GPI - Gestão de Projectos Informáticos

Time Management

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Time Management

Time management allows the project manager to:


• Coordinate allocated effort
• Terminate the project on time, as required by business
needs
• Guarantee return on investment within appropriate time
delay => reduction of benefits
balance finish date with the costs required to recover

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Detailed Planning

Activities planning principles

Adopt rolling wave planning


Involve in planning those who have execution responsibilities
Plan controllable activities

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Detailed Planning

Activities Planning Sequence


• Starts with the decomposition of WBS Work Packages
into activities required to achieve each Milestone
• Estimate the activities duration
• Define the sequence / dependencies between activities
• Identify the resources need to perform those activities
• Estimate each resource’ effort required

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

estimated effort (days FTE / person)


Duration =
# allocated resources

BUT ...
Attention has to be given to:

• Non working days (weekends, holidays)


• Vacations;
• Part time work
• Training, thickness, other reasons;
• External environment disturb (mails; meetings; …)
• Interpersonal relationship

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Working Days

Days per year 365

Week ends 104

Hollidays 9
Treated by project
Vacation 22 management
software
Working days (wd) 230

Part-time work ???

Buffer at the end of


Absences (training, thikness,…) 15 project (proportional)
Buffer by WP
Environment / relationships 0,1 a 0,2 * du (PT) (proportional)

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

ID Task Name Duration


December 2006 January 2007 February 2007 March 2007
23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02
0 Teste 68 d
1 A 34 d
2 PA1 18 d Work Packages
3 a11 5d
4 a12 4d Buffers
5 a13 6d
6 Buffer A1 3d
7 MA1 0d 22-12
8 PA2 16 d
9 a21 4d
10 a22 7d
11 a23 9d
12 Buffer A2 3d
13 MA2 0d 17-01
14 B 30 d
15 PB1 12 d
16 b11 4d
17 b12 6d
18 Buffer B1 2d
19 MB1 0d 02-02
20 PB2 18 d
21 b21 10 d
22 b22 15 d
23 Buffer B2 3d
24 MB2 0d 01-03
25 Buffer Projecto 4d
Project Buffer

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Plan with Networks


Use of a mathematics technique

Critical Path Method (CPM) or


Precedence Diagramming Method (PDM)

Program Evaluation and Review Technique – PERT

Usually not used to communicate the Plan

Network Types:
• Precedence network (activities on nodes)
• Activity-on-arrow network

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network

A D

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

End-to-Start or Finish-to-Start

A B

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 A 5d
2 B 3d

B can start after A finishes

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

Start-to-Start

Allowing paralelism
C
D

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M
5 C 5d
6 D 3d

D can’t start before C starts

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

Finish-to-Finish

Allowing paralelism
E
F

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M
9 E 5d
10 F 3d

F only can finish when E is finished

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

Start-to-Finish

G H

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M
13 G 5d
14 H 3d

H can’t finish until G is not initiated

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

lag

When a fixed waiting time between activities has to exist.


(for instance the time required to approve a document after it is availlable
for revision)
+ lag
A B
+2

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M
17 A 5d
18 B 3d

B may be innitiated 2 days after A is finished

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

lag (negative)

- lag
A B
-2

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M
21 A 5d
22 B 3d

B may be innitiated 2 days before A finishes

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on nodes network


Dependencies representation

lag (start-to-start)

+ lag
C
+2 D

ID Task Name Duration


Week -1 Week 1 Week 2 Week 3
M T W T F S S M T W T F S S M T W T F S S M
25 C 5d
26 D 3d

D may be innitiated 2 days after C start

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Activities on arrow netwoks

3
B dummy

A C D
1 2 4 5

Forces Finish-to-Start

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

es + d = ef

early start (es) duration (d) early finish (ef)

Activity name

late start (ls) slack (s) late finish (lf)

slack = lf - ef
lf - d = ls

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

early start (es) duration (d) early finish (ef)

Activity name

late start (ls) slack (s) late finish (lf)

early start
late finish
slack

activity

late start early finish

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

act dur dep lag ef = es + d es d ef


slack = ls - es desc
A 3 -
lf = ls + d ls slack lf
B 2 A

C 2 A -2

D 1 B +2
C 3 2 5
B +2
3 0 5
0 3 3 7 1 8
A D
0 0 3 7 0 8
-2 1 2 3
C
5 4 7
Maria do Rosário Bernardo
GPI - Gestão de Projectos Informáticos

•Forward Path

1.Activity ES = EF of the predecessor


activity
2.When there are several predecessors use
the max (EF of all predecessors)

ES D 10
Activiy
LS Slack LF 10 D 10+D
Activiy
LS Slack LF
ES D 8
Activiy
LS Slack LF

ES D EF
Activiy
3.Early Finish (EF) = ES + Duration LS Slack LF

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

•Backward Path

1.Start with the last activity


2.Follow the paths from the last activity until
ES D EF
the first one Activiy
3.Last activity : LF = EF LS Slack LF

4.LF = LS of the successor activity


5.If there are multiple successors use the min ES D EF
(LS of all predecessors) Activiy
6.LS = LF – Duration 8 Slack LF

ES D EF
Activiy
ES D EF
8-D Slack 8
Activiy
10 Slack LF
7.Slack = LF-EF = LS-ES
Maria do Rosário Bernardo 22
GPI - Gestão de Projectos Informáticos

Exercise 4 -1 5
B C

0 2 3
A G

2 10
D E

Duration ? +3
5
Critical path ? F
Consequences is D delays 2 days?
Consequences is C delays 2 days?
Consequences is F delays 2 days?
If A starts on 4-Oct : Estimated data and hour of conclusion ?
Maria do Rosário Bernardo