Time Management
Time Management
Detailed Planning
Detailed Planning
BUT ...
Attention has to be given to:
Working Days
Hollidays 9
Treated by project
Vacation 22 management
software
Working days (wd) 230
Network Types:
• Precedence network (activities on nodes)
• Activity-on-arrow network
A D
End-to-Start or Finish-to-Start
A B
Start-to-Start
Allowing paralelism
C
D
Finish-to-Finish
Allowing paralelism
E
F
Start-to-Finish
G H
lag
lag (negative)
- lag
A B
-2
lag (start-to-start)
+ lag
C
+2 D
3
B dummy
A C D
1 2 4 5
Forces Finish-to-Start
es + d = ef
Activity name
slack = lf - ef
lf - d = ls
Activity name
early start
late finish
slack
activity
C 2 A -2
D 1 B +2
C 3 2 5
B +2
3 0 5
0 3 3 7 1 8
A D
0 0 3 7 0 8
-2 1 2 3
C
5 4 7
Maria do Rosário Bernardo
GPI - Gestão de Projectos Informáticos
•Forward Path
ES D 10
Activiy
LS Slack LF 10 D 10+D
Activiy
LS Slack LF
ES D 8
Activiy
LS Slack LF
ES D EF
Activiy
3.Early Finish (EF) = ES + Duration LS Slack LF
•Backward Path
ES D EF
Activiy
ES D EF
8-D Slack 8
Activiy
10 Slack LF
7.Slack = LF-EF = LS-ES
Maria do Rosário Bernardo 22
GPI - Gestão de Projectos Informáticos
Exercise 4 -1 5
B C
0 2 3
A G
2 10
D E
Duration ? +3
5
Critical path ? F
Consequences is D delays 2 days?
Consequences is C delays 2 days?
Consequences is F delays 2 days?
If A starts on 4-Oct : Estimated data and hour of conclusion ?