light products stored at their bubble point
• Boiler feedwater from deaerator or steam condensate from a condenser or
flash drum
Vapor Pressure
Within any line designed for liquid flow, the pressure should not be permitted to fall
to the bubble (boiling) point at any locations. Generally, larger fittings or lines are
required. Examples of where this may occur are:
• Column side draws. Loss in entrance (nozzle) and elbow may exceed liquid
head in draw-off pan. It may be necessary to increase nozzle and elbow one
size and then reduce to line size.
• Meter runs—through upstream fittings and below orifice
• A throttling valve—outlet
• Syphons—any point upstream
• Reciprocating pumps with long suction lines—pulsating pressure may fall
below bubble point
• Pump suction (NPSH)—(see foregoing discussion)
Hydraulic Surge
Line sizes for liquids are sometimes influenced by hydraulic surges which occur
when the flow is rapidly decelerated, such as in loading lines to trucks and
airplanes. The magnitude of such pressure surges is normally inversely proportional
to the flow area, so that they can be substantially reduced by use of larger lines. See
Section 800 of the Fluid Flow Manual for methods to calculate surge pressure.
Minimum Velocities
Velocity may have to be kept above a certain minimum to keep solids in suspen-
sion, keep the line clean, or to minimize temperature drop in a hot line or tempera-
ture rise in a cold line, etc.
Pressure Letdown
Substantial pressure reduction often occurs within a process plant, on products
leaving the plant to store, on boiler blowdown, and on condensate letdown to flash
drums. As with branched lines mentioned above, they need to be only large enough
for maximum capacity and to provide for control. But there are some other things to
watch out for:
Flashing. When not on the discharge of a pump, the liquid may be at or near its
boiling point and start vaporizing upstream, downstream, or within the control
valves. In high pressure systems, it is usually best to avoid flashing in upstream
piping. The control valve would then be sized for saturated liquid inlet and down-
stream piping sized for flashing flow.
Cavitation Through Control Valves. A control valve produces a pressure drop by
reducing the area between the seat and the plug (disk or ball in rotary valves).
Process fluid accelerates through the reduced opening. As the fluid accelerates,
pressure in the area of acceleration drops, then recovers partially as the fluid enters
the valve/piping cavity and decelerates (Bernoulli’s equation).
If the pressure in the area of acceleration drops below the vapor pressure of the
process fluid, the process fluid will flash and form vapor bubbles. If the pressure
recovers above the vapor pressure of the fluid, the vapor bubbles will collapse
(implode) and go back into solution. The implosion of the bubbles generates so
much energy that metal is physically washed away from the valve body and the
downstream piping. Cavitation is accompanied by noise that can be described as “a
cement truck with its rotating drum full of gravel,” only louder. Severe cavitation
can generate noise in excess of 110 dBA.
Cavitation can be treated by selecting a valve with a lower pressure recovery coeffi-
cient, e.g., a valve where the process fluid is impinged upon itself from opposite
sides of a cage (anti-cavitation cage trim) or by taking the pressure drop in several
stages. Refer to the Instrumentation and Control Manual, Section 970 “Control
Valve Problems” for additional information.
Erosion. Very high velocities (above 100 to 200 ft/sec) in flashing liquid lines can
result in erosion of piping if the liquid bombardment destroys or prevents protective
coating of corrosion products. As this is dependent on pipe material and the nature
of corrosion, consultation with the materials engineer is desirable for such cases.
For flashing condensate in carbon steel lines, a limiting momentum has been
suggested to minimize erosion at elbows, tees, etc. This is expressed as a maximum
reaction force on the fitting (V2/2gV) of 300 lb/ft2 of pipe cross-section area.
Erosion can be minimized by using long sweep (5-diameter) bends, or more erosion
resistant material. t generally is not a problem except with pure compounds or
narrow boiling point mixtures.
Vortices
A vortex is a whirling liquid moving in concentric circles around a vacuum or
cavity in the center of the circle. Vortices occur most frequently on bottom outlets of
vessels and columns and can inhibit flow.
A vortex breaker is usually nothing more than a small plate welded above an outlet
which disrupts the circular pattern of a forming vortex. A vortex breaker per Stan-
dard Drawing GE-C99913 (see the Pressure Vessel Manual) should be provided on
the bottom outlet nozzle from each vessel where two phases may be present and/or
which provides flow to a pump suction.
Gravity Flow
When there is no pressure difference other than level to cause flow, check the line
elevation and pressure gradient at design flow to be sure the upstream level is
adequate. The line can usually be made smaller by first dropping through a vertical
leg followed by a horizontal line running full, rather than by providing a nearly hori-
zontal run flowing only partly full.
Meter Runs
Occasionally meter runs must be larger than economic lines to provide proper flow
element to line diameter ratio. They should be considered when sizing lines in
consultation with the instrument engineer.
Headers
When headers are used to distribute flow to a number of similar parallel units, such
as heat exchangers, it will usually be cheaper to make the header pressure drop low
to avoid the need for individual control on each of the parallel paths. The header
pressure drop should be consistent with the tolerable variation in flow.
where:
D = Inside diameter, in.
q = Duty, MMBtu/hr
Flashing Water
As may be expected, flashing water lines (such as condensate return lines) have
capacities far less than a water line that is not flashing. Calculations have shown that
the capacity of a flashing water line with line pressures up to 1000 psig at the inlet
and atmospheric pressure at the outlet is about 35% of the capacity of the line if it
was not flashing.
See Section 350 of the Utilities Manual for further discussion of flashing water line
sizing. In addition, the program PIPEFLOW-2 can perform flashing calculations.
P cr 1⁄2 G P1 ⋅ V1 1 ⁄ 2
------- = ------------------------ ⋅ ------ ⋅ -----------------
2
P1 k ⋅ ( k + 1 ) P1 g
(Eq. 300-4)
P cr G P1 ⋅ V1 1 ⁄ 2
------- = ------ ⋅ -----------------
P1 P1 g
(Eq. 300-5)
where:
G = mass flow, lb/sec-ft2
Pcr = critical pipe outlet pressure, lb/ft2
P1 = inlet pressure, lb/ft2
P2 = outlet pressure, lb/ft2
V1 = specific volume of gas at inlet, ft3/lb
f = friction factor
g = 32.2
k = ratio of specific heats for gas
L = pipe length, ft
D = inside pipe diameter, ft
The specific heat ratio, k, is 1.4 for air and diatomic gases such as oxygen, nitrogen
and hydrogen and between 1.0 and 1.4 for more complex gases. Whether it is 1.0 or
1.4 generally causes only minor differences in the pressure drop calculation.
Globe and angle valves smaller than line size are generally not economical because
of the large pressure loss through these valves.
Reduced port plug cocks have a pressure loss equivalent to several velocity heads so
it is seldom economical to make such valves smaller than the line. Also, for higher
pressure ratings, plug valves cost less than gate valves so that possible investment
savings are not as great. The economy of reduced size plug cocks of the full port
type can be investigated in the same manner as for gate and ball valves, except the
loss in the valve may be somewhat less than in a gate valve, say 0.05 velocity heads.
It is generally not economical to provide a reduced size valve if a tee proceeding or
following the valve must also be reduced size. Added pressure drop in the reduced
size side-outlet tee will economically outweigh the cost savings of the reduced size
valve. Where a reduced size valve discharges into the side connection of a tee, the
tee should be full line size with two or three diameters of pipe between the reducer
and the tee. On the upstream side of a valve, no straight pipe is needed between the
tee and reducer.
The selection of pipe and valve sizes for steam flow is usually not based on
economics. The pressure drop in steam headers must be low so that steam can be
delivered throughout a process plant at its rated pressure. As a rule of thumb, pres-
sure drop in steam lines is usually limited to 4 or 5 psi per 1000 feet for 150 psig
steam and 1 or 2 psi per 1000 feet for 40 psig steam.
Method of Analysis
As mentioned earlier, the determination of the economic valve size is fundamen-
tally a matter of balancing the investment savings for the smaller valve against the
increased cost of power required to overcome the pressure drop through the smaller
valve. The incremental investment cost for pump and driver is considered insignifi-
cant since the increased pressure drop across the smaller valve will rarely result in a
larger pump case. The added investment cost for electrical facilities is considered
insignificant. To find the minimum cost, the derivative of the Total Annual Valve
Cost (Equation 300-6) is taken and set equal to zero.
Cost v 0.7457
= -------------- + ---------------- P Loss [ b + 8760 c t ]
r eff.
(Eq. 300-7)
where:
r = Payout period, yr
Costv = Installed cost of valve, flanges, and reducers (if any), $
b = Power demand charge, $/kw-yr
Note In some cases the demand charge is included with
the rate charge. In these situations, “b” is not needed.
For Liquids:
2
0.0011SQ
∆P = --------------------------- ( K v + K e )
4
d
–7 3
Q∆P 6.4 ⋅ 10 SQ
P Loss = ------------ = ---------------------------------- ( K v + K e )
1715 4
d
(Eq. 300-8)
For Gases:
2
∆P = ------------ ( K v + K e ) --- ---------------------
2720 1 M
4
ρ 100, 000
d
M∆P
P Loss = ------------------
13750ρ
3
= --------------- ( K v + K e ) ----- ---------------------
19782 1 M
2
ρ 100, 000
4
d
(Eq. 300-9)
where:
∆P = Pressure drop through valve, psi
V1 – V2 2
h = --------------------
2g
(Eq. 300-10)
where:
h = head loss, ft
V1 = initial velocity, ft/sec
V2 = final velocity, ft/sec
g = acceleration of gravity
The sudden enlargement is equivalent to an included taper angle of 180 degrees and
as this angle is decreased, the head loss first increases by about 20%, then decreases
to the Borda formula value for an included angle of 40 degrees and reaches a
minimum loss for an included angle of about 7 degrees. This minimum loss is about
13% of the Borda formula loss. For most installations, however, a taper with an
included angle of 7 degrees either consumes too much space or is too costly. There-
fore, some valves are installed with outlet tapers having 12-degree included angles,
but most are installed with standard reducer fittings with very large included angles.
The velocity head loss coefficient for standard enlarger fittings is charted in the
Fluid Flow Manual. An approximation for the curve is:
d d
K E = 1.7 – 2 ---- , for ---- < 0.8
D D
In some installations there is no distinction between on-plot and off-plot; all facili-
ties are grouped together. Examples include producing gathering stations, water
injection plants, and offshore producing platforms where area separation is
impossible.
Pipe Routing
Within a given operating area, on-plot or off-plot, the simplest piping arrangement
is usually achieved by placing equipment in sequential positions as determined by
process or system flow requirements. Generally, the equipment is placed in rows on
one or both sides of a main pipeway. Some equipment may be elevated for process
reasons.
Elevated pipeways are preferred if space is at a premium. Grade level pipe prevents
ready access to equipment. See Figure 300-5 for a typical on-plot process layout.
Sequential positioning of equipment is not always possible, especially with large or
complex plants, or where more than one facility shares the same site. For example,
the following factors can upset the orderly sequence of equipment layout, espe-
cially if space is limited:
lines, the most expensive piping (alloy and/or large diameter) is routed on a prelimi-
nary plot plan. This keeps these runs short and economical.
The remaining pipe is then routed between equipment, using the pipeway. The
pipeway area with the greatest density of pipe is identified in this fashion. This is
called the pinch point and, with the addition of space for future lines, it dictates the
width of the pipeway. See Section 324, Pipeways.
If space is at a premium, it is almost always possible to reduce the pinch point and
pipeway width by relocating certain equipment and adding length to some piping.
Once a layout is developed, the equipment piping connections, if not already estab-
lished, can be properly oriented and sized.
turns are only acceptable in situations where there are very few lines and little
possibility of future interference. See Figure 300-6.
7. Lateral connections should be made from the top of steam, vapor, and air lines
unless condensate drainage is desired. Connections for liquid lines are typi-
cally on the bottom, but each case must be evaluated.
8. Install vents and drains. Piping should be designed with a minimum of high
points that will trap gases and a minimum of pockets that will trap liquids.
Where high and low points do exist, the system is usually provided with NPS ¾
(minimum) vent and drain connections. Typical applications and installations
for operating, maintenance, and hydrostatic testing will be discussed presently.
See also Standard Drawings GD-L31335 and GD-L1057.
9. Do not install dead legs in piping unless it is planned to extend the lines in the
future. If support is needed add a dummy pipe extension to the nearest support.
Dead legs can accumulate solids and open-ended dummy legs can trap water.
Both are susceptible to internal corrosion. See Figure 300-7.
10. Minimize buried piping. Piping should be routed aboveground on supports.
Burial may be necessary at road crossings, for protection from freezing or solar
heating, and for fire protection. Buried lines may be more expensive, subject to
corrosion, difficult to detect leaks in, and prone to future maintenance prob-
lems. See Section 350.
Operability
Operating personnel must be allowed to perform their daily tasks efficiently. There-
fore, the most commonly used valves and instruments should be easily accessible,
and sufficient space must exist between piped equipment so that personnel can pass
quickly and freely through the plant. The following guidelines on clearances and
accessibility are expanded and illustrated in the Safety in Designs Manual.
Valving. Valves that must be operated several times a day or shift should be acces-
sible from grade. When this is not practical, access must be provided through the
use of stiles, ladders and platforms, valve extension handles, or chainwheels. On the
other hand, access to little-used drain valves from a kneeling position or vent valves
from a ladder is acceptable.
Standard Drawing GB-L99961 illustrates the recommended options for mounting
valves in almost all situations. Standard Drawing GB-L13963 provides details for
fabrication of extension handles for rising stem valves. Valves should not be
installed with the stem below horizontal because the bonnet accumulates debris and
water, leading to freezing and corrosion.
Valve handwheel extensions and chainwheels are used only when no reasonable
alternative exists. The mechanisms require maintenance and are subject to corro-
sion, and such valves are difficult to repack. Chainwheels are a nuisance, may not
operate in an emergency, and can be a hazard if the chain is left off its tie-back and
hangs in an accessway. NPS 2 valves are the smallest that should be considered for
chainwheels.
Clearances and Accessibility. For access by operators and ease of maintenance,
clear spaces of at least 30 to 36 inches must be provided around all equipment,
including attached piping and neighboring facilities, and on platforms and stiles. If
available, a clearance of four or five feet is not excessive. Pipe and equipment insu-
lation thickness must also be considered when laying out the facility. Valves should
be given special care. The handwheel must be accessible (See the Safety in Designs
Manual) but the stem should not extend into accessways. Early planning drawings
should provide for 4-foot clearances until final layout drawings show that spacing
can be decreased.
Major access aisles should be reasonably straight and free of random impediments
such as pipe stanchions, valve handles, ladders, diagonal bracing, instruments, elec-
trical boxes, chains, etc. Some aisles are used frequently for personnel and emer-
gency access, and four-foot to five-foot widths are not unreasonable.
Proximity. Equipment, valves, and instruments that operate in conjunction with
each other should be placed near or at least in sight of each other. Level gages
should be visible from the associated level control valve and level control valve
manifolds should be visible from the related level gage. In general, control valve
manifolds should be near their actuating instruments, and any indicating instrument
should be visible from any related manually controlled valve.
Safety
Fire Safety. This discussion covers general piping and equipment layout as they are
affected by considerations of fire safety. Detailed spacing requirements are covered
in the Fire Protection Manual. Fire safety in relation to piping component use and
material selection is covered elsewhere in this manual.
Fired equipment such as furnaces, boilers, and oil field heater-treaters should be
kept separate from lines and equipment handling flammable fluids and upwind of
relief valves venting to the atmosphere or other potential hydrocarbon sources. Fuel
and snuffing steam block valves for fired heaters should be kept at least 50 feet from
the heaters.
Pump seal failures are a common cause of fire. Pumps and other equipment
handling flammable fluids should not be installed beneath platforms, structures, or
pipeways. Overhead instrument or electrical runs should be routed around such
equipment.
Pipe trenches should be avoided. They collect debris and promote corrosion. If
unavoidable, adequate drainage must be provided.
Flanges and valves should be minimized in high fire risk areas. Remotely operated
or thermal closing valves should be considered for critical service in areas where
fire would prevent access.
Fire water piping systems in and adjacent to protected facilities should be buried to
prevent freezing and ensure operation during a fire.
General facility layout considerations are reviewed in detail in the Fire Protection
Manual and, in the case of tank fields, the Tank Manual. Fired heater piping is
discussed below and in the Fired Heater and Waste Heat Recovery Manual.
Mechanical Safety. Mechanical safety and operability go hand in hand. Valve stems
are a common problem. The safest arrangement is to install the valve in a hori-
zontal line with the handwheel at a convenient elevation and the stem vertical.
When this is not possible the piping should be arranged so the stem does not project
either diagonally or horizontally into areas needed for access, especially at head
level. Acceptable valve positioning is discussed above in “Operability” in this
section.
Clearances and valving around equipment requiring frequent maintenance such as
pumps, turbines, and compressors deserve special attention because of the amount
of time spent there by maintenance personnel, who need room for tools, spare parts,
and machinery component laydown.
For mechanical strength the smallest pipe size recommended for all services other
than instrumentation is NPS ¾. Some operating centers apply other standards and
these are discussed in Sections 700 and 800.
Wear plates are recommended at pipe supports if there is frequent line movement
due to thermal cycling or vibration, especially on thin wall piping. Insulated lines
should have shoes in accordance with Standard Drawing GB-M99653.
Relief Systems. Relief valves that discharge into closed piping systems should be
installed higher than their downstream piping. To prevent the formation of liquid
slugs and for proper drainage, the complete relief system must continuously slope
downward to the nearest liquid knockout drum. The minimum slope should be 2½
inches per 100 feet to effectively drain low spots created by the normal sag of lines
between stanchions. This slope is the same as that recommended in API 521.
At times, the main relief header may be quite large in order to handle possible relief
loads. This, combined with the slope requirement, can present special layout prob-
lems with respect to other plant piping. Lateral pipe must be routed over or under
the relief header. The relief header is often the largest line and the highest line on
plant pipeways, except for the relief valves that drain into the header. See Figure
300-8.
If more than one facility is discharging into a common relief system, each header
may be provided with a locked-open block valve and, typically, a liquid knockout
drum. In most cases the block valve is a single slide-gate valve with provision for
blinding the header on the upstream side of the valve. Horizontal mounting of the
valve is required, so that the gate cannot drop inadvertently. No other valves should
be allowed in the system unless they can be locked open. Most operating centers
have their own established practices. Variations in design practices are discussed in
Sections 700 and 800.
Sudden extreme changes of temperature and the need to handle liquid slugs during
relief have an impact on the support and anchoring of relief systems. Proper sizing
of closed pressure relief systems is covered in the Instrumentation and Control
Manual. Support and anchoring of piping are covered in Section 330 of this manual.
Relief valves that discharge directly to the atmosphere should be downwind of any
fired equipment and provided with a vertical discharge line that vents at least 10 feet
above any platform within a 25-foot radius.
Ease of Maintenance
The two most significant factors in layout and piping design impacting
maintenance are:
• Sufficient work space and access around equipment
• Sufficient valves, flanges, and blinds for proper isolation, cleanup, and testing
of plant facilities
Where economically justified, permanently piped utility tie-ins can be installed in a
facility. Standard Drawing GD-L1012 illustrates such connections for steamout,
pumpout, purge, and flushing of piping and equipment. Section 100 of the Utilities
Manual discusses the risk factors of such connections.
Space and Access. Where possible, equipment requiring periodic disassembly in
the field, such as pumps, turbines, and compressors, should have sufficient space
around it for tools, parts, and elbow room. Five or more feet is common.
Piping should not be routed over equipment unless there is a process reason. Clear
overhead access should be provided for equipment handling. If this is not possible
the piping should be flanged and removable spools provided.
Piping should not interfere with access to process equipment by maintenance equip-
ment, including cranes. For rotating equipment provide access from above and at
least one side. For heat exchanger bundle pulling, and fan and coil removal from
filters and fan coolers, leave space at one end. For filters, vessels and columns with
removable internals or packing leave space at one side.
Isolation, Cleanup, and Testing. Although their use should be minimized, flanges
are required to remove piping for access to equipment, blind for pressure tests, and
to expose piping for inspection when necessary. The requirements and methods for
these functions vary between operating centers.
Hydrostatic testing of lines and equipment can be done against closed valves, but
the surest method of achieving a valid test is with plate blanks, or blind flanges.
Standard Drawing GF-L99965 provides guidance for the blinding of refinery lines
and equipment, but applies equally well to all facilities. Section 250 discusses
blinding at flanges. Section 640 and Model Specification PIM-MS-3541 cover pres-
sure testing.
323 Manifolds
A piping manifold is an assembly of pipe, valves and fittings that gathers fluid from
one or more sources and redirects it to one or more destinations. The term manifold
is also applied to any assemblage of piping and valves grouped at one location for
ease and convenience of operation. The latter meaning covers plot limit manifolds
where all piping enters and leaves a plant, steam trap and sample draw manifolds,
and even an individual control valve manifold with its block valves and bypass.
Transfer/blending. Figure 300-9 illustrates a typical oil field manifold installation,
common in producing field-gathering stations, water injection stations, and in
process plant off-plot product blending areas.
Plot Limit. Plot limit manifolds are groupings of isolation valves and blinds in the
lines to and from a facility. They are generally located at the plot limit where, often,
the main plant overhead pipeway drops into a grade level off-plot pipeway at a
waterfall. Manifolds provide quick and safe operator access for plant isolation in
the event of a fire or plant upset, and convenience during startup and shutdown.
Small facilities may not use manifolds, instead installing block valves at the most
convenient locations in the system. See Standard Drawings GF-A1247, GF-A1248,
and GF-A1249.
Systems for which plant piping does not typically enter a plant at the plot limit
manifold are cooling water, potable water, and fire water. These are normally buried
for fire and freeze protection and do not shut down with the plant. System connec-
tions for washing, steamout, flushing, and purge are normally made at the plot limit
manifold. These are shown on Standard Drawing GD-L1012.
Manifolds that are used daily are located at grade or accessed with stairs and plat-
forms, depending on local practice or operator preference.
Control Valve. Unless specific process conditions govern, control valve manifolds
should be located at grade (preferred) or on conveniently located platforms, with
sufficient space on at least one side to service the valve and operator. Typical loca-
tions are against pipe stanchions and vessels. They should be in sight of instruments
or indicators showing the variables they control.
Proper selection and sizing of control valves are discussed in the Pump Manual and
Instrumentation and Control Manual. Control valves are typically installed with
block valves and a globe bypass valve of the same size as the control valve. This
allows continued system operation on manual control when the control valve is
removed for maintenance. Some operating centers prefer to omit the bypass valve in
noncritical service.
Properly sized control valves are usually one size smaller than the connected piping
and are specified with flanges in all sizes for ease of removal. A plugged full-port
NPS ¾ drain is usually installed between the control valve and the upstream block
valve. Allow enough space between the drain and grade for plug removal and
rodding the drain valve, which collects scale and debris. Standard Drawing
GF-A1250 illustrates typical manifold configurations.
Small Pipe
It is often convenient to group in one location small operation or maintenance func-
tions that would otherwise be scattered throughout the facility. Examples are steam
traps and sample draws. On off-plot pipeways NPS ¾ × 1 solar thermal relief valves
are often manifolded together to a common discharge. Small piping is further
discussed in Section 340 of this manual.
Steam Trap. Steam traps require periodic servicing and replacement. Routing all
condensate lines in a given area from piping and equipment to one location greatly
facilitates this. Typical steam trap manifolds are illustrated on Standard Drawing
GD-L99596 (see the Utilities Manual). The application of steam tracing is discussed
in the Utilities Manual.
Sample Draws. Process samples from overhead lines and equipment are often
brought to grade and arranged in one location. In addition to operator convenience
this allows sample drip disposal at one location and reduces the amount of cooling
water piping when hot samples are involved. Typical sample draw configurations
are shown on Standard Form PIM-EF-403 and are discussed further in Section 340.
If grouping sample draws results in a long run from a sample point, the sample draw
should be of the circulating type to ensure a true sample and eliminate the need to
discard sample liquid. This requires discharging the sample stream to a point with
lower pressure than the sample point. Tank sample draw manifolds are covered in
the Tank Manual.
Thermal Relief. Multiple thermal relief valves are sometimes manifolded together.
These are discussed in Section 340 and the Tank Manual.
324 Pipeways
This discussion is divided into on-plot and off-plot pipeways. The current trend is to
place on-plot pipeways overhead and off-plot pipeways at grade. Where real estate
is at a premium an elevated pipeway permits use of the space beneath it for access
to equipment.
On-plot Pipeways
On-plot elevated pipeways (see Standard Drawing GF-A1242) have advantages
over those at grade level:
• The area under them is cleaner and clear of other plant facilities. Grade level
pipeways collect debris, are difficult to clean, and restrict access to equipment
and other plant areas
• The pipeway structure is a support for electrical and instrument distribution
systems
• Stanchions serve as locations for electrical outlets, utility stations, firefighting
equipment, first aid stations, and piping manifolds
• The piping is more easily drained and cleaned during shutdown
Fig. 300-12 Small Pipe Supported from Larger Lines or Intermediate Supports
Edge Beams. In most plants it is considered good practice to provide overhead edge
beams connecting the stanchion columns. Edge beams provide the following bene-
fits:
• Lateral bracing
• A continuous support system for electrical conduit and instrument cable racks
(except over pumps)
• Support for lateral lines entering or leaving the pipeway
• Support for intermediate small pipe supports (already discussed under Stan-
chion Spacing)
Arrangement of Lines. The heaviest lines are placed near the columns to avoid
excessive moments in the stanchion beams. Do not place lines over the columns if a
future upper deck is a possibility. The upper practical limit for liquid-filled piping in
overhead pipeways is NPS 18. Of course, structures can be built for any line size,
but costs increase quickly.
Process and utility headers should normally be placed on the pipeway side where
most of their lateral connections will be. An exception may be steam headers to
turbines, which should be located on the opposite side of the pipeway to allow suffi-
cient flexibility in the lateral steam lines. In plants with equipment on both sides of
the pipeway, the utility headers will normally be in the center. If double-deck stan-
chions are used, the utilities are normally placed on the upper level.
Line Spacing. Standard Drawings GC-L88505 and GD-L88506 provide dimen-
sional information for line spacing. Insulated lines require more space. When laying
out piping, space can be conserved by staggering flanges.
Intersections and Corners. Generally, an elevation change is necessary at intersec-
tions and corners. This permits changes in line sequence when necessary and
accommodates adding lines in the future. Flat turns at corners are only acceptable if
the same line sequence is suitable in both pipeways, and if there is no chance that
the corner will become an intersection in the future. See Figure 300-6.
Expansion Loops. Steam, condensate and hot process lines need room to expand
and contract, and expansion loops are normally used. Expansion joints are not
recommended on-plot. See Section 240.
Loops should extend over the pipeway, as opposed to the plant area, and be
supported from the stanchions. They should be as close as possible to the center of
the pipe run.
Typically loops are nested. Most pipeways have at least one critical line in terms of
temperature, length, size, and (therefore) stress. Lines that undergo greater linear
movement than the critical line should be placed inside this line in the loop system,
and lines with less movement should be placed outside. Figure 300-13 demon-
strates this.
Anchors and Guides. Additional flanges, dummy legs, guides, or anchor points
may be required to restrain or guide the movement of hot lines or prevent trans-
mittal of expansion stresses into equipment nozzles. See Section 330.
Off-plot
Grade level off-plot pipeways are sized and developed in much the same way as on-
plot. Greater width is often provided to accommodate line movement. Piping should
be maintained at least 18 inches above grade on steel sleepers with concrete foot-
ings. Designs are discussed in the Civil and Structural Manual.
On pipeways that change direction and follow the natural terrain with elevation
changes, small piping can be often allowed to “snake” in the pipeway, reducing the
number of expansion loops.
Besides expansion loops, off-plot lines sometimes use expansion joints (slip joints).
These are not recommended, especially in hydrocarbon service; they require mainte-
nance and, being packed joints, have no fire resistance. See Section 240.
especially critical with cast iron equipment. Flexibility design methods are
explained in Section 330. Any grade level pipe supports should be adjustable and
supported on a slab that is integral with the equipment foundation to eliminate
differential movement.
Suction strainers are used primarily to catch debris especially in the suction piping
of newly commissioned or modified systems. In the case of compressors they are
especially important because of compressors’ sensitivity to even the finest scale and
grit. Although they are normally purchased, the fabrication of temporary suction
strainers is discussed in Section 240.
Centrifugal Pumps
For piping arrangement in congested areas, top suction/discharge pumps are
preferred over side and end suction/discharge. Access space around large pumps
should be greater than the three-foot minimum; use five to six feet for large multi-
stage pumps. All pumps should be piped with suction and discharge block valves
and a check valve mounted at the pump discharge.
Standard Drawings GF-L99958 and GF-L99959 demonstrate piping variations for
end suction and top suction pumps. All these illustrations demonstrate a major rule:
the general mass of pipe, valves, and manifolding is placed in a compact area in
front of the pump.
Pump piping is usually larger than the pump nozzles. Valving at the pump should be
the same size as the nozzles. If pump suction pressure is important, the suction
valve should be line size.
Pump suction piping should be as short as practicable and have a minimum of bends
to reduce turbulence. A good rule is to provide five diameters of straight pipe into
the suction nozzle, or two diameters if a reducer is also used. The pipe between the
block valve and suction nozzle should have a straight section long enough to accom-
modate a temporary suction screen. The piping should be designed so the strainer
can be installed and removed without springing the pipe or otherwise disturbing
pump alignment. Extra flanges and pipe supports may be needed.
Double-suction pumps are a special concern. Any right angle bend near the pump
suctions should be in the vertical plane to ensure balanced flow to the impeller. If
this is not practical, five or more diameters of straight pipe should be installed, or
the pump manufacturer consulted. Although not recommended, straightening vanes
can be used in restricted areas.
Reducers in horizontal suction lines are normally installed with the flat side up to
avoid trapping vapor and restricting flow. Flat-side-down reducers are acceptable
when the liquid source is elevated and grit and solids could accumulate at the low
point. If carried into the suction, these could damage the pump. This arrangement
also eliminates the need for a drain connection at the low point.
Reciprocating Pumps
Like centrifugal pumps, positive displacement pumps also require suction and
discharge block valves, but not a check valve in the discharge. The piping is usually
located at grade to allow the better support needed for pulsing flow. Figure 300-14
is a schematic sketch of typical arrangements.
All positive displacement pumps normally have a pressure relief valve between the
discharge nozzle and block valve. The relief valve should discharge to the suction
source, usually a tank or accumulator. Relief into the suction line is less desirable,
particularly if serious heat buildup can occur during circulation.
As with centrifugal pumps, temporary startup strainers are normally used and
installed in a spool between the suction valve and nozzle.
Suction and discharge pulsation dampeners are often installed to reduce vibration in
piping and equipment and to reduce the impact of acceleration head. Considerations
of net positive suction head (NPSH) are unique for reciprocating pumps. See the
Pump Manual.
On large reciprocating pumps, piping and dampener design require rigorous acous-
tical analysis. Although expensive, such analysis is usually cost-effective if it
prevents redesign or lost productivity. See the Compressor Manual and the Pump
Manual.
Steam Turbines
This discussion is limited to single and multistage noncondensing turbines. The
basic considerations in piping turbines are similar to those for centrifugal pumps,
including the use of temporary startup suction strainers. Most turbines have side
nozzles, with the option of having both suction and discharge on the same side.
Some models have vertical inlet nozzles. If the piping is simple, with no discharge
pressure relief valve or APS (automatic pump startup, with a control valve in the
inlet piping), having both nozzles on one side may be the best choice.
Inlet Piping. The inlet header and piping should be well steam-trapped to prevent
condensate from entering the machine, especially on startup. This is particularly
important for multistage turbines. Figure 300-15 illustrates good piping practice for
a turbine with APS.
Fig. 300-15 Steam Turbine with APS, Piping and Valve Arrangement—Typical for
Single-stage Turbine
Discharge Piping. The discharge valve on most turbines is normally left open when
the turbine is not operating, especially when an APS is installed. When the turbine
is not operating, condensate collects and drains continuously through a case drain
(provided on most turbines). If there is no case drain, piping downstream of the
block valve must be steam-trapped. Some installations require a pressure relief
valve to protect the turbine case exhaust when the discharge valve is closed. Figure
300-16 shows an acceptable discharge piping configuration.
When piping turbines, access must always be kept open to packing glands, lube
oil connections and the governor. Acceptable arrangements are shown in Figure
300-17.
Reciprocating Compressors
The typical reciprocating compressor is a horizontal cylinder machine and,
depending on pressures, can be single or multistage. The suction nozzle is normally
on top of the cylinder but can be on the bottom for air compressors. The discharge is
on the opposite side. The American Petroleum Institute does not allow bottom
Fig. 300-16 Steam Turbine Discharge Piping—Typical for Low Pressure Exhaust
Fig. 300-17 Steam Turbine Piping—Packing Gland, Lube Oil Connection, Governor
Accessibility
suction nozzles on process machines. Primary concerns with compressors are liquid
carryover from suction scrubbers and entry of solid contaminants into the machine.
Reciprocating compressors are generally elevated to accommodate discharge piping.
Larger units have platforms around them for access to the cylinders and suction
piping. Although suction piping may be elevated for drainage back to a liquid
knockout vessel, piping is kept close to the foundation level because of vibration
and for ease of support.
Compressors, especially multistage units, have a great deal of auxiliary piping in
addition to process piping. This and the need to disassemble cylinders necessitates
allowing more space around them than for most other equipment. Typical auxiliary
systems to be piped include N2 purge systems for startup and shutdown, cooling
water, dry air purge, lube oil circulation, and vent and drain collection.
The suction and discharge piping at each unit should have block valves. Suction and
discharge piping for each stage should be kept short, have a minimum of bends, and
drain away from the cylinder. Piping should be no smaller than the cylinder nozzle
sizes, and block valves should always be line size. Piping arrangement is further
discussed in the Compressor Manual.
Suction Piping. Suction piping, including interstage suction piping, should have
temporary suction strainers and provision for temporary pressure gages. Piping
should not be pocketed and should slope back into upstream liquid knockout
vessels. If this is not practical, the line should have a drain to remove any conden-
sate that may collect against the block valve prior to startup.
Knockout vessels (scrubbers) should be fitted with mist eliminating pads to prevent
carryover of liquid and solids, and located as close as possible to the compressor
cylinder—within a maximum of 50 feet.
For most services it is advisable to heat trace and insulate suction and interstage
suction piping between the upstream liquid knockout vessel and the cylinder to
prevent condensation. This is not usually done for producing equipment.
In addition to temporary suction strainers, special precautions are taken in initially
cleaning suction and interstage piping systems, including pulsation dampeners,
between the liquid knockout vessel and cylinders. Typically an acid pickling proce-
dure is used to remove all scale and grit. This procedure is described in Specifica-
tion PIM-MS-2411, as well as in Section 600 of this manual.
Discharge Piping. Normally, piping from the cylinder outlet to the next stage liquid
knockout vessel is mechanically cleaned only. Intercoolers are often installed to
enhance condensate removal and to lower gas temperatures for reasons involving
personnel safety and piping materials.
Pulsation. The pulsing flow, pipe vibration and cyclic movement of reciprocating
compressors can be a problem. With smaller units this is usually controlled by rigid
support and anchoring of the piping. However, for units larger than 500 HP, or with
discharge of more than 1000 psig, or for units operating in parallel it is good prac-
tice to make a formal pulsation analysis.
Chevron is a member of the Southern Gas Association (SGA) Program which, by
arrangement with the Southwest Research Institute (SWRI), provides analysis of
piping systems for attenuation of pulsations. This analysis typically results in adjust-
ments to line sizes and lengths, and the evaluation of pulsation dampeners (also
called surge bottles, volume bottles, and snubbers) in both suction and discharge
piping. The analysis can include a design review of specific pipe and vessel
supports and anchors. The Compressor Manual discusses this subject in Section 100
and in the various equipment specifications.
Pulsation dampeners are considered pressure vessels, not piping components, and
must be installed as close as possible to the cylinder. This is discussed in the
Compressor Manual. Figure 300-18 illustrates typical dampener arrangements.
Centrifugal Compressors
These units are similar to multistage centrifugal pumps in principle but operate at
speeds as high as 15,000 rpm and pressures to 5000 psig or more. The prime
concerns are the same as for reciprocating compressors: liquid and solid carryover.
In general, centrifugal compressors will tolerate more liquid in “mist” form than
reciprocating machines, but still will not tolerate free liquid. Similarly, they will
tolerate carryover of small quantities of solid particles—10 microns or smaller—
without significant erosion. However, temporary suction strainers and liquid
knockout vessels are still required.
To provide multistep compression, two or more casings are often mounted in series
on one set of shafts with the driver. Intercoolers and liquid knockout vessels are
installed, as with reciprocating compressors. As with reciprocating machines, ample
space is needed for the many auxiliary systems requiring access, and to dismantle
the machine and its piping. Figure 300-19 illustrates a schematic piping arrange-
ment for such a two-casing system.
The piping nozzles are normally on the same side of the machine and are available
face up or face down. Piping requirements are similar to those for reciprocating
machines: line size block valves are used and the piping should drain away from the
compressor. However, volume bottles with additional pipe anchors and supports are
not required.
On up-connected machines (nozzles on top) flanged breakout spools should be
installed to allow removal of the machine for maintenance. For high-pressure,
heavy-wall pipe these spools should be fitted in place and welded in the field to
ensure proper alignment. Such spools should be fitted with lifting eyes for handling.
Prefabricated spools often do not fit and can pull the casing out of alignment when
bolted up. Piping arrangement is further discussed in the Compressor Manual.
Suction Piping. Liquid knockout vessels should be installed in the suction lines,
with mist eliminating pads, and suction piping should be mechanically cleaned
and/or air blown. In extreme cases of corrosion or scaling the lines are acid pickled.
See Specification PIM-MS-2411. The suction piping between the liquid knockout
mist eliminating pad and the suction nozzle is typically heat traced and insulated to
prevent condensation.
As with centrifugal pumps, the suction lines should have at least five diameters of
straight pipe coming into the suction nozzle, with any suction strainer upstream of
this pipe. A rigorous analysis of the aerodynamics of suction piping is given in the
Elliott Company’s Centrifugal Compressor Inlet Piping—A Practical Guide, which
is included in the Compressor Manual.
Piping at the suction nozzle should contain a dropout spool for installation of the
temporary startup strainer. Extra care should be taken in the selection of strainers for
centrifugal compressors. If the perforated plate of the strainer is too light it is
susceptible to rupture from solids buildup or vibration in the high velocity stream.
The strainer should be bare perforated plate with no overlay of wire mesh screen.
Discharge Piping. Piping is installed and cleaned like piping for reciprocating
machines. Intercoolers are usually installed for condensate removal. A check valve
is added between the nozzle and block valve.
Ladder runs are limited to 30 feet between platforms. Platform and ladder design
and applications are discussed in the Civil and Structural Manual and the Safety in
Designs Manual.
Piping should not pass through platforms unless the platform is intended to provide
blinding access for the piping, in which case maintain 30 inches of clear walkway
around the piping. Instrumentation should be accessible from platforms, not from
ladders. Place control valves at grade, if possible. See the Instrumentation and
Control Manual for other layout considerations.
Heat Exchangers
Shell and Tube. The shell and tubing should be arranged with the channel section
away from the plant, and with enough clear space to allow channel and bundle
removal. If completed early enough, a review of piping study alternatives generally
results in the best location and orientation of nozzles for the fabricator. It can also
have an impact on exchanger process design that can benefit piping layout. Figure
300-21 illustrates a simplified piping design resulting from reversing the shell-side
flow of an exchanger.
Exchangers in series are often stacked and connected with matching flanges coinci-
dent with the channel section. Three units high is the practical limit. Standard
Drawing GD-L1050 illustrates the use of jack screws and blinds with stacked
exchangers.
For heat exchangers, it is common piping practice to:
• Use flanged removable spools at channel sections to allow easy removal of
channel and bundle
• Emphasize the importance of pipe flexibility analysis. Pipe-induced forces on
flanges can contribute to body flange leaks
• Install piping and insulation with sufficient room for wrench clearance at body
flanges
• In exchangers with cooling water (normally on the tube side), mount a flanged
nozzle with valve between the cooling water inlet and outlet block valves to
allow flushing the cooling water side to the atmosphere while the plant is in
operation
Awkward Configuration
Preferred Configuration
Air Coolers. Sometimes called fin-fans, air coolers should be installed to allow free
flow of air into the underside of the unit. Typically mounted on legs at grade, they
are also installed above pipeways in process areas. They should not be placed over
hydrocarbon handling equipment, such as pumps or compressors, with a potential
for leaks or fire. See Standard Drawing GF-A1242.
Air coolers are available with once-through or multipass design with flanged
headers on each end. More than one bundle can share the same fan(s), with each
bundle having its own inlet and outlet headers.
When laying out piping, the expansion and contraction of the tube bundles must be
considered. Also, if the connected piping will impose any more than minimal forces
on the nozzles, the manufacturer’s design should be reviewed for adequacy.
328 Instrumentation
This section covers general practices in use of pipe for mounting instruments.
Control valve manifolds have been discussed previously, in Section 323. Instrument
applications and standard drawings of installation methods are included in the
Instrumentation and Control Manual.
General
Piped instrument connections from lines and equipment should be installed with
root valves of the same pipe class and material as the line or equipment to which it
connects. Consider using stainless steel needle valves in clean service.
Connections should be NPS ¾ minimum, except for orifice flange connections,
which are NPS ½ in ANSI Class 300 through Class 600 flanges and should use
½-inch tubing.
Field instruments should be mounted in positions readily accessible from grade or
a platform. The 30-inch minimum clearance requirement should be maintained on
platforms.
Flow Instruments
Meter runs should be given as much straight pipe upstream as practicable. Minimum
lengths for various installations and services are reviewed in the Instrumentation
and Control Manual. The orifice should be located upstream of any associated
control valve and preferably be accessible from a platform if elevated.
Strainers should be installed upstream of all positive displacement meters—at a
distance of 10 pipe diameters in the case of turbine meters. The strainer should have
a valved blowdown connection and pressure gages to check efficiency. In services
subject to two-phase flow, vapor eliminators should also be installed in the line.
Refer to the Instrumentation and Control Manual.
Level Instruments
Level instruments are generally mounted directly on vessels and columns. When
supplementary instruments such as level gages and alarms are added the assemblies
are often mounted on a bridle. Bridles are used to minimize the number of connec-
tions on a vessel and provide increased mechanical strength. This is reviewed in
detail in the Instrumentation and Control Manual.
Typically, level controllers and gages on a vessel are independently mounted to
provide independent readings. However, when a horizontal vessel diameter exceeds
six feet, the recommended method of mounting is as shown in Figure 300-22. This
avoids excessively long individual connections. Level instruments should not share
common connections with other services, such as fill, drain or pumpout lines, where
flow can disturb readings.
Fig. 300-22 Level Instrument Mounting—Horizontal Vessels Exceeding Six Feet in Diameter
Gage glasses should have dedicated block valves and be fitted with vent and drain
valves to allow in-place rodding and cleaning of the glass. Refer to the Instrumenta-
tion and Control Manual for specific applications.
The ratio of displacement versus stress buildup depends on the flexibility of the
piping system. A flexible piping system has relatively free movement and little
expansion stress buildup. A rigid piping system has very little movement (displace-
ment) and high expansion stress buildup.
Unlike sustained stresses, expansion stresses are self-limiting; local yielding of the
pipe at points of high stress concentration decreases the stress and stops further
yielding. As a result of local yielding, a new equilibrium at the higher temperature
and lower expansion stress level is established. When the system cools down the
stresses reappear with an opposite sign and may again cause local yielding. A piping
system subjected to a temperature cycle will go through a range of stresses
commonly referred to as the displacement stress range.
Expansion stresses are usually attributable to thermal expansion and, typically, are
cyclical. Because they are almost always self-limiting, a single application of the
load does not produce a failure; failure is by fatigue after a (usually) high number of
load applications.
Fatigue failures begin as a small crack at a stress riser or material imperfection on
the inner or outer surface of the pipe. Poor or irregular welds are examples of stress
risers. Leakage will generally occur before catastrophic failure, although simulta-
neous corrosion and expansion stress cycling can lead to a very rapid failure. Brittle
materials are particularly susceptible to fatigue failure.
Flexibility Analysis
It is the usual practice to perform piping flexibility analysis for:
• NPS 3 and larger lines connected to rotating equipment
• Lines connected to reciprocating compressors
• Lines with temperatures of 600°F and higher
ANSI/ASME B31.3 requires no formal analysis for systems that (1) are duplicates
or replacements without significant change of systems with satisfactory service
records, (2) can be readily judged adequate by comparison with previously analyzed
systems, or (3) are of uniform size, have no more than two points of fixation, have
no intermediate restraints, and fall within the limitations of the following empirical
equation from ANSI/ASME B31.3:
DY/(L-U)2 ≤ 0.03
(Eq. 300-14)
where:
D = outside diameter of pipe, in.
Guides
A long pipe under axial compression is a weak column subject to buckling. To
prevent buckling, lateral restraint (a guide) is used. Guides should not be placed
near directional changes, where they would interfere with the flexibility of the
piping.
Anchors
Anchors are rigid devices that prevent translation and rotation of the pipe at one
point so that the pipe is fully fixed in all axes. A flanged connection of pipe to a
piece of equipment is an anchor. There are very few other anchor points used in
piping systems.
Stops
A stop prevents movement in the axial direction, but permits rotation of the pipe. In
most cases a stop also acts as a support. Stops are frequently, but mistakenly,
referred to as anchors. One needs to keep in mind the definition of anchors given
above.
After designing anchors and stops, and determining the reaction forces, the piping
designer should consult the structural designer about the adequacy of the pipeway
structure.
341 General
Small diameter piping within the Company is defined as NPS 1½ and smaller, and
large diameter piping as NPS 2 and larger. This is typical within the industry
although NPS 2 is sometimes considered small diameter piping.
Because of the difficulty and cost of properly butt welding small diameter pipe,
NPS 1½ and smaller piping is normally installed with threaded or socket weld
couplings, fittings, and valves. Unions are used instead of flanges to assemble and
disassemble the piping where the service or the piping classification allows.
With the exception of certain instrument piping and some vendor supplied auxiliary
piping on equipment, NPS ¾ pipe is the smallest recommended size. In the normal
course of operations and maintenance NPS ½ and smaller is considered too suscep-
tible to mechanical damage. Root connections are of special concern because of the
possible moments and stresses that can be imposed at the main pipe or equipment
tie-in. Some operating centers take exception to the NPS ¾ limitation in certain
applications. This is discussed in Sections 700 and 800.
Tubing is not recommended in place of small process piping. Tubing materials and
applications are discussed in Section 230.
Typical common small pipe services, with available references, are:
• Vents and drains. Standard Drawing GD-L31335, Section 320 of this manual
• Sample draws. Standard Form PIM-EF-403, Standard Drawings GA-L31652
and GB-J1223
• Steamout, pumpout, purge, and flush. Standard Drawing GD-L1012
• Steam tracing. In the Utilities Manual, Section 700, Standard Drawings
GD-L1066 and GF-L99888 and Standard Form UTL-EF-593
• Steam trap manifolds
• Condensate collection. In the Utilities Manual, Standard Drawing
GD-L99596 and Standard Form UTL-EF-302
• Solar thermal relief. Section 340 of this manual
• Utility stations. Standard Form UTL-EF-308, in the Utilities Manual
• Instrumentation. Instrumentation and Control Manual
• Equipment auxiliary piping. General Machinery Manual, API Standard 614
and the appropriate equipment manual
• Chemical injection systems
Seal Welding. The primary reason for seal welding valves and threaded joints is to
increase safety and mechanical strength. Stress concentration caused by exposed
thread runout notches is thereby eliminated. Seal welding also minimizes leakage
and accidental thread backoff. Seal welding is normally used in services where:
• The fluid is flammable (and the fire risk from leakage is high)
• The fluid is hazardous
• Vibration or thermal loads exist
Seal welding should cover all exposed threads with weld metal and should blend
into the pipe as smoothly as practicable (see Standard Drawing GD-L1057 for
details). Threaded joints to be seal welded must be made up dry, without thread
compound or Teflon tape, because these materials contaminate the weld and can
release toxic vapors.
Seal welding requirements vary in the Corporation Piping Specification. Low-pres-
sure water and air services do not require seal welding. In Pipe Classes that require
limited seal welding selected joints are seal welded, principally the pressure side of
the first valve off equipment or pipe headers. In Pipe Classes that require complete
seal welding, all joints (except plugs in valved vents and drains, and instrument and
tubing connections) are seal welded. See the Corporation Piping Specification.
Bridge Welding. In severe cyclic services the branch root connections should be
made with short nipples (but not all-thread nipples) and multiple weld passes built
up to the full hub diameter of the valve and for the full length of the nipple. For
bridge welding details refer to Standard Drawing GD-L1057. Consider the use of
top entry valves so repairs can be made without cutting the valve from the line.
Which applications require bridge welding versus seal welding should be given
some thought. Bridge welding should be considered for critical services only. The
additional field labor required is expensive. Also, special precautions may be neces-
sary to protect valves from heat while welding. This is described on Standard
Drawing GD-L1057.
Suggested applications for bridge welding of small root valves are:
• Systems with flange ratings above ANSI Class 900
• Steam and boiler feedwater service at 600 psig
• LPG and H2S services
• Vibrating service involving reciprocating and rotating equipment
Threaded Connections Versus Socket Welding. Threaded connections for
NPS 1½ and smaller pipe are usually less expensive than socket welded connec-
tions, but have the following disadvantages:
• Weakness resulting from the notch effect at the root of the thread which local-
izes the effect of imposed stresses, promoting fatigue failure
• The decrease in effective wall thickness where threads are cut
• Susceptibility to thread disengagement by expansion when exposed to fire
• Inability to properly seal weld joints once pipe dope or Teflon tape is used
Where exposed threads are not acceptable, joints should be socket welded or
threaded and seal welded. Both are considered the equivalent of butt welded or
flanged joints for fire safety. Economics should govern the choice between them.
Figure 300-23 shows comparative times to field fabricate and erect NPS 2 and
smaller pipe using various methods.
With socket welded construction, vents and drains should use screwed valves or
valves with one socket weld connection and one screwed connection.
All open ended connections to flammable fluid systems such as drains, vents,
unused instrument connections, etc., should be fitted with threaded solid bar stock
plugs of the same material as the connection. Bar stock plugs should have a shank
equal in length to at least twice their diameter to accommodate pipe wrenches (hex
head plugs will not withstand repeated use). Free machining steels (high lead or
high sulfur content) should not be used for bar stock plugs because they are subject
to corrosion and cannot be seal welded.
Flanges. Socket weld or butt weld flanges should be used for steam above 150 psig,
and LPG, hydrogen, or hazardous services where thermal cycling is anticipated. See
Section 250 of this manual for further discussion.
Unions. Unions should be specified with metal-to-metal seats. They are most
commonly used in low-pressure hydrocarbon and utility services to 150 psig.
The standards for malleable iron and carbon steel unions are ANSI B16.39 and MSS
SP83, respectively. These standards do not specify seat construction, seat dimen-
sions, or closure nut thread diameter. Each manufacturer sets his own dimensions
and thread type for the coupling nut. As a result, union parts from different manu-
facturers are not interchangeable and any replacements should be done on a unit
basis. Used union parts from the same manufacturer should not be reused without
lapping the seating surfaces. It is recommended that each operating center stan-
dardize on one manufacturer to avoid problems of mismatching or noninterchange-
able parts.
Because of their brittleness white or gray cast iron unions should not be used;
malleable or ductile cast iron should be specified. Forged carbon steel should be
used in all hydrocarbon services.
• Backfilling and compacting to prevent contact with any material that could
damage the coating
These concerns and appropriate procedures are discussed in the Pipeline Manual
and the Coatings Manual.
Cathodic Protection. Cathodic protection (CP) can be roughly defined as retarding
or preventing the corrosion of a metal by imposing an electrical current flowing to
the metal through an electrolyte. In the case of buried piping, the pipe is the metal
and the soil is the electrolyte.
The basic principle of cathodic protection is quite simple, but the applications can
be very complex. A thorough discussion of design and application is included in the
Corrosion Prevention Manual.
Cathodic protection is often used with coatings to protect piping. Regardless of the
care used in coating and installing buried lines there will often be small pinholes, or
“holidays,” in the coating. A cathodic protection system can protect against corro-
sion at these points and significantly extend the life of the piping.
Cathodic protection is applied to underground piping as a system. At every location
where cathodically protected pipe leaves the soil (or water) it must be electrically
isolated from the aboveground continuation of the line if the continuation is not part
of the CP system. This is done with an insulating flange kit (or insulating union on
small diameter pipe) that uses electrically insulating bolt sleeves, nut washers, and
sealing gasket in a conventional flange makeup. Figure 300-25.
Producing piping, cross country pipelines, and submarine piping are the principal
users of cathodic protection. It is also used to protect steel marine piling, offshore
drilling and producing structures, ship hull exteriors, and tanker interiors. With the
possible exception of protecting tank bottoms, cathodic protection is seldom used in
refineries.
Care must be taken when designing a CP system to protect coated piping. Exces-
sive current flow can result in cathodic disbondment of the coating from the metal
at points where the coating is damaged, resulting in further deterioration of the
coating. This phenomenon is discussed in the Coatings Manual and the Corrosion
Prevention Manual. Because of excessive power requirements and difficulty in
uniform distribution of protection, cathodic protection is rarely applied to bare
piping.
Casings. Pipe crossings beneath roads and railroad rights-of-way, in addition to
being coated, often must be sleeved in a casing. Casings are generally a local
requirement of the right-of-way owner or the governing jurisdictional body. The
design and installation of casings is discussed in API Recommended Practice 1102,
Recommended Practice for Liquid Petroleum Pipelines Crossing Railroads and
Highways, and in the Civil and Structural Manual and the Pipeline Manual.
LPG piping through brick or concrete walls and through earth fills, such as road
crossings and embankments, should be protected by oil-filled casings treated with
protective coatings. The oil-filled casing gives extra protection to the LPG line and
allows leakage to be detected by pressure gages on the casing before it reaches the
atmosphere.